Project Management Assignment 3: Unit Project Part B

Verified

Added on  2023/06/13

|29
|4746
|459
AI Summary
This article provides detailed information on Project Management Assignment 3: Unit Project Part B, including project activities, dependencies, resources required, budget, cost-benefit analysis, and more. The article also includes a table of contents, author note, and references. The subject is Project Management, and the course code and college/university are not mentioned.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
0
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Assignment 3: Unit project - Part B
Software Failures
Name of Student
Name of the University
Author Note

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Table of Contents
Project Activities.............................................................................................................................2
Activity List:................................................................................................................................2
Dependencies and Sequence of Above Activities...........................................................................4
Resources Required for each Activity.........................................................................................6
Duration of each activity...........................................................................................................11
Bar Chart....................................................................................................................................13
Critical Path...............................................................................................................................15
WBS...........................................................................................................................................17
Project Completion Date (Milestones and durations)................................................................17
Budget........................................................................................................................................18
Cost Benefit Analysis................................................................................................................20
Resource Sheet:.........................................................................................................................23
References......................................................................................................................................24
Document Page
2
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Project Activities
Activity List:
WBS Task Name Duration Start Finish
0
Essendon & Buckley Street level crossing
removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18
1.5
Milestone 1: Completion of project initiation
phase 0 days Fri 8/3/18 Fri 8/3/18
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18
2.5 Assessment of design options 26 days Thu 12/13/18 Thu 1/17/19
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19
2.7 Milestone 2: Completion of planning phase 0 days Wed 2/27/19 Wed 2/27/19
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19
Document Page
3
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.2 North west alliance project partner announced 39 days Mon 4/15/19 Thu 6/6/19
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19
3.5 Refinement of design including community inputs 50 days Tue 8/13/19 Mon 10/21/19
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19
3.7 Milestone 3 : Completion of procurement phase 0 days Wed 12/18/19 Wed 12/18/19
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1 On-going community consultation 32 days Thu 12/19/19 Fri 1/31/20
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20
4.4 Finalized design released to the community 90 days Wed 5/20/20 Wed 12/9/20
4.5
Contract awarded for Buckley street level crossing
removal project 156 days Wed 5/20/20 Thu 5/20/21
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21
4.10 Milestone 4: Completion of Construction phase 0 days Wed 10/20/21 Wed 10/20/21
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22
5.4 Milestone 4: Completion of project closure phase 0 days Wed 11/17/21 Wed 11/17/21

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Dependencies and Sequence of Above Activities
WBS Task Name Duration Start Finish Predecessors
0
Essendon & Buckley Street level
crossing removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18 2
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18 3
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18 3
1.5
Milestone 1: Completion of project
initiation phase 0 days Fri 8/3/18 Fri 8/3/18 5,4
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18 6
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18 8,6
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18 9
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18 10,9
2.5 Assessment of design options 26 days Thu 12/13/18 Thu 1/17/19 11
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19 12,11
2.7
Milestone 2: Completion of planning
phase 0 days Wed 2/27/19 Wed 2/27/19 13
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
Document Page
5
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19 14
3.2
North west alliance project partner
announced 39 days Mon 4/15/19 Thu 6/6/19 16,14
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20 17
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19 17
3.5
Refinement of design including
community inputs 50 days Tue 8/13/19 Mon 10/21/19 19
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19 20
3.7
Milestone 3 : Completion of procurement
phase 0 days Wed 12/18/19 Wed 12/18/19 21,20
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1 On-going community consultation 32 days Thu 12/19/19 Fri 1/31/20 22
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20 24,22
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20 25
4.4
Finalized design released to the
community 90 days Wed 5/20/20 Wed 12/9/20 26
4.5
Contract awarded for Buckley street level
crossing removal project 156 days Wed 5/20/20 Thu 5/20/21 26
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20 26
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21 27
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21 30
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21 31
4.10 Milestone 4: Completion of Construction 0 days Wed 10/20/21 Wed 10/20/21 32
Document Page
6
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
phase
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21 33
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21 35,33
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22 35
5.4
Milestone 4: Completion of project closure
phase 0 days Wed 11/17/21 Wed 11/17/21 35
Resources Required for each Activity
WBS Task Name Duration Start Finish Resource Names
0
Essendon & Buckley
Street level crossing
removal
985 days Wed 4/25/18 Tue 2/1/22
1
Initiation phase of the
project 73 days Wed 4/25/18 Fri 8/3/18
1.1
Identifying objectives of
the project 15 days Wed 4/25/18 Tue 5/15/18 Project manager
1.2
Undertaking feasibility
study 20 days Wed 5/16/18 Tue 6/12/18 Project manager
1.3
Establishing project
charter 16 days Fri 7/13/18 Fri 8/3/18
Project manager, Project
planner
1.4
Appointing team
members of the project 22 days Wed 6/13/18 Thu 7/12/18
Project manager, Project
planner

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
7
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
1.5
Milestone 1: Completion
of project initiation
phase
0 days Fri 8/3/18 Fri 8/3/18
2
Planning phase of the
project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18
Supervisor, Construction
manager
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18
Construction technician,
Contractor, Equipment cost[1]
2.3
Community information
sessions 25 days Wed 10/3/18 Tue 11/6/18
Construction manager,
Contractor
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18
Construction manager,
Contractor
2.5
Assessment of design
options 26 days Thu 12/13/18 Thu 1/17/19
Construction manager,
Contractor, Sub-contractor
2.6
Lowering Buckley street
under rail line 29 days Fri 1/18/19 Wed 2/27/19
Architect, Construction
manager, Construction
technician, Sub-contractor
2.7
Milestone 2: Completion
of planning phase 0 days Wed 2/27/19 Wed 2/27/19
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
3.1 Community input on 32 days Thu 2/28/19 Fri 4/12/19 Cost for removing level
Document Page
8
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
design elements
crossing[1], Supervisor,
Architect, Construction
technician, Equipment cost[1]
3.2
North west alliance
project partner
announced
39 days Mon 4/15/19 Thu 6/6/19
Supervisor, Architect,
Construction manager,
Contractor, Procurement
manager
3.3
Construction partner
announced 134 days Fri 6/7/19 Wed 10/7/20
Supervisor, Architect,
Construction technician,
Contractor, Procurement
manager
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19
Cost for removing level
crossing[1], Architect,
Construction technician,
Contractor
3.5
Refinement of design
including community
inputs
50 days Tue 8/13/19 Mon 10/21/19
Architect, Construction
technician, Contractor,
Financial manager,
Procurement manager
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19
Supervisor, Architect,
Equipment cost[1],
Procurement manager
Document Page
9
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.7
Milestone 3 :
Completion of
procurement phase
0 days Wed
12/18/19 Wed 12/18/19
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1
On-going community
consultation 32 days Thu 12/19/19 Fri 1/31/20
Supervisor, Architect,
Contractor, Procurement
manager, Sub-contractor
4.2
Construction
commences 34 days Mon 2/3/20 Thu 3/19/20
Cost for removing level
crossing[1], Project manager,
Architect, Construction
technician, Procurement
manager
4.3
Preparatory work
commenced 43 days Fri 3/20/20 Tue 5/19/20
Cost for removing level
crossing[1], Supervisor,
Architect, Construction
technician, Contractor,
Equipment cost[1], Sub-
contractor
4.4
Finalized design
released to the
community
90 days Wed 5/20/20 Wed 12/9/20
Supervisor, Architect,
Construction manager,
Construction technician,
Procurement manager
4.5 Contract awarded for 156 days Wed 5/20/20 Thu 5/20/21 Cost for removing level

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Buckley street level
crossing removal project
crossing[1], Project manager,
Architect, Construction
technician, Contractor, Sub-
contractor
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20
Cost for removing level
crossing[1], Architect,
Construction manager,
Construction technician,
Equipment cost[1]
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21
Cost for removing level
crossing[1], Project manager,
Supervisor, Architect,
Construction manager,
Construction technician, Sub-
contractor
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21
Cost for removing level
crossing[1], Project manager,
Architect, Construction
manager, Construction
technician, Contractor
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21 Architect, Construction
manager, Construction
technician, Contractor, Sub-
Document Page
11
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
contractor
4.10
Milestone 4: Completion
of Construction phase 0 days Wed
10/20/21 Wed 10/20/21
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21
Project manager, Project
planner
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21
Project manager, Project
planner
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22
Project manager, Project
planner
5.4
Milestone 4: Completion
of project closure phase 0 days Wed
11/17/21 Wed 11/17/21
Duration of each activity
WBS Task Name Duration Start Finish
0
Essendon & Buckley Street level crossing
removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18
1.5 Milestone 1: Completion of project initiation 0 days Fri 8/3/18 Fri 8/3/18
Document Page
12
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
phase
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18
2.5 Assessment of design options 26 days Thu 12/13/18 Thu 1/17/19
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19
2.7 Milestone 2: Completion of planning phase 0 days Wed 2/27/19 Wed 2/27/19
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19
3.2 North west alliance project partner announced 39 days Mon 4/15/19 Thu 6/6/19
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19
3.5 Refinement of design including community inputs 50 days Tue 8/13/19 Mon 10/21/19
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19
3.7 Milestone 3 : Completion of procurement phase 0 days Wed 12/18/19 Wed 12/18/19
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1 On-going community consultation 32 days Thu 12/19/19 Fri 1/31/20
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20
4.4 Finalized design released to the community 90 days Wed 5/20/20 Wed 12/9/20
4.5 Contract awarded for Buckley street level crossing 156 days Wed 5/20/20 Thu 5/20/21

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
13
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
removal project
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21
4.10 Milestone 4: Completion of Construction phase 0 days Wed 10/20/21 Wed 10/20/21
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22
5.4 Milestone 4: Completion of project closure phase 0 days Wed 11/17/21 Wed 11/17/21
Document Page
14
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Bar Chart
Document Page
15
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Figure 1: bar representation of the activities
(Source: Created by Author)

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
16
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Critical Path
Document Page
17
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Figure 2: Critical Path representation
(Source: Created by Author)
Document Page
18
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
WBS
Figure 3: WBS
(Source: Created by Author Using MS project and WBS Schedule Pro)
Project Completion Date (Milestones and durations)
WBS Task Name Duration Start Finish Cost
0
Essendon & Buckley Street
level crossing removal
Project
985 days Wed 4/25/18 Tue 2/1/22 $153,991,424.00
1 Initializing First phase of
the project 73 days Wed 4/25/18 Fri 8/3/18 $104,512.00
2 Second phase Planning of 148 days Mon 8/6/18 Wed 2/27/19 $15,763,440.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
19
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
the project
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20 $50,064,000.00
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21 $87,871,216.00
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22 $188,256.00
Budget
WBS Task Name Duration Start Finish Cost
0
Essendon & Buckley Street level
crossing removal 985 days Wed
4/25/18 Tue 2/1/22 $153,991,424.00
1 Initiation phase of the project 73 days Wed
4/25/18 Fri 8/3/18 $104,512.00
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18 $3,360.00
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18 $4,480.00
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18 $40,704.00
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18 $55,968.00
1.5
Milestone 1: Completion of project
initiation phase 0 days Fri 8/3/18 Fri 8/3/18 $0.00
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19 $15,763,440.00
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18 $82,720.00
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18 $15,086,400.00
Document Page
20
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18 $100,000.00
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18 $104,000.00
2.5 Assessment of design options 26 days Thu
12/13/18 Thu 1/17/19 $156,000.00
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19 $234,320.00
2.7
Milestone 2: Completion of planning
phase 0 days Wed 2/27/19 Wed 2/27/19 $0.00
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20 $50,064,000.00
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19 $24,197,120.00
3.2
North west alliance project partner
announced 39 days Mon 4/15/19 Thu 6/6/19 $380,640.00
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20 $443,520.00
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19 $9,300,800.00
3.5
Refinement of design including
community inputs 50 days Tue 8/13/19 Mon 10/21/19 $500,000.00
3.6 Finalizing design 42 days Tue
10/22/19 Wed 12/18/19 $15,241,920.00
3.7
Milestone 3 : Completion of procurement
phase 0 days Wed
12/18/19 Wed 12/18/19 $0.00
4 Construction phase 480 days Thu
12/19/19 Wed 10/20/21 $87,871,216.00
4.1 On-going community consultation 32 days Thu
12/19/19 Fri 1/31/20 $317,440.00
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20 $9,211,616.00
Document Page
21
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20 $24,443,760.00
4.4
Finalized design released to the
community 90 days Wed 5/20/20 Wed 12/9/20 $439,200.00
4.5
Contract awarded for Buckley street level
crossing removal project 156 days Wed 5/20/20 Thu 5/20/21 $9,448,448.00
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20 $24,346,560.00
4.7 Major works commence 48 days Thu
12/10/20 Mon 2/15/21 $9,490,752.00
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21 $9,507,840.00
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21 $665,600.00
4.10
Milestone 4: Completion of Construction
phase 0 days Wed
10/20/21 Wed 10/20/21 $0.00
5 Closure phase 74 days Thu
10/21/21 Tue 2/1/22 $188,256.00
5.1 Post-project review 20 days Thu
10/21/21 Wed 11/17/21 $50,880.00
5.2 Stakeholder-sign off 30 days Thu
11/18/21 Wed 12/29/21 $76,320.00
5.3 Documentation 24 days Thu
12/30/21 Tue 2/1/22 $61,056.00
5.4
Milestone 4: Completion of project
closure phase 0 days Wed
11/17/21 Wed 11/17/21 $0.00

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
22
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Cost Benefit Analysis
Input Values
SL. No Hardware $ 100,000,000.00
1 Software $ 10,000,000.00
2 Development team salaries $ 10,000,000.00
3 Training $ 10,000,000.00
Total Development Cost $ 130,000,000.00
4
5 Hardware $ 2,000,000.00
6 Software $ 3,000,000.00
7 Operational Labor $ 18,000,000.00
Total Operational Cost $ 23,000,000.00
8
9 Approximate salary savings $ 54,000,000.00
10 Reduced operating cost $ 60,000,000.00
Total Benefit $ 114,000,000.00
11
Discount Rate Used 6.00%
Net Present Value Calculation
Enter values for the cost-benefit analysis in the INPUT_VALUES worksheet
Year of
Project
0 1 2 3 4 5 TOTAL
S
$0.00 $
114,000,00
0.00
$
114,000,0
00.00
$
114,000,0
00.00
$
114,000,00
0.00
$
114,000,00
0.00
6.00% 1.0000 0.9434 0.8900 0.8396 0.7921 0.7473
$
114,000,
000.00
$0.00 $107,547,1
69.81
$101,459,
594.16
$95,716,5
98.27
$90,298,67
7.61
$85,187,43
1.71
$
23,000,0
Document Page
23
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
00.00
$
130,000,
000.00
$0.00 $
107,547,16
9.81
$
209,006,7
63.97
$
304,723,3
62.24
$
395,022,03
9.85
$
480,209,47
1.55
$
480,209,4
71.55
$
(130,000,
000.00)
$0.00 $
(23,000,00
0.00)
$
(23,000,00
0.00)
$
(23,000,0
00.00)
$
(23,000,00
0.00)
$
(23,000,000
.00)
1.0000 0.9434 0.8900 0.8396 0.7921 0.7473
$0.00 $
(21,698,11
3.21)
$
(20,469,91
8.12)
$
(19,311,2
43.51)
$
(18,218,15
4.25)
$
(17,186,937
.98)
$
(130,000,
000.00)
$
(151,698,1
13.21)
$
(172,168,0
31.33)
$
(191,479,
274.84)
$
(209,697,4
29.09)
$
(226,884,36
7.07)
$
(226,884,
367.07)
$
(130,000,
000.00)
$
85,849,056
.60
$
80,989,67
6.04
$
76,405,35
4.76
$
72,080,523
.35
$
68,000,493.
73
$
253,325,1
04.49
$
(130,000,
000.00)
$
(44,150,94
3.40)
$
36,838,73
2.65
$
113,244,0
87.40
$
185,324,61
0.76
$
253,325,10
4.49
1.1165
Break Even Chart
0 1 2 3 4 5 0
$0.00
$100,000,000.00
$200,000,000.00
$300,000,000.00
$400,000,000.00
$500,000,000.00
$600,000,000.00 NPV of all BENEFITS NPV of all COSTS
Year
Document Page
24
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Resource Sheet:
Unique
ID Resource Name Type Max.
Units Std. Rate Ovt. Rate Cost/Use Accrue At Base
Calendar
1 Project
manager Work 100% $28.00/hr $0.00/hr $0.00 Prorated Standard
2 Project planner Work 100% $290.00/hr $0.00/hr $0.00 Prorated Standard
3 Supervisor Work 100% $240.00/hr $0.00/hr $0.00 Prorated Standard
4 Contractor Work 100% $270.00/hr $0.00/hr $0.00 Prorated Standard
5 Architect Work 100% $260.00/hr $0.00/hr $0.00 Prorated Standard
6 Construction
technician Work 100% $270.00/hr $0.00/hr $0.00 Prorated Standard
7 Procurement
manager Work 100% $220.00/hr $0.00/hr $0.00 Prorated Standard
8 Construction
manager Work 100% $230.00/hr $0.00/hr $0.00 Prorated Standard
9 Sub-contractor Work 100% $250.00/hr $0.00/hr $0.00 Prorated Standard
10 Equipment cost Material $15,000,000.00 $0.00 Prorated
11
Cost for
removing level
crossing
Material $9,000,000.00 $0.00 Prorated
12 Financial
manager Work 100% $230.00/hr $0.00/hr $0.00 Prorated Standard

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
25
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
References
Binder, J. (2016). Global project management: communication, collaboration and management
across borders. Routledge.
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning
from and with each other. Routledge.
de Carvalho, M. M., Patah, L. A., & de Souza Bido, D. (2015). Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), 1509-1522.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Gido, J., Clements, J., & Clements, J. (2014). Successful project management. Nelson Education.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt
Assn.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Document Page
26
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
JOSEPH. PHILLIPS, P. M. P., CBAP, I., & PMP, C. (2018). PMP PROJECT MANAGEMENT
PROFESSIONAL STUDY GUIDE. McGraw-Hill Education.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Krajewski, L. J., Malhotra, M. K., & Ritzman, L. P. (2015). Operations management: processes
and supply chains. Pearson.
Leach, L. P. (2014). Critical chain project management. Artech House.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Meredith, J. R., Shafer, S. M., Mantel Jr, S. J., & Sutton, M. M. (2016). Project management in
practice. Wiley Global Education.
Document Page
27
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and
technology. Taylor & Francis.
Riol, H., & Thuillier, D. (2015). Project management for academic research projects: balancing
structure and flexibility. International Journal of Project Organisation and
Management, 7(3), 251-269.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Sears, S. K., Sears, G. A., Clough, R. H., Rounds, J. L., & Segner, R. O. (2015). Construction
project management. John Wiley & Sons.
Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on
project success and on the execution of business strategies. International Journal of
Project Management, 33(1), 53-66.
Snyder, C. S. (2014). A guide to the project management body of knowledge: PMBOK (®)
guide. Project Management Institute: Newtown Square, PA, USA.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
28
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D. (2015).
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
1382-1394
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.