PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Assignment 3: Unit project - Part B
Software Failures
Name of Student
Name of the University
Author Note
Project Management Assignment 3: Unit Project Part B_1
1
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Table of Contents
Project Activities.............................................................................................................................2
Activity List:................................................................................................................................2
Dependencies and Sequence of Above Activities...........................................................................4
Resources Required for each Activity.........................................................................................6
Duration of each activity...........................................................................................................11
Bar Chart....................................................................................................................................13
Critical Path...............................................................................................................................15
WBS...........................................................................................................................................17
Project Completion Date (Milestones and durations)................................................................17
Budget........................................................................................................................................18
Cost Benefit Analysis................................................................................................................20
Resource Sheet:.........................................................................................................................23
References......................................................................................................................................24
Project Management Assignment 3: Unit Project Part B_2
2
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Project Activities
Activity List:
WBS Task Name Duration Start Finish
0
Essendon & Buckley Street level crossing
removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18
1.5
Milestone 1: Completion of project initiation
phase 0 days Fri 8/3/18 Fri 8/3/18
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18
2.5 Assessment of design options 26 days Thu 12/13/18 Thu 1/17/19
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19
2.7 Milestone 2: Completion of planning phase 0 days Wed 2/27/19 Wed 2/27/19
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19
Project Management Assignment 3: Unit Project Part B_3
3
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.2 North west alliance project partner announced 39 days Mon 4/15/19 Thu 6/6/19
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19
3.5 Refinement of design including community inputs 50 days Tue 8/13/19 Mon 10/21/19
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19
3.7 Milestone 3 : Completion of procurement phase 0 days Wed 12/18/19 Wed 12/18/19
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1 On-going community consultation 32 days Thu 12/19/19 Fri 1/31/20
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20
4.4 Finalized design released to the community 90 days Wed 5/20/20 Wed 12/9/20
4.5
Contract awarded for Buckley street level crossing
removal project 156 days Wed 5/20/20 Thu 5/20/21
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21
4.10 Milestone 4: Completion of Construction phase 0 days Wed 10/20/21 Wed 10/20/21
5 Closure phase 74 days Thu 10/21/21 Tue 2/1/22
5.1 Post-project review 20 days Thu 10/21/21 Wed 11/17/21
5.2 Stakeholder-sign off 30 days Thu 11/18/21 Wed 12/29/21
5.3 Documentation 24 days Thu 12/30/21 Tue 2/1/22
5.4 Milestone 4: Completion of project closure phase 0 days Wed 11/17/21 Wed 11/17/21
Project Management Assignment 3: Unit Project Part B_4
4
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
Dependencies and Sequence of Above Activities
WBS Task Name Duration Start Finish Predecessors
0
Essendon & Buckley Street level
crossing removal 985 days Wed 4/25/18 Tue 2/1/22
1 Initiation phase of the project 73 days Wed 4/25/18 Fri 8/3/18
1.1 Identifying objectives of the project 15 days Wed 4/25/18 Tue 5/15/18
1.2 Undertaking feasibility study 20 days Wed 5/16/18 Tue 6/12/18 2
1.3 Establishing project charter 16 days Fri 7/13/18 Fri 8/3/18 3
1.4 Appointing team members of the project 22 days Wed 6/13/18 Thu 7/12/18 3
1.5
Milestone 1: Completion of project
initiation phase 0 days Fri 8/3/18 Fri 8/3/18 5,4
2 Planning phase of the project 148 days Mon 8/6/18 Wed 2/27/19
2.1 Site investigations 22 days Mon 8/6/18 Tue 9/4/18 6
2.2 Solution announced 20 days Wed 9/5/18 Tue 10/2/18 8,6
2.3 Community information sessions 25 days Wed 10/3/18 Tue 11/6/18 9
2.4 Trader consultation 26 days Wed 11/7/18 Wed 12/12/18 10,9
2.5 Assessment of design options 26 days Thu 12/13/18 Thu 1/17/19 11
2.6 Lowering Buckley street under rail line 29 days Fri 1/18/19 Wed 2/27/19 12,11
2.7
Milestone 2: Completion of planning
phase 0 days Wed 2/27/19 Wed 2/27/19 13
3 Procurement phase 420 days Thu 2/28/19 Wed 10/7/20
Project Management Assignment 3: Unit Project Part B_5
5
PROJECT MANAGEMENT: - ASSIGNMENT 3: UNIT PROJECT - PART B
3.1 Community input on design elements 32 days Thu 2/28/19 Fri 4/12/19 14
3.2
North west alliance project partner
announced 39 days Mon 4/15/19 Thu 6/6/19 16,14
3.3 Construction partner announced 134 days Fri 6/7/19 Wed 10/7/20 17
3.4 Community consultation 47 days Fri 6/7/19 Mon 8/12/19 17
3.5
Refinement of design including
community inputs 50 days Tue 8/13/19 Mon 10/21/19 19
3.6 Finalizing design 42 days Tue 10/22/19 Wed 12/18/19 20
3.7
Milestone 3 : Completion of procurement
phase 0 days Wed 12/18/19 Wed 12/18/19 21,20
4 Construction phase 480 days Thu 12/19/19 Wed 10/20/21
4.1 On-going community consultation 32 days Thu 12/19/19 Fri 1/31/20 22
4.2 Construction commences 34 days Mon 2/3/20 Thu 3/19/20 24,22
4.3 Preparatory work commenced 43 days Fri 3/20/20 Tue 5/19/20 25
4.4
Finalized design released to the
community 90 days Wed 5/20/20 Wed 12/9/20 26
4.5
Contract awarded for Buckley street level
crossing removal project 156 days Wed 5/20/20 Thu 5/20/21 26
4.6 Early works commence 102 days Wed 5/20/20 Thu 10/8/20 26
4.7 Major works commence 48 days Thu 12/10/20 Mon 2/15/21 27
4.8 Boom gates removed 112 days Tue 2/16/21 Wed 7/21/21 30
4.9 Finalizing landscapes 65 days Thu 7/22/21 Wed 10/20/21 31
4.10 Milestone 4: Completion of Construction 0 days Wed 10/20/21 Wed 10/20/21 32
Project Management Assignment 3: Unit Project Part B_6

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Essendon & Buckley Street Level Crossing Removal Project Scope Statement
|11
|1455
|267

Project Management of Customer Relationship Program
|12
|1962
|32

Project Management: Hucks Case Study
|29
|4856
|80

Gantt Chart of Software Training Program_modified | Desklib
|2
|579
|69

Project Management: Work Breakdown Structure, Network Diagram, Gantt Chart, Budget, Risk, Communication, Status Report, Reflection