This assignment analyzes the successful implementation of a cloud-based ERP system for the company CLAIMit. The analysis highlights the benefits of accessing the system via the cloud, which aids in managing operations and business functions effectively. The document emphasizes the importance of mitigating risks and challenges through appropriate strategies. It also stresses the critical need to address security concerns through robust measures to ensure project progress is not hampered.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Implementation of cloud based ERP system within a company named “CLAIMit”
Name of the Student
Name of the University
Author’s Note
Implementation of cloud based ERP system within a company named “CLAIMit”
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
PROJECT MANAGEMENT
Table of Contents
1. Project name................................................................................................................................2
2. Name of the organization.............................................................................................................2
3. Background..................................................................................................................................2
4. Project Scope...............................................................................................................................3
5. Date of status report.....................................................................................................................3
6. Project progress and performance...............................................................................................5
7. Issues............................................................................................................................................7
8. Budget Status...............................................................................................................................8
9. Planned deliverables and activities............................................................................................10
9.1 Deliverables.........................................................................................................................10
9.2 Activities..............................................................................................................................10
10. Network diagram and Gantt chart............................................................................................13
10.1 Network Diagram..............................................................................................................13
10.2 Gantt chart.........................................................................................................................14
11. Review of risks........................................................................................................................15
12. Project and Personal reflection................................................................................................17
Bibliography..................................................................................................................................19
PROJECT MANAGEMENT
Table of Contents
1. Project name................................................................................................................................2
2. Name of the organization.............................................................................................................2
3. Background..................................................................................................................................2
4. Project Scope...............................................................................................................................3
5. Date of status report.....................................................................................................................3
6. Project progress and performance...............................................................................................5
7. Issues............................................................................................................................................7
8. Budget Status...............................................................................................................................8
9. Planned deliverables and activities............................................................................................10
9.1 Deliverables.........................................................................................................................10
9.2 Activities..............................................................................................................................10
10. Network diagram and Gantt chart............................................................................................13
10.1 Network Diagram..............................................................................................................13
10.2 Gantt chart.........................................................................................................................14
11. Review of risks........................................................................................................................15
12. Project and Personal reflection................................................................................................17
Bibliography..................................................................................................................................19
2
PROJECT MANAGEMENT
1. Project name
The name of the project is “implementation of cloud based ERP system within a
company named CLAIMit.
2. Name of the organization
The name of the organization is CLAIMit, which is a restaurant and café deal sites that
generally helps in offering steep discounts at famous restaurants to various consumers who
generally purchase them in various form of electronic ClAIMit coupon. The main mission of the
company is to provide cafes as well as restaurants an online presence that they lack for
generating traffic and sales. It is identified that CLAIMit generally collaborates with businesses
to incentivize consumers for visiting as well as spending in store by providing proper attractive
discounts.
3. Background
The organization “CLAIMit” is one of the online site that is developed for serving as a
directory of cafes as well as restaurants in Malaysia. The company was founded in the year 2014
by CLAIMit Sdn Bhd. The organization officially began its operation after the first quarter of
2015. The organization serves its customers properly however due to very strong competition
from different existing deal sites, the company faces lot of issues as well as challenges in
competing with those sites and thus it decided to focus only on the beverage and food industry.
CLAIMit wants to expand its business within food and beverage industry but with the expansion
of the business, the company analyzes the need of cloud based ERP system for flexible access
PROJECT MANAGEMENT
1. Project name
The name of the project is “implementation of cloud based ERP system within a
company named CLAIMit.
2. Name of the organization
The name of the organization is CLAIMit, which is a restaurant and café deal sites that
generally helps in offering steep discounts at famous restaurants to various consumers who
generally purchase them in various form of electronic ClAIMit coupon. The main mission of the
company is to provide cafes as well as restaurants an online presence that they lack for
generating traffic and sales. It is identified that CLAIMit generally collaborates with businesses
to incentivize consumers for visiting as well as spending in store by providing proper attractive
discounts.
3. Background
The organization “CLAIMit” is one of the online site that is developed for serving as a
directory of cafes as well as restaurants in Malaysia. The company was founded in the year 2014
by CLAIMit Sdn Bhd. The organization officially began its operation after the first quarter of
2015. The organization serves its customers properly however due to very strong competition
from different existing deal sites, the company faces lot of issues as well as challenges in
competing with those sites and thus it decided to focus only on the beverage and food industry.
CLAIMit wants to expand its business within food and beverage industry but with the expansion
of the business, the company analyzes the need of cloud based ERP system for flexible access
3
PROJECT MANAGEMENT
and thus the higher authority of the organization decided to implement cloud based ERP system
within the organization.
4. Project Scope
The scope of the project is divided into in-scope as well as out-scope
In-scope: In-scope of the project is as follows:
Implementation of cloud based ERP system within the organization
Completing the project within the estimated time and budget
Checking infrastructure of the company
Migrating data
Transferring technology as well as knowledge
Out-scope: Out scope of the project are as follows:
Proper details of the suppliers are not provided
The project does not provide proper training facility to the employees
5. Date of status report
The date of creating the project status report is 20th April 2018. It is identified that the
status of the project is provided in the table below as per the date.
Task Name Duration % Complete
Implementation of cloud based ERP system
within a company named "CLAIMit"
129 days 55%
PROJECT MANAGEMENT
and thus the higher authority of the organization decided to implement cloud based ERP system
within the organization.
4. Project Scope
The scope of the project is divided into in-scope as well as out-scope
In-scope: In-scope of the project is as follows:
Implementation of cloud based ERP system within the organization
Completing the project within the estimated time and budget
Checking infrastructure of the company
Migrating data
Transferring technology as well as knowledge
Out-scope: Out scope of the project are as follows:
Proper details of the suppliers are not provided
The project does not provide proper training facility to the employees
5. Date of status report
The date of creating the project status report is 20th April 2018. It is identified that the
status of the project is provided in the table below as per the date.
Task Name Duration % Complete
Implementation of cloud based ERP system
within a company named "CLAIMit"
129 days 55%
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4
PROJECT MANAGEMENT
Initiation phase 13 days 100%
Developing business case 2 days 100%
Undertaking feasibility study 3 days 100%
Establishing project charter 2 days 100%
Appointing the project team members 3 days 100%
Arranging the requirements 3 days 100%
Milestone 1: Completion of initiation phase 0 days 100%
Planning phase 38 days 100%
Creating project plan 4 days 100%
Creating resource plan 5 days 100%
Creating financial plan 4 days 100%
Creating quality plan 5 days 100%
Creating risk plan 4 days 100%
Creating acceptance plan 5 days 100%
Creating communication plan 6 days 100%
Creating procurement plan 5 days 100%
Milestone 2: Completion of planning phase 0 days 100%
Execution phase 72 days 28%
Selection of an ERP system 8 days 100%
Definition of implementation phase 7 days 100%
Evaluating options 6 days 83%
Data migration 6 days 0%
Check infrastructure 7 days 0%
PROJECT MANAGEMENT
Initiation phase 13 days 100%
Developing business case 2 days 100%
Undertaking feasibility study 3 days 100%
Establishing project charter 2 days 100%
Appointing the project team members 3 days 100%
Arranging the requirements 3 days 100%
Milestone 1: Completion of initiation phase 0 days 100%
Planning phase 38 days 100%
Creating project plan 4 days 100%
Creating resource plan 5 days 100%
Creating financial plan 4 days 100%
Creating quality plan 5 days 100%
Creating risk plan 4 days 100%
Creating acceptance plan 5 days 100%
Creating communication plan 6 days 100%
Creating procurement plan 5 days 100%
Milestone 2: Completion of planning phase 0 days 100%
Execution phase 72 days 28%
Selection of an ERP system 8 days 100%
Definition of implementation phase 7 days 100%
Evaluating options 6 days 83%
Data migration 6 days 0%
Check infrastructure 7 days 0%
5
PROJECT MANAGEMENT
Customization 8 days 0%
Change management 9 days 0%
Technology and knowledge transfer 8 days 0%
Project management and testing 7 days 0%
On going support 6 days 0%
Milestone 3: Completion of execution phase 0 days 0%
Closure phase 6 days 0%
Post project review 3 days 0%
Stakeholder sign off 2 days 0%
Documentation 1 day 0%
6. Project progress and performance
The progress as well as performance of the project can be analyzed from the table that is
provided below:
Task Name % Complete
Implementation of cloud based ERP system within a
company named "CLAIMit"
55%
Initiation phase 100%
Developing business case 100%
Undertaking feasibility study 100%
Establishing project charter 100%
PROJECT MANAGEMENT
Customization 8 days 0%
Change management 9 days 0%
Technology and knowledge transfer 8 days 0%
Project management and testing 7 days 0%
On going support 6 days 0%
Milestone 3: Completion of execution phase 0 days 0%
Closure phase 6 days 0%
Post project review 3 days 0%
Stakeholder sign off 2 days 0%
Documentation 1 day 0%
6. Project progress and performance
The progress as well as performance of the project can be analyzed from the table that is
provided below:
Task Name % Complete
Implementation of cloud based ERP system within a
company named "CLAIMit"
55%
Initiation phase 100%
Developing business case 100%
Undertaking feasibility study 100%
Establishing project charter 100%
6
PROJECT MANAGEMENT
Appointing the project team members 100%
Arranging the requirements 100%
Milestone 1: Completion of initiation phase 100%
Planning phase 100%
Creating project plan 100%
Creating resource plan 100%
Creating financial plan 100%
Creating quality plan 100%
Creating risk plan 100%
Creating acceptance plan 100%
Creating communication plan 100%
Creating procurement plan 100%
Milestone 2: Completion of planning phase 100%
Execution phase 28%
Selection of an ERP system 100%
Definition of implementation phase 100%
Evaluating options 83%
Data migration 0%
Check infrastructure 0%
Customization 0%
Change management 0%
Technology and knowledge transfer 0%
Project management and testing 0%
PROJECT MANAGEMENT
Appointing the project team members 100%
Arranging the requirements 100%
Milestone 1: Completion of initiation phase 100%
Planning phase 100%
Creating project plan 100%
Creating resource plan 100%
Creating financial plan 100%
Creating quality plan 100%
Creating risk plan 100%
Creating acceptance plan 100%
Creating communication plan 100%
Creating procurement plan 100%
Milestone 2: Completion of planning phase 100%
Execution phase 28%
Selection of an ERP system 100%
Definition of implementation phase 100%
Evaluating options 83%
Data migration 0%
Check infrastructure 0%
Customization 0%
Change management 0%
Technology and knowledge transfer 0%
Project management and testing 0%
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7
PROJECT MANAGEMENT
On going support 0%
Milestone 3: Completion of execution phase 0%
Closure phase 0%
Post project review 0%
Stakeholder sign off 0%
Documentation 0%
7. Issues
The issues as well as challenges that the project faces are as follows:
Improper management: As the project manager of the organization are not experienced
therefore they faces lot of issues as well as challenges in managing the project. Therefore it is
very much necessary to hire experienced project manager in order to manage the project properly
so that entire project will be completed within estimated time and budget.
Security issues: The project faces number of security issues due to improper migration
of data as well as information. It is quite important to secure the data as well as information by
implementing proper risk management strategies.
Inappropriate estimation of budget: It is analyzed that the budget that is estimated for
project is not appropriate and thus the project faces financial issues. It is quite important to
estimate the budget of the project appropriately by analyzing the market properly.
Improper risk management: The risks that are associated with the project are not
managed properly by the organization and as a result the progress of the entire project gets
PROJECT MANAGEMENT
On going support 0%
Milestone 3: Completion of execution phase 0%
Closure phase 0%
Post project review 0%
Stakeholder sign off 0%
Documentation 0%
7. Issues
The issues as well as challenges that the project faces are as follows:
Improper management: As the project manager of the organization are not experienced
therefore they faces lot of issues as well as challenges in managing the project. Therefore it is
very much necessary to hire experienced project manager in order to manage the project properly
so that entire project will be completed within estimated time and budget.
Security issues: The project faces number of security issues due to improper migration
of data as well as information. It is quite important to secure the data as well as information by
implementing proper risk management strategies.
Inappropriate estimation of budget: It is analyzed that the budget that is estimated for
project is not appropriate and thus the project faces financial issues. It is quite important to
estimate the budget of the project appropriately by analyzing the market properly.
Improper risk management: The risks that are associated with the project are not
managed properly by the organization and as a result the progress of the entire project gets
8
PROJECT MANAGEMENT
obstructed. Therefore it is quite important to manage the risks that are associated with the
project.
Inappropriate communication: Due to improper communication between team
members, it is quite difficult to complete the entire project successfully within estimated time
and budget. It is quite important to communicate properly about the project needs with the team
members.
8. Budget Status
The budget status of the project is provided in the table below:
Task Name Duration Start Finish Cost
Implementation of cloud
based ERP system within a
company named "CLAIMit"
129 days Fri 1/12/18 Wed 7/11/18 $60,080.00
Initiation phase 13 days Fri 1/12/18 Tue 1/30/18 $6,520.00
Developing business case 2 days Fri 1/12/18 Mon 1/15/18 $640.00
Undertaking feasibility
study
3 days Tue 1/16/18 Thu 1/18/18 $1,560.00
Establishing project charter 2 days Fri 1/19/18 Mon 1/22/18 $1,200.00
Appointing the project
team members
3 days Tue 1/23/18 Thu 1/25/18 $1,560.00
Arranging the requirements 3 days Fri 1/26/18 Tue 1/30/18 $1,560.00
Milestone 1: Completion of 0 days Tue 1/30/18 Tue 1/30/18 $0.00
PROJECT MANAGEMENT
obstructed. Therefore it is quite important to manage the risks that are associated with the
project.
Inappropriate communication: Due to improper communication between team
members, it is quite difficult to complete the entire project successfully within estimated time
and budget. It is quite important to communicate properly about the project needs with the team
members.
8. Budget Status
The budget status of the project is provided in the table below:
Task Name Duration Start Finish Cost
Implementation of cloud
based ERP system within a
company named "CLAIMit"
129 days Fri 1/12/18 Wed 7/11/18 $60,080.00
Initiation phase 13 days Fri 1/12/18 Tue 1/30/18 $6,520.00
Developing business case 2 days Fri 1/12/18 Mon 1/15/18 $640.00
Undertaking feasibility
study
3 days Tue 1/16/18 Thu 1/18/18 $1,560.00
Establishing project charter 2 days Fri 1/19/18 Mon 1/22/18 $1,200.00
Appointing the project
team members
3 days Tue 1/23/18 Thu 1/25/18 $1,560.00
Arranging the requirements 3 days Fri 1/26/18 Tue 1/30/18 $1,560.00
Milestone 1: Completion of 0 days Tue 1/30/18 Tue 1/30/18 $0.00
9
PROJECT MANAGEMENT
initiation phase
Planning phase 38 days Wed 1/31/18 Fri 3/23/18 $15,600.00
Creating project plan 4 days Wed 1/31/18 Mon 2/5/18 $2,400.00
Creating resource plan 5 days Tue 2/6/18 Mon 2/12/18 $1,200.00
Creating financial plan 4 days Tue 2/13/18 Fri 2/16/18 $960.00
Creating quality plan 5 days Mon 2/19/18 Fri 2/23/18 $2,400.00
Creating risk plan 4 days Mon 2/26/18 Thu 3/1/18 $960.00
Creating acceptance plan 5 days Fri 3/2/18 Thu 3/8/18 $3,000.00
Creating communication
plan
6 days Fri 3/9/18 Fri 3/16/18 $1,680.00
Creating procurement plan 5 days Mon 3/19/18 Fri 3/23/18 $3,000.00
Milestone 2: Completion of
planning phase
0 days Fri 3/23/18 Fri 3/23/18 $0.00
Execution phase 72 days Mon 3/26/18 Tue 7/3/18 $36,120.00
Selection of an ERP system 8 days Mon 3/26/18 Wed 4/4/18 $1,920.00
Definition of
implementation phase
7 days Thu 4/5/18 Fri 4/13/18 $3,640.00
Evaluating options 6 days Mon 4/16/18 Mon 4/23/18 $2,640.00
Data migration 6 days Tue 4/24/18 Tue 5/1/18 $2,640.00
Check infrastructure 7 days Wed 5/2/18 Thu 5/10/18 $5,320.00
Customization 8 days Fri 5/11/18 Tue 5/22/18 $4,160.00
Change management 9 days Wed 5/23/18 Mon 6/4/18 $4,320.00
PROJECT MANAGEMENT
initiation phase
Planning phase 38 days Wed 1/31/18 Fri 3/23/18 $15,600.00
Creating project plan 4 days Wed 1/31/18 Mon 2/5/18 $2,400.00
Creating resource plan 5 days Tue 2/6/18 Mon 2/12/18 $1,200.00
Creating financial plan 4 days Tue 2/13/18 Fri 2/16/18 $960.00
Creating quality plan 5 days Mon 2/19/18 Fri 2/23/18 $2,400.00
Creating risk plan 4 days Mon 2/26/18 Thu 3/1/18 $960.00
Creating acceptance plan 5 days Fri 3/2/18 Thu 3/8/18 $3,000.00
Creating communication
plan
6 days Fri 3/9/18 Fri 3/16/18 $1,680.00
Creating procurement plan 5 days Mon 3/19/18 Fri 3/23/18 $3,000.00
Milestone 2: Completion of
planning phase
0 days Fri 3/23/18 Fri 3/23/18 $0.00
Execution phase 72 days Mon 3/26/18 Tue 7/3/18 $36,120.00
Selection of an ERP system 8 days Mon 3/26/18 Wed 4/4/18 $1,920.00
Definition of
implementation phase
7 days Thu 4/5/18 Fri 4/13/18 $3,640.00
Evaluating options 6 days Mon 4/16/18 Mon 4/23/18 $2,640.00
Data migration 6 days Tue 4/24/18 Tue 5/1/18 $2,640.00
Check infrastructure 7 days Wed 5/2/18 Thu 5/10/18 $5,320.00
Customization 8 days Fri 5/11/18 Tue 5/22/18 $4,160.00
Change management 9 days Wed 5/23/18 Mon 6/4/18 $4,320.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10
PROJECT MANAGEMENT
Technology and knowledge
transfer
8 days Tue 6/5/18 Thu 6/14/18 $3,840.00
Project management and
testing
7 days Fri 6/15/18 Mon 6/25/18 $3,080.00
On going support 6 days Tue 6/26/18 Tue 7/3/18 $4,560.00
Milestone 3: Completion of
execution phase
0 days Tue 7/3/18 Tue 7/3/18 $0.00
Closure phase 6 days Wed 7/4/18 Wed 7/11/18 $1,840.00
Post project review 3 days Wed 7/4/18 Fri 7/6/18 $960.00
Stakeholder sign off 2 days Mon 7/9/18 Tue 7/10/18 $560.00
Documentation 1 day Wed 7/11/18 Wed 7/11/18 $320.00
9. Planned deliverables and activities
9.1 Deliverables
The deliverables of the project are as follows:
Implementation of cloud based ERP system
Migration of data
Checking the infrastructure of the organization
Customization
Transferring technology and knowledge transfer
Testing and project management
PROJECT MANAGEMENT
Technology and knowledge
transfer
8 days Tue 6/5/18 Thu 6/14/18 $3,840.00
Project management and
testing
7 days Fri 6/15/18 Mon 6/25/18 $3,080.00
On going support 6 days Tue 6/26/18 Tue 7/3/18 $4,560.00
Milestone 3: Completion of
execution phase
0 days Tue 7/3/18 Tue 7/3/18 $0.00
Closure phase 6 days Wed 7/4/18 Wed 7/11/18 $1,840.00
Post project review 3 days Wed 7/4/18 Fri 7/6/18 $960.00
Stakeholder sign off 2 days Mon 7/9/18 Tue 7/10/18 $560.00
Documentation 1 day Wed 7/11/18 Wed 7/11/18 $320.00
9. Planned deliverables and activities
9.1 Deliverables
The deliverables of the project are as follows:
Implementation of cloud based ERP system
Migration of data
Checking the infrastructure of the organization
Customization
Transferring technology and knowledge transfer
Testing and project management
11
PROJECT MANAGEMENT
9.2 Activities
The activities of the project are provided in the table below:
Task Name
Implementation of cloud based ERP system within a company named "CLAIMit"
Initiation phase
Developing business case
Undertaking feasibility study
Establishing project charter
Appointing the project team members
Arranging the requirements
Milestone 1: Completion of initiation phase
Planning phase
Creating project plan
Creating resource plan
Creating financial plan
Creating quality plan
Creating risk plan
Creating acceptance plan
Creating communication plan
Creating procurement plan
Milestone 2: Completion of planning phase
PROJECT MANAGEMENT
9.2 Activities
The activities of the project are provided in the table below:
Task Name
Implementation of cloud based ERP system within a company named "CLAIMit"
Initiation phase
Developing business case
Undertaking feasibility study
Establishing project charter
Appointing the project team members
Arranging the requirements
Milestone 1: Completion of initiation phase
Planning phase
Creating project plan
Creating resource plan
Creating financial plan
Creating quality plan
Creating risk plan
Creating acceptance plan
Creating communication plan
Creating procurement plan
Milestone 2: Completion of planning phase
12
PROJECT MANAGEMENT
Execution phase
Selection of an ERP system
Definition of implementation phase
Evaluating options
Data migration
Check infrastructure
Customization
Change management
Technology and knowledge transfer
Project management and testing
Ongoing support
Milestone 3: Completion of execution phase
Closure phase
Post project review
Stakeholder sign off
Documentation
PROJECT MANAGEMENT
Execution phase
Selection of an ERP system
Definition of implementation phase
Evaluating options
Data migration
Check infrastructure
Customization
Change management
Technology and knowledge transfer
Project management and testing
Ongoing support
Milestone 3: Completion of execution phase
Closure phase
Post project review
Stakeholder sign off
Documentation
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13
PROJECT MANAGEMENT
10. Network diagram and Gantt chart
10.1 Network Diagram
Figure 1: Network Diagram
(Source: Created by Author)
PROJECT MANAGEMENT
10. Network diagram and Gantt chart
10.1 Network Diagram
Figure 1: Network Diagram
(Source: Created by Author)
14
PROJECT MANAGEMENT
10.2 Gantt chart
Figure 2: Gantt chart
(Source: Created by Author)
PROJECT MANAGEMENT
10.2 Gantt chart
Figure 2: Gantt chart
(Source: Created by Author)
15
PROJECT MANAGEMENT
11. Review of risks
Risks Description Impact Probability Mitigation
measures
Important
estimation of
budget
Due to improper
budget
estimation, the
project faces
difficulty in
completing the
project properly
within the
estimated time
and budget.
High High The budget of
the project must
be estimated
properly by
analyzing the
market so that
proper budget
estimation for
the project will
be done.
Security issues The project
faces lot of
security issues
due to migration
of data.
High Medium Proper risk
mitigation
strategies must
be implemented
in order to
resolve the
security risks
that are
associated with
PROJECT MANAGEMENT
11. Review of risks
Risks Description Impact Probability Mitigation
measures
Important
estimation of
budget
Due to improper
budget
estimation, the
project faces
difficulty in
completing the
project properly
within the
estimated time
and budget.
High High The budget of
the project must
be estimated
properly by
analyzing the
market so that
proper budget
estimation for
the project will
be done.
Security issues The project
faces lot of
security issues
due to migration
of data.
High Medium Proper risk
mitigation
strategies must
be implemented
in order to
resolve the
security risks
that are
associated with
1 out of 16
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.