Project Management and Leadership Behavior

Verified

Added on  2020/05/16

|14
|2554
|422
AI Summary
This assignment examines the essential characteristics that project managers should possess to ensure successful project completion. It emphasizes the importance of specific project management practices aligned with the Project Management Body of Knowledge (PMBOK) framework. Furthermore, the paper highlights crucial leadership behaviors exhibited by effective project managers, contributing to positive project results.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Project Plan: Fit out of a medium-rise office building in a Sydney suburb
Name of the Student
Name of the University
Author’s Note

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Executive Summary
The project mainly reflects on the Vella IT office Fitout for undertaking the fitout of the building
in a Sydney suburb. It is identified that the project manager Tony Faultier left the job abruptly
and as a result the company hires a new project manager for completing the project on time. It is
identified that the report summarizes the current status of the project including Cost variance as
well as schedule variance. Proper overview of leadership behavior is elaborated for utilizing it
within the project. Furthermore, the paper illustrates overview of the existing team environment
with proper recommendations for making changes within the project.
Document Page
Table of Contents
Introduction......................................................................................................................................4
1.0 Current status of the project.......................................................................................................5
2.0 List of additional information the new project manager needs to source................................11
3.0 Overview of leadership behavior on the project......................................................................11
4.0 Overview of existing team environment and recommendations.............................................12
Conclusion.....................................................................................................................................13
Bibliography..................................................................................................................................14
Document Page
Introduction
The project plan is based on fitout of a medium-rise office building in Sydney suburb.
The previous project manager of this project plan was Tony Faultier who left the company
abruptly and is moving overseas. Therefore, a new project manager is assigned for the project
who communicated with the stakeholders to know about the project progress and its current
status. The total fitout budget is $1.2M and it is estimated that the entire project of fitout will be
completed within the duration of 4 months. The success of this fitout project needs to be
determined by the management by utilizing three components which includes design, budget as
well as time.
The paper mainly elaborates current status of the project which including both Cost
variance and Schedule variance. It is identified that the paper also highlights the importance of
leadership behavior in the project. Additionally, an overview about the existing team
environment with proper recommendations for changes within work processes as well as policies
for establishing proper cooperative environment is elaborated.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1.0 Current status of the project
WBS Task Name Duration Resource Names Cost
% Work
Complete
Actual Duration Actual Cost
Schedule
variance
Cost variance
0
Fitout of medium-rise
office building in a Sydney
suburb
87.44 days $1,200,000.00 37% 32.81 days $484,085.02
1 Start of the project plan 0 days $0.00 0% 0 days $0.00
2 Project plan 18 days $120,800.00 48% 6.64 days $58,400.00
2.1
Development of project
plan
2 days
Project Manager, Project Sponsor,
Structural Engineer, Architect,
Civil Engineer, Designer
$30,400.00 100% 2 days $30,400.00
0 day $ 0
2.2
Appointment of
architect
7.27 days
Project Manager, Civil Engineer,
Designer, Project Sponsor
$73,600.00 14% 2 days $11,200.00
5.27 days $ 62400
Document Page
2.3 Schematic design 1 day
Architect, Civil Engineer, Project
Manager, Designer, Developer,
Electrician
$16,800.00 100% 1 day $16,800.00
0 day $ 0
2.4 Consultant of proposals 6 days $0.00 0% 1 day $0.00 5 days $ 0
3
Design and
documentation
87.44 days $798,800.00 48% 56.49 days $425,685.02
3.1 Documentation of tender 2 days
Project Manager, Project Sponsor,
Designer, Developer, Electrician,
Architect, Civil Engineer, Site
investigator, Structural Engineer
$19,200.00 100% 2 days $19,200.00
0 day $ 0
3.2 Submit documentation
for approval
1 day Civil Engineer, Project Manager,
Project Sponsor, Architect,
Designer, Developer, Electrician,
Site investigator, Structural
$15,200.00 100% 1 day $15,200.00 0 day $ 0
Document Page
Engineer
3.3 Services design 2 days
Architect, Civil Engineer, Designer,
Project Manager, Developer,
Electrician, Project Sponsor, Site
investigator, Structural Engineer
$75,258.00 100% 2 days $75,258.00
0 day $ 0
3.4
Completion of
documentation
2 days
Project Manager, Project Sponsor,
Architect, Civil Engineer, Designer,
Developer
$26,414.00 100% 2 days $26,414.00
0 day $ 0
3.5 Ground floor 2.5 days $51,920.00 75% 2.11 days $39,874.80
3.5.1
Adding of furniture,
plumbing, electrical works
and data and telecom
infrastructure
2 days
Architect, Civil Engineer, Designer,
Structural Engineer, Developer,
Electrician, Project Manager,
Project Sponsor
$51,920.00 75% 1.69 days $39,874.80
0.31 day $ 12046
3.6 First floor 68.85 days $22,700.00 25% 5.46 days $5,616.67

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
3.6.1
Adding of furniture,
plumbing, electrical works
and data and telecom
infrastructure
2.63 days
Architect, Civil Engineer, Designer,
Project Manager, Site investigator,
Structural Engineer
$22,700.00 25% 0.21 days $5,616.67
2.42 days $ 17083.33
3.7 Second floor 40.27 days $260,508.00 25% 13.31 days $67,721.56
3.7.1
Adding of furniture,
plumbing, electrical works
and data and telecom
infrastructure
9 days
Designer, Project Manager,
Structural Engineer, Architect,
Civil Engineer, Developer,
Electrician, Project Sponsor, Site
investigator
$260,508.00 25% 2.98 days $67,721.56
6.02 days $ 192787
3.8 Top floor 14 days $327,600.00 50% 10.5 days $176,400.00
Document Page
3.8.1
Adding of furniture,
plumbing, electrical works
and data and telecom
infrastructure
14 days
Architect, Civil Engineer, Designer,
Developer, Electrician, Project
Manager, Project Sponsor, Site
investigator, Structural Engineer
$327,600.00 50% 10.5 days $176,400.00
3.5 days $ 151200
4 Construction phase 19.71 days $220,400.00 0% 0 days $0.00
4.1 Building owner approval 2.71 days Architect, Civil Engineer, Designer $28,000.00 0% 0 days $0.00 2.71 days $28,000.00
4.2 Procurement 1.5 days
Civil Engineer, Designer, Project
Manager, Site investigator,
Developer, Electrician, Project
Sponsor
$30,000.00 0% 0 days $0.00
1.5 days $30,000.00
4.3 Head contract 7 days
Architect, Civil Engineer, Site
investigator, Structural Engineer
$104,000.00 0% 0 days $0.00
7 days $104,000.00
4.4 Furniture installation 1 day Architect, Civil Engineer, Designer $16,800.00 0% 0 days $0.00 1 day $16,800.00
4.5 Practical completion 2 days Civil Engineer, Designer, Site $41,600.00 0% 0 days $0.00 2 days $41,600.00
Document Page
investigator, Structural Engineer
5 Project closure phase 21 days $60,000.00 0% 0 days $0.00
5.1
Draft of the project
report
3.5 days
Civil Engineer, Project Manager,
Project Sponsor
$20,800.00 0% 0 days $0.00
3.5 days $20,800.00
5.2 Final project report 7 days Project Manager $39,200.00 0% 0 days $0.00 7 days $39,200.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
2.0 List of additional information the new project manager needs to source
The list of additional information about the project that the new project manager need to
source in order to produce proper detailed status of the project are elaborated below:
Information about project risk: It is quite necessary for the new project manager to
know about the risks that are associated with the project. It is identified that due to proper
understanding of the project they can easily implement proper steps as well as strategies for
resolving project issues and challenges.
Limitations of the project: The project limitations must be known to the new project
managers so that while implementing project strategies for success they should avoid steps that
will obstruct the success of the project. Proper information about limitations allows them to
develop project in such a way that the project will become successful.
Information about project goal: Proper information about the project goal is necessary
for the new project managers as depending on the project goals they can progress with the
project. It is quite important to complete the project as per its goals and objectives.
3.0 Overview of leadership behavior on the project
As per the organizational zoo model, it is identified that Tony Faultier is a poor leader.
According to the model, a real leader is a person who has number of willing followers who
generally want to help them as they are generally get inspired by them and respect them as a
person. However, it is analyzed that Tony faultier is a very much belligerent and he is a person
whom the team members see as a person who is very much lazy impatient as well as intolerant to
Document Page
others. He was very much autocratic and was always unwilling to listen about the advice of the
team members. Further, the model elaborates that for becoming a leader, it is necessary to have
proper performance so that the stewardship as well as demonstrated actions generally serve
others effectively. However, it is identified that Tony did not perform effectively for managing
the issues that generally occurs within the project. In addition to this Tony faultier also does not
arrange proper training method for the staffs of the organization.
It is identified that the company must prefer proper leadership behavior for the
recruitment of the project manager and the recommendations for the targeted behavior include:
Demonstration of drive for results: The project managers must have effective
leadership characteristic that generally insists them to achieve proper project results.
Demanding truth: It is very much necessary for the project managers to know the real
issue or risk that is mainly associated with the project in order to make proper project related
decisions. It is identified that effective project managers requires demanding for the truth from
the project team members so that they can able to minimize issues. It is analyzed that hiding or
ignoring issues by the project manager will obstruct the success of the project.
Demonstrating courage: The project managers must have courage to communicate
properly with the team members so that the project can perform well with the support of the
project team members.
4.0 Overview of existing team environment and recommendations
It is identified that existing team environment of the company is not proper as the team
members does not have proper communication with the project managers and others for
Document Page
discussing on the project. The risks that are associated with the project are only known to few
team members which helps in reflecting that they does not communicate properly among each
other. The project manager is autocratic and the views of the team members are not listed by
him. Additionally the project manager is very much belligerent as well as bullying which
highlights that is very much necessary to improve the existing team environment of the
company.
The recommendations include:
Proper communication: It is quite necessary to communicate with the team members of
the project effectively. Proper communication with the team members of the project helps in
resolving issues as well as challenges that are mainly associated with the project.
Clarification of roles: Knowing everyone‘s role is also considered as one of the
important step of building proper team environment as clarification of roles assists in creating
flexibility as well as efficiency within the project work.
Trusting team members: In order to build proper team environment, it is very much
necessary to trust the team members of the project. It is necessary to assume that the team
members are responsible as well as competent towards work.
Conclusion
It can be concluded that the new project managers must be hired on the basis of certain
characteristics so that the entire project of the organization can be easily managed. It is necessary
to have certain characteristics among the project managers so that the project will be successfully

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
completed. The paper also highlights some of the leadership behavior that is also necessary for
the project managers in order to achieve positive outcome within the project.
Bibliography
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Snyder, C.S., 2014. A guide to the project management body of knowledge: PMBOK (®)
guide. Project Management Institute: Newtown Square, PA, USA.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on project
success and on the execution of business strategies. International Journal of Project
Management, 33(1), pp.53-66.