Ticket Generation System for Riverina Show
VerifiedAdded on 2020/05/28
|11
|1735
|92
AI Summary
The assignment describes the development of a ticket generation system for the Riverina Agriculture and Lifestyle Show. The project emphasizes the use of agile project management methodologies to ensure efficient and successful completion within a 5-month timeframe and budget. Key aspects include cost estimation, resource allocation, client requirement fulfillment, project planning, and documentation. The project aims to streamline ticket generation, making it faster and more affordable for the Riverina Agriculture and Lifestyle Show.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT
Table of Contents
Part 1: MOV Values........................................................................................................................2
Part 2: Scope Management Plan......................................................................................................4
Part 3: Project Schedule...................................................................................................................7
Part 4: Project Risk Analysis...........................................................................................................8
Part 5: Quality Management Plan....................................................................................................8
Part 6: Project Closure and Evaluation............................................................................................8
Bibliography..................................................................................................................................11
Table of Contents
Part 1: MOV Values........................................................................................................................2
Part 2: Scope Management Plan......................................................................................................4
Part 3: Project Schedule...................................................................................................................7
Part 4: Project Risk Analysis...........................................................................................................8
Part 5: Quality Management Plan....................................................................................................8
Part 6: Project Closure and Evaluation............................................................................................8
Bibliography..................................................................................................................................11
2PROJECT MANAGEMENT
Part 1: MOV Values
Ranking: The IT and software development projects are more likely to form the use of the
technological aspect as the most impactful factor that is crucial for the project. The development
and installation of RALS ticketing system project involves the impact on the project financially,
operational, strategically, customer based, and social grounds. These factors have been
highlighted below,
Factor Description Ran
k
Financially The project of development and installation of RALS ticketing system
is largely dependent on the project budget. The impact on the project
resources would cause large scale modification on the operations of the
project.
1st
Operational The project of development and installation of RALS ticketing system
involves a series of technology related activities that would combine
for forming the final project deliverable.
2nd
Strategicall
y
The project of development and installation of RALS ticketing system
would comprise of developing project plan strategically so that the IT
and project management concepts can be aligned successfully.
3rd
Customer
Based
The project of development and installation of RALS ticketing system
is customer based and would comprise of forming the improved
4th
Part 1: MOV Values
Ranking: The IT and software development projects are more likely to form the use of the
technological aspect as the most impactful factor that is crucial for the project. The development
and installation of RALS ticketing system project involves the impact on the project financially,
operational, strategically, customer based, and social grounds. These factors have been
highlighted below,
Factor Description Ran
k
Financially The project of development and installation of RALS ticketing system
is largely dependent on the project budget. The impact on the project
resources would cause large scale modification on the operations of the
project.
1st
Operational The project of development and installation of RALS ticketing system
involves a series of technology related activities that would combine
for forming the final project deliverable.
2nd
Strategicall
y
The project of development and installation of RALS ticketing system
would comprise of developing project plan strategically so that the IT
and project management concepts can be aligned successfully.
3rd
Customer
Based
The project of development and installation of RALS ticketing system
is customer based and would comprise of forming the improved
4th
3PROJECT MANAGEMENT
functional operations.
Social
Grounds
The project of development and installation of RALS ticketing system
is least bothered by the social aspects as the project only forms an
information system for the ticketing process of Riverina Agriculture
and Lifestyle Show
5th
a. Better- The project of development and installation of RALS ticketing system would comprise
of improving the process of faster data and information management with the help of the new
system developed
b. Faster- The information sharing via the system developed would be faster and it would also
comprise of providing the remote access to the main data storage for the users with authentic
access
c. Cheaper- Ticket generation for the Riverina Agriculture and Lifestyle Show would be cheap as
the manual management of the operations would consume a number of resources while on the
other hand the system would do all these cohesively
d. Do more- The project of development and installation of RALS ticketing system would get the
benefit of forming improved ground with the available information for future projects
Appropriate Metric with timeframe:
Factor Metrics Timeframe (in months)
Financially NPV, Revenue, and Profit Calculation 4
functional operations.
Social
Grounds
The project of development and installation of RALS ticketing system
is least bothered by the social aspects as the project only forms an
information system for the ticketing process of Riverina Agriculture
and Lifestyle Show
5th
a. Better- The project of development and installation of RALS ticketing system would comprise
of improving the process of faster data and information management with the help of the new
system developed
b. Faster- The information sharing via the system developed would be faster and it would also
comprise of providing the remote access to the main data storage for the users with authentic
access
c. Cheaper- Ticket generation for the Riverina Agriculture and Lifestyle Show would be cheap as
the manual management of the operations would consume a number of resources while on the
other hand the system would do all these cohesively
d. Do more- The project of development and installation of RALS ticketing system would get the
benefit of forming improved ground with the available information for future projects
Appropriate Metric with timeframe:
Factor Metrics Timeframe (in months)
Financially NPV, Revenue, and Profit Calculation 4
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT MANAGEMENT
Operational Management Plan 5
Strategicall
y
Feedback and Suggestions 2
Customer
Based
Strategic Analysis Matrix 4
Social
Grounds
Social Sites 3
MOV statement: The completion of the project of development and installation of RALS
ticketing system would help in forming the improved generation of the ticket and information
storage for the Riverina Agriculture and Lifestyle Show
Part 2: Scope Management Plan
Define the scope: The project of development and installation of RALS ticketing system
involves the use of the technology and principles of software development projects. The project
of development and installation of RALS ticketing system involves a series of technology related
activities that would combine for improving the process of faster data and information
management with the help of the new ticket generation system for the Riverina Agriculture and
Lifestyle Show.
Operational Management Plan 5
Strategicall
y
Feedback and Suggestions 2
Customer
Based
Strategic Analysis Matrix 4
Social
Grounds
Social Sites 3
MOV statement: The completion of the project of development and installation of RALS
ticketing system would help in forming the improved generation of the ticket and information
storage for the Riverina Agriculture and Lifestyle Show
Part 2: Scope Management Plan
Define the scope: The project of development and installation of RALS ticketing system
involves the use of the technology and principles of software development projects. The project
of development and installation of RALS ticketing system involves a series of technology related
activities that would combine for improving the process of faster data and information
management with the help of the new ticket generation system for the Riverina Agriculture and
Lifestyle Show.
5PROJECT MANAGEMENT
Requirements: The budgeter, computer devices, documenter, IT engineer, network components,
planner, project manager, storage, system analyst, tester, wireless routers, contractor, and analyst
are the requirements of the project of development and installation of RALS ticketing system.
In scope-out scope items: The in scope project items for development and installation of RALS
ticketing system project are initiation documents, charter documents, plan, design, database,
system, and final documents. The out of scope items for development and installation of RALS
ticketing system project are transportation requirements, change plan, and communication
process.
Deliverables: The deliverables for the project of development and installation of RALS ticketing
system are,
WBS Task Name Duration Start Finish
1.2 Documenting the project charter 4 days Thu 2/15/18 Tue 2/20/18
1.3 Documenting the initiation documents 3 days Wed 2/21/18 Fri 2/23/18
2.2 Outlining the project plan 4 days Thu 3/1/18 Tue 3/6/18
2.6 Estimating the project costs 2 days Thu 3/22/18 Fri 3/23/18
3.1.2 Making appropriate design 10 days Mon 4/9/18 Fri 4/20/18
3.2.1 Developing the storage 10 days Mon 5/7/18 Fri 5/18/18
3.2.3 User Interface is developed 4 days Thu 5/24/18 Tue 5/29/18
3.2.6 Infrastructure is developed 7 days Wed 6/20/18 Thu 6/28/18
Requirements: The budgeter, computer devices, documenter, IT engineer, network components,
planner, project manager, storage, system analyst, tester, wireless routers, contractor, and analyst
are the requirements of the project of development and installation of RALS ticketing system.
In scope-out scope items: The in scope project items for development and installation of RALS
ticketing system project are initiation documents, charter documents, plan, design, database,
system, and final documents. The out of scope items for development and installation of RALS
ticketing system project are transportation requirements, change plan, and communication
process.
Deliverables: The deliverables for the project of development and installation of RALS ticketing
system are,
WBS Task Name Duration Start Finish
1.2 Documenting the project charter 4 days Thu 2/15/18 Tue 2/20/18
1.3 Documenting the initiation documents 3 days Wed 2/21/18 Fri 2/23/18
2.2 Outlining the project plan 4 days Thu 3/1/18 Tue 3/6/18
2.6 Estimating the project costs 2 days Thu 3/22/18 Fri 3/23/18
3.1.2 Making appropriate design 10 days Mon 4/9/18 Fri 4/20/18
3.2.1 Developing the storage 10 days Mon 5/7/18 Fri 5/18/18
3.2.3 User Interface is developed 4 days Thu 5/24/18 Tue 5/29/18
3.2.6 Infrastructure is developed 7 days Wed 6/20/18 Thu 6/28/18
6PROJECT MANAGEMENT
4.2 Final reports are developed 3 days Fri 7/27/18 Tue 7/31/18
Acceptance Criteria: The acceptance criteria for the project of development and installation of
RALS ticketing system are
Ticket generation would be faster and cheaper for Riverina Agriculture and Lifestyle
Show
Completion of the project in estimated budget and resource allocated
Time taken for the project would be less than 5 months
Provide a list of Resources:
ID Resource Name Work
1 Budgeter 72 hrs
2 Computer Devices 1
3 Documenter 106 hrs
4 IT Engineer 288 hrs
5 Network Components 1
6 Planner 56 hrs
7 Project Manager 86 hrs
8 Storage 1
9 System Analyst 176 hrs
10 Tester 120 hrs
11 Wireless routers 1
12 Contractor 56 hrs
13 Analyst 24 hrs
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
S S S S S S S S S S S
Mar 11, '18 Apr 8, '18 May 6, '18 Jun 3, '18 Jul 1, '18 Jul 29, '18
56h
0.33 0.67
24h 18h
48h 80h 80h 56h 8h 16h
0.33 0.67
6h
1
24h 80h 32h 24h 16h
64h 56h
0.33 0.67
56h
Figure 1: List of resources for the project
4.2 Final reports are developed 3 days Fri 7/27/18 Tue 7/31/18
Acceptance Criteria: The acceptance criteria for the project of development and installation of
RALS ticketing system are
Ticket generation would be faster and cheaper for Riverina Agriculture and Lifestyle
Show
Completion of the project in estimated budget and resource allocated
Time taken for the project would be less than 5 months
Provide a list of Resources:
ID Resource Name Work
1 Budgeter 72 hrs
2 Computer Devices 1
3 Documenter 106 hrs
4 IT Engineer 288 hrs
5 Network Components 1
6 Planner 56 hrs
7 Project Manager 86 hrs
8 Storage 1
9 System Analyst 176 hrs
10 Tester 120 hrs
11 Wireless routers 1
12 Contractor 56 hrs
13 Analyst 24 hrs
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
S S S S S S S S S S S
Mar 11, '18 Apr 8, '18 May 6, '18 Jun 3, '18 Jul 1, '18 Jul 29, '18
56h
0.33 0.67
24h 18h
48h 80h 80h 56h 8h 16h
0.33 0.67
6h
1
24h 80h 32h 24h 16h
64h 56h
0.33 0.67
56h
Figure 1: List of resources for the project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT MANAGEMENT
Part 3: Project Schedule
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Development and
Installation of RALS
Ticketing System
124 days Mon 2/12/18 Thu 8/2/18
1 1 Project Initialization 12 days Mon 2/12/18 Tue 2/27/18
2 1.1 Analyzing the requirements3 days Mon 2/12/18 Wed 2/14/18
3 1.2 Documenting the project charter4 days Thu 2/15/18 Tue 2/20/18
4 1.3 Documenting the
initiation documents
3 days Wed 2/21/18 Fri 2/23/18
5 1.4 Meeting for project kick off1 day Mon 2/26/18 Mon 2/26/18
6 1.5 Submitting the project
documents
1 day Tue 2/27/18 Tue 2/27/18
7 2 Project Planning and
Resource Accumulation
25 days Wed 2/28/18 Tue 4/3/18
8 2.1 Selecting the project plan
methodology
1 day Wed 2/28/18 Wed
2/28/18
9 2.2 Outlining the project plan 4 days Thu 3/1/18 Tue 3/6/18
10 2.3 Reviewing the plan 2 days Wed 3/7/18 Thu 3/8/18
11 2.4 Analyzing the Client's
requirements
3 days Fri 3/9/18 Tue 3/13/18
12 2.5 Selecting the project team6 days Wed 3/14/18 Wed 3/21/18
13 2.6 Estimating the project costs2 days Thu 3/22/18 Fri 3/23/18
14 2.7 Accumulating the project
resources
7 days Mon 3/26/18 Tue 4/3/18
15 3 System Development and Testing80 days Wed 4/4/18 Tue 7/24/18
16 3.1 Designing the system 23 days Wed 4/4/18 Fri 5/4/18
17 3.1.1 Selecting design platform3 days Wed 4/4/18 Fri 4/6/18
18 3.1.2 Making appropriate design10 days Mon 4/9/18 Fri 4/20/18
19 3.1.3 Reviewing the design 3 days Mon 4/23/18 Wed 4/25/18
20 3.1.4 Prototyping the design 4 days Thu 4/26/18 Tue 5/1/18
21 3.1.5 Simulating the design 3 days Wed 5/2/18 Fri 5/4/18
22 3.2 Developing the system 42 days Mon 5/7/18 Tue 7/3/18
23 3.2.1 Developing the storage 10 days Mon 5/7/18 Fri 5/18/18
24 3.2.2 Database is integrated 3 days Mon 5/21/18 Wed 5/23/18
25 3.2.3 User Interface is developed4 days Thu 5/24/18 Tue 5/29/18
26 3.2.4 Programming and
Coding the ticketing
system
10 days Wed 5/30/18 Tue 6/12/18
27 3.2.5 Functions Integration
in the system
5 days Wed 6/13/18 Tue 6/19/18
28 3.2.6 Infrastructure is developed7 days Wed 6/20/18 Thu 6/28/18
29 3.2.7 Hardware components
are deployed
3 days Fri 6/29/18 Tue 7/3/18
30 3.3 System Testing 15 days Wed 7/4/18 Tue 7/24/18
31 3.3.1 User Interface is tested3 days Wed 7/4/18 Fri 7/6/18
32 3.3.2 Black box testing 3 days Mon 7/9/18 Wed 7/11/18
33 3.3.3 White Box testing 3 days Thu 7/12/18 Mon 7/16/18
34 3.3.4 User experience analysis3 days Tue 7/17/18 Thu 7/19/18
35 3.3.5 Test run and Simulation3 days Fri 7/20/18 Tue 7/24/18
36 4 Final Documentation 7 days Wed 7/25/18 Thu 8/2/18
37 4.1 Project Closure checklist
is formed
2 days Wed 7/25/18 Thu 7/26/18
38 4.2 Final reports are developed3 days Fri 7/27/18 Tue 7/31/18
39 4.3 Submission of documents 2 hrs Wed 8/1/18 Wed 8/1/18
40 4.4 Reviewing the documents 5 hrs Wed 8/1/18 Wed 8/1/18
41 4.5 Signing the documents 1 hr Wed 8/1/18 Wed 8/1/18
42 4.6 Project Closed 1 day Thu 8/2/18 Thu 8/2/18
Analyst
Documenter
Documenter
Project Manager
Documenter
Planner
Planner
Planner
Project Manager
Project Manager
Budgeter
Budgeter
System Analyst
System Analyst
IT Engineer
System Analyst
IT Engineer
IT Engineer,Storage[1]
IT Engineer
IT Engineer
IT Engineer
System Analyst
Contractor
Computer Devices[1],IT Engineer,Network Co
Tester
Tester
Tester
Tester
Tester
Documenter
Documenter
Documenter
Project Manager
Project Manager
S W S T M F T
Feb 11, '18 Apr 22, '18 Jul 1, '18 Sep 9, '18
Figure 2: Gantt chart showing project schedule
Part 3: Project Schedule
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Development and
Installation of RALS
Ticketing System
124 days Mon 2/12/18 Thu 8/2/18
1 1 Project Initialization 12 days Mon 2/12/18 Tue 2/27/18
2 1.1 Analyzing the requirements3 days Mon 2/12/18 Wed 2/14/18
3 1.2 Documenting the project charter4 days Thu 2/15/18 Tue 2/20/18
4 1.3 Documenting the
initiation documents
3 days Wed 2/21/18 Fri 2/23/18
5 1.4 Meeting for project kick off1 day Mon 2/26/18 Mon 2/26/18
6 1.5 Submitting the project
documents
1 day Tue 2/27/18 Tue 2/27/18
7 2 Project Planning and
Resource Accumulation
25 days Wed 2/28/18 Tue 4/3/18
8 2.1 Selecting the project plan
methodology
1 day Wed 2/28/18 Wed
2/28/18
9 2.2 Outlining the project plan 4 days Thu 3/1/18 Tue 3/6/18
10 2.3 Reviewing the plan 2 days Wed 3/7/18 Thu 3/8/18
11 2.4 Analyzing the Client's
requirements
3 days Fri 3/9/18 Tue 3/13/18
12 2.5 Selecting the project team6 days Wed 3/14/18 Wed 3/21/18
13 2.6 Estimating the project costs2 days Thu 3/22/18 Fri 3/23/18
14 2.7 Accumulating the project
resources
7 days Mon 3/26/18 Tue 4/3/18
15 3 System Development and Testing80 days Wed 4/4/18 Tue 7/24/18
16 3.1 Designing the system 23 days Wed 4/4/18 Fri 5/4/18
17 3.1.1 Selecting design platform3 days Wed 4/4/18 Fri 4/6/18
18 3.1.2 Making appropriate design10 days Mon 4/9/18 Fri 4/20/18
19 3.1.3 Reviewing the design 3 days Mon 4/23/18 Wed 4/25/18
20 3.1.4 Prototyping the design 4 days Thu 4/26/18 Tue 5/1/18
21 3.1.5 Simulating the design 3 days Wed 5/2/18 Fri 5/4/18
22 3.2 Developing the system 42 days Mon 5/7/18 Tue 7/3/18
23 3.2.1 Developing the storage 10 days Mon 5/7/18 Fri 5/18/18
24 3.2.2 Database is integrated 3 days Mon 5/21/18 Wed 5/23/18
25 3.2.3 User Interface is developed4 days Thu 5/24/18 Tue 5/29/18
26 3.2.4 Programming and
Coding the ticketing
system
10 days Wed 5/30/18 Tue 6/12/18
27 3.2.5 Functions Integration
in the system
5 days Wed 6/13/18 Tue 6/19/18
28 3.2.6 Infrastructure is developed7 days Wed 6/20/18 Thu 6/28/18
29 3.2.7 Hardware components
are deployed
3 days Fri 6/29/18 Tue 7/3/18
30 3.3 System Testing 15 days Wed 7/4/18 Tue 7/24/18
31 3.3.1 User Interface is tested3 days Wed 7/4/18 Fri 7/6/18
32 3.3.2 Black box testing 3 days Mon 7/9/18 Wed 7/11/18
33 3.3.3 White Box testing 3 days Thu 7/12/18 Mon 7/16/18
34 3.3.4 User experience analysis3 days Tue 7/17/18 Thu 7/19/18
35 3.3.5 Test run and Simulation3 days Fri 7/20/18 Tue 7/24/18
36 4 Final Documentation 7 days Wed 7/25/18 Thu 8/2/18
37 4.1 Project Closure checklist
is formed
2 days Wed 7/25/18 Thu 7/26/18
38 4.2 Final reports are developed3 days Fri 7/27/18 Tue 7/31/18
39 4.3 Submission of documents 2 hrs Wed 8/1/18 Wed 8/1/18
40 4.4 Reviewing the documents 5 hrs Wed 8/1/18 Wed 8/1/18
41 4.5 Signing the documents 1 hr Wed 8/1/18 Wed 8/1/18
42 4.6 Project Closed 1 day Thu 8/2/18 Thu 8/2/18
Analyst
Documenter
Documenter
Project Manager
Documenter
Planner
Planner
Planner
Project Manager
Project Manager
Budgeter
Budgeter
System Analyst
System Analyst
IT Engineer
System Analyst
IT Engineer
IT Engineer,Storage[1]
IT Engineer
IT Engineer
IT Engineer
System Analyst
Contractor
Computer Devices[1],IT Engineer,Network Co
Tester
Tester
Tester
Tester
Tester
Documenter
Documenter
Documenter
Project Manager
Project Manager
S W S T M F T
Feb 11, '18 Apr 22, '18 Jul 1, '18 Sep 9, '18
Figure 2: Gantt chart showing project schedule
8PROJECT MANAGEMENT
Part 4: Project Risk Analysis
Figure 3: Risk Analysis in Excel template
Part 5: Quality Management Plan
The quality management for the project of Developing New Rostering System for Riverina
Agriculture and Lifestyle Show is given below,
Development of Verification Activities: User interface system testing, design simulation, and
integrated database testing is carried on as the set of verification activities for the project of
development and installation of RALS ticketing system
Development of Validation Activities: The validation activities for the project of development
and installation of RALS ticketing system can be done by the use of the process implementation
plan, quality management plan, and change management plan
Part 6: Project Closure and Evaluation
Annotated Bibliography: The study by Menzies (2014) has helped in developing a complete
understanding of the simple projects for software development. The software development
Part 4: Project Risk Analysis
Figure 3: Risk Analysis in Excel template
Part 5: Quality Management Plan
The quality management for the project of Developing New Rostering System for Riverina
Agriculture and Lifestyle Show is given below,
Development of Verification Activities: User interface system testing, design simulation, and
integrated database testing is carried on as the set of verification activities for the project of
development and installation of RALS ticketing system
Development of Validation Activities: The validation activities for the project of development
and installation of RALS ticketing system can be done by the use of the process implementation
plan, quality management plan, and change management plan
Part 6: Project Closure and Evaluation
Annotated Bibliography: The study by Menzies (2014) has helped in developing a complete
understanding of the simple projects for software development. The software development
9PROJECT MANAGEMENT
projects play a crucial role for developing appropriate products and services for the project plan.
The SDLC approach is used for the software development projects that involve the development
of an information system. Conforto et al. (2014) have provided a deep study of agile software
development projects and critically evaluate whether the method should be implied by any other
projects. The Agile methodology is widely used for software development projects. However,
the approach can be implied for construction projects as well. According to Tan et al. (2014), the
estimation of the project durations is very crucial and it forms an impact on the completion of the
project operations. The project development comprise of using scheduling methods for ensuring
that the project is achieved successfully.
Closure Checklist: The general closure checklist for the project is given below,
Factor Check?
Accurate cost estimation is done
Project Resources are aligned properly
Client’s requirement criteria is met
Project plan is developed by using methodology
Agreements and other documents are being made
Figure 3: Project Closure Checklist
Project Evaluation:
projects play a crucial role for developing appropriate products and services for the project plan.
The SDLC approach is used for the software development projects that involve the development
of an information system. Conforto et al. (2014) have provided a deep study of agile software
development projects and critically evaluate whether the method should be implied by any other
projects. The Agile methodology is widely used for software development projects. However,
the approach can be implied for construction projects as well. According to Tan et al. (2014), the
estimation of the project durations is very crucial and it forms an impact on the completion of the
project operations. The project development comprise of using scheduling methods for ensuring
that the project is achieved successfully.
Closure Checklist: The general closure checklist for the project is given below,
Factor Check?
Accurate cost estimation is done
Project Resources are aligned properly
Client’s requirement criteria is met
Project plan is developed by using methodology
Agreements and other documents are being made
Figure 3: Project Closure Checklist
Project Evaluation:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT MANAGEMENT
Time: Time taken for the project would be less than 5 months
Cost: Completion of the project in estimated budget and resource allocated
Functionality: Ticket generation would be faster and cheaper for Riverina Agriculture and
Lifestyle Show
Time: Time taken for the project would be less than 5 months
Cost: Completion of the project in estimated budget and resource allocated
Functionality: Ticket generation would be faster and cheaper for Riverina Agriculture and
Lifestyle Show
1 out of 11
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.