Modifications in Showground Station
Name of the Student:
Name of the University:
Modifications in Showground Station_1

1PROJECT MANAGEMENT
Executive Summary
The project plan is based on modifications of the Showground Station with the core activities of
the construction work included civil, instrumentation, and electrical as well as structural
specialists of the project work. The background of this project plan is based on the company to
plan initiative of staring the construction project in Sydney. In this particular project plan, the
project management aspects which are used such as scope management, time, cost, quality,
human resource, communication, risk, procurement and stakeholder management plan. The
project is started at 9th May, 2019 and end at 7th April, 2021 with an estimated budget of
$668.720. The scope of this project is procurement of the raw materials, installation of water
treatment plant and other procurements items to be installed.
Modifications in Showground Station_2

2PROJECT MANAGEMENT
Letter for permission from the organization
5th April, 2019
Dear Australian Government,
I am in the process to modify the Showground Station; therefore I would like your permission to
include following materials into this project such as:
The scheduled project timeline is 500 days while it will start from 9th May, 2019 and end at 7th
April, 2021. The estimated budget for the project is $668,720. The main scope of this project is
installation of water treatment plant, workshops and storage. I would like your contact
information you will provide me regarded the right holder. Your permission is required to hold
and does the project plan. I am attached the project charter which will provide you required
information regarding the modifications work of the station.
I would appreciate your concern to my request and if you require any additional information,
please do not hesitate to contact me.
Sincerely,
Project Manager
Modifications in Showground Station_3

3PROJECT MANAGEMENT
Table of Contents
1.0 Introduction................................................................................................................................4
2.0 Project baseline..........................................................................................................................4
2.1 Schedule baseline...................................................................................................................5
2.2 Cost baseline..........................................................................................................................5
2.3 Scope baseline.......................................................................................................................6
3. Project subsidiary plans...............................................................................................................7
3.1 Scope management plan........................................................................................................7
3.2 Schedule management plan...................................................................................................8
3.3 Cost management plan.........................................................................................................15
3.4 Quality management plan....................................................................................................20
3.5 Human resource management plan......................................................................................21
3.6 Communications management plan.....................................................................................26
3.7 Risk management plan.........................................................................................................29
3.8 Procurement management plan............................................................................................32
3.9 Stakeholder management plan.............................................................................................32
4. Conclusion.................................................................................................................................37
References......................................................................................................................................38
Bibliography..................................................................................................................................40
Modifications in Showground Station_4

4PROJECT MANAGEMENT
1.0 Introduction
Showground Station is the underground rapid transit stations which are being built by
Metro Trains Sydney consortium at the Doran Drive. It is a part of Transport of NSW’s Sydney
metro Northwest project. They are providing train services to the passengers those are planned to
take trains to go to their destination. The proposed modifications into the Showground Station
are included site offices and amentias, car parking, workshops, stores, laydown and water
treatment plant.
The project management plan is included project baseline in addition to project
subsidiary plans. There is analyzing of different project plans which are used for successful
completion of modifications into the showground station. Scope, schedule and cost management
plans are provided so that the project can assemble with its development requirements, complete
within schedule time as well as estimate the budget mandatory to complete the development
work of the development related to the showground stations.
2.0 Project baseline
The project baseline is key significant element of the project management as without the
project baseline there is no required to measure the performance and there is no earned value
analysis for the project work. There are three main project baselines which are summarized in
this project plan such as schedule baseline, cost baseline and scope baseline.
Modifications in Showground Station_5

5PROJECT MANAGEMENT
2.1 Schedule baseline
Kerzner and Kerzner (2017) stated that the schedule baseline is approved schedule of the
project plan which is being agreed by the project team members before the project can start. It is
a measurement of the schedule as planned against progress on the actual schedule to be
measured. In this modifications project plan of showground station, Sydney the schedule
baseline is used for analyzing the performance of project as well as report to the schedule
variances.
Name Duration
Project initiation phase 46 days
Project Planning Phase 190 days
Project execution phase 155 days
Project monitoring and controlling phase 83 days
Project Closure phase 26 days
2.2 Cost baseline
Larson and Gray (2017) discussed that the cost baseline is part of the project baseline
which can handle the total amount of cost is to be predicted based on the project requirements
and capitals required to complete the plan in scheduled time period. It is approved project budget
into the time distribution format so that there is monitoring and controlling the cost performance
of the development plan. The total expected cost of the project is $668,720.
Modifications in Showground Station_6

6PROJECT MANAGEMENT
Name Cost Baseline Cost
Project initiation phase $50,640.00 $50,640.00
Project Planning Phase $229,040.00 $229,040.00
Project execution phase $232,400.00 $232,400.00
Project monitoring and controlling
phase
$129,520.00 $129,520.00
Project Closure phase $27,120.00 $27,120.00
2.3 Scope baseline
Fleming and Koppelman (2016) illustrated that the scope baseline is a part of the project
lifecycle so that it includes project scope documents, work breakdown structure and project
goals, objectives which are required to complete the development plan. The scopes of this project
are as follows:
The development is to be completed in schedule time of 500 days.
The cost assigned to the project is to be $668,720.
Water treatment plant
Procurement of the raw materials
Installation of the plant
Modifications in Showground Station_7

7PROJECT MANAGEMENT
3. Project subsidiary plans
3.1 Scope management plan
This plan is an aspect of the project management as it assists the project manager to
identify the project boundaries, objectives as well as goals of the project plan. It is important to
provide positive results to the project. The purpose of this project plan is to develop as well as
modify the best quality of Showground station which has capacity to make improvement into the
facilities and amentias (Harrison and Lock 2017). Following are the objectives of the project
work such as:
Procurement of the best quality of the raw materials such as water treatment plant,
storage, workshops and others
Construction of car parking
Installation of stores and laydown
Implementation of stable as well as robust, effective system
The scope of this particular project plan is to finish the project work on planned time and
predictable project budget. The out scope of this project plan is to transfer to the site area and
installation of metal roof and best quality of distribution pipes into the Showcase station. The
start date of the project plan is Thu 5/9/19 and end date of the plan is Wed 4/7/21. The estimated
budget of the project plan is calculated to be $668,720; therefore within this project budget the
project manager should finish the work.
The list of the project deliverables are as follows such as:
Project charter
Modifications in Showground Station_8