Project Management Case Study - Tier One Suppliers Insurance Group (TOSIG)

Verified

Added on  2023/06/11

|17
|2474
|398
AI Summary
This case study reflects on the implementation of CRM system within the organization TOSIG that facilitates insurance to One tier suppliers. It covers project background, schedule, time and cost management, resource management, risk management and more.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Case Study- Tier One Suppliers Insurance Group (TOSIG)
Name of the Student
Name of the University
Author’s Note

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1. Project Background................................................................................................................2
1.1 Project Background..........................................................................................................2
1.2 Project goal.......................................................................................................................2
1.3 Project objective...............................................................................................................2
1.4 Project Deliverable...........................................................................................................2
1.5 Strategic alignment of project..........................................................................................3
2. Project Schedule.....................................................................................................................3
2.1 Milestones........................................................................................................................3
2.2 Project requirements.........................................................................................................4
2.3 Limits and exclusions.......................................................................................................4
2.4 Work/ process breakdown schedule.................................................................................5
3. Time and cost management....................................................................................................7
3.1 Time management............................................................................................................7
3.2 Cost management.............................................................................................................8
4. Resource management.........................................................................................................11
5. Risk management.................................................................................................................12
6. Communication management plan.......................................................................................13
References................................................................................................................................15
Document Page
2
PROJECT MANAGEMENT
1. Project Background
1.1 Project Background
The paper mainly reflects on the implementation of CRM system within the
organization “TOSIG” that facilitates insurance to One tier suppliers. It is found that the
organization faces lot of issues and challenges due to the current process that the organization
follows as the agents needs to re-enter data within the organization system which is quite
time-consuming. In order to mitigate the issue, the organization implements CRM system
within the organization so that its information system is upgraded and the organization will
be able to get proper facility of insurance to the clients.
1.2 Project goal
The main goal of TOSIG is to implement customer relationship management system
to upgrade the information system of the organization. It is found that due to the
implementation of CRM system, the organization can get the chance of offering more
insurance to the clients.
1.3 Project objective
The project objectives are:
To implement customer relationship management system within the organization
To enhance the business opportunities for the organization
To minimize the time that is generally spend in entering data
1.4 Project Deliverable
The project deliverables are listed below:
Analysis of system requirements
Selection of proper platform
Designing outline
Document Page
3
PROJECT MANAGEMENT
Testing of simulation
Completion of design
Designing approval
Completion of design implication
Migration of database'
Conducting black box testing
1.5 Strategic alignment of project.
It is essential to align the objectives as well as goals of the organization with the
project to fulfill the demands as well as needs of the project. It is identified if the needs as
well as requirements of the organization is known then the project manager takes the
initiative of aligning the project with the objectives of the organization so that the developed
system will be beneficial for the organization for achieving its goals and objectives.
2. Project Schedule
2.1 Milestones
The project milestones are provided in the table below:
WBS Task Name Completion date
M1 Approval of project Tue 12-06-18
M2 Getting plan approval Mon 09-07-18
M3' Designing approval Thu 26-07-18
M4 Entire development of the system Tue 28-08-18
M5 Functional testing is conducted Mon 17-09-18
M6 Project Closure Thu 18-10-18

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
2.2 Project requirements
The project requirements are as follows:
Hardware: The hardware requirements include:
Computer
Operating system-Windows 10
RAM
Hard-drive
Software: The software requirements include:
Zoho
Romexsoft
Human resources: The people who are associated with the project are listed below:
Project manager
Business analyst
Programmer_1
Programmer_2
Database developer
Graphical user interface developer
Tester
Administration officer
2.3 Limits and exclusions
The limits and exclusions of the project are listed below:
The CRM system implementation must not extended after its final completion
date otherwise the project budget will increase
Document Page
5
PROJECT MANAGEMENT
Involvement of all the project team members within the project otherwise project
would not get completed on the assumed time.
2.4 Work/ process breakdown schedule
The work/process breakdown schedule is provided below:
WBS Task Name
0 Implementation of CRM system for TOSIG
1 Initialization
1.1 Analysis of project requirements
1.2 Accumulation of resources
1.3 Documentation of project charter
1.4 Meeting for project initiation
M1 Approval of project
2 Planning
2.1 Scheduling of project activities
2.2 Division of project resources
2.3 Development of project schedule
2.4 Development of plan
2.5 Communication of project planning
2.6 Planning for risk management
M2 Getting plan approval
3 Designing phase
3.1 Analysis of system requirements
3.2 Selection of proper platform
Document Page
6
PROJECT MANAGEMENT
3.3 Designing outline
3.4 Testing of simulation
3.5 Completion of design
M3' Designing approval
4 Development of system
4.1 Completion of design implication
4.2 Migration of database'
4.3 Conducting black box testing
4.4 Development of system interface
4.5 Testing of prototype
4.6 Requirements of functions
4.7 Conducting beta testing
M4 Entire development of the system
5 System Deployment
5.1 Creating deployment plan
5.2 Modification within the system
5.3 Testing of compatibility
5.4 Deployment of system
M5 Functional testing is conducted
6 Documentation and training
6.1 Development of training manuals
6.2 Development of training program
6.3 Providing staff training
6.4 Developing final reports

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
7
PROJECT MANAGEMENT
6.5 Documents sign off
6.6 System maintenance
M6 Project Closure
3. Time and cost management
3.1 Time management
The entire schedule of the project will be managed with the help of Gantt chart. It is
identified that Gantt chart are utilized to track as well as manage the time of the project so
that the entire project can be completed within the expected time.
Figure 1: Gantt chart
(Source: Created by Author)
Document Page
8
PROJECT MANAGEMENT
3.2 Cost management
The project cost can be effectively managed as per the budget that is assumed by the
project manager in the planning stage of the project. It is analyzed that the entire budget is
provided below with which the project manager can be able to track the cost of the project.
WBS Task Name Duration Resource Names Cost
0
Implementation of CRM
system for TOSIG
100 days $57,240.00
1 Initialization 8 days $4,600.00
1.1
Analysis of project
requirements
2 days Project manager $1,360.00
1.2
Accumulation of
resources
3 days Business analyst $1,200.00
1.3
Documentation of
project charter
2 days Project manager $1,360.00
1.4
Meeting for project
initiation
1 day Project manager $680.00
M1 Approval of project 0 days $0.00
2 Planning 19 days $12,960.00
2.1
Scheduling of project
activities
3 days Project manager $2,040.00
2.2
Division of project
resources
2 days Administration officer $480.00
2.3
Development of project
schedule
4 days Project manager $2,720.00
Document Page
9
PROJECT MANAGEMENT
2.4 Development of plan 5 days
Database developer,
Project manager
$5,400.00
2.5
Communication of
project planning
2 days Project manager $1,360.00
2.6
Planning for risk
management
3 days Tester $960.00
M2 Getting plan approval 0 days $0.00
3 Designing phase 13 days $7,440.00
3.1
Analysis of system
requirements
2 days Database developer $800.00
3.2
Selection of proper
platform
1 day Business analyst $400.00
3.3 Designing outline 3 days Project manager $2,040.00
3.4 Testing of simulation 2 days
Graphical user interface
developer
$800.00
3.5 Completion of design 5 days Project manager $3,400.00
M3' Designing approval 0 days $0.00
4 Development of system 23 days $9,440.00
4.1
Completion of design
implication
1 day Database developer $400.00
4.2 Migration of database' 3 days
Administration officer,
Database developer
$1,920.00
4.3
Conducting balck box
testing
2 days Tester $640.00

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
4.4
Development of system
interface
5 days
Graphical user interface
developer
$2,000.00
4.5 Testing of prototype 2 days Tester $640.00
4.6
Requirements of
functions
8 days Business analyst $3,200.00
4.7 Conducting beta testing 2 days Tester $640.00
M4
Entire development of
the system
0 days $0.00
5 System Deployment 14 days $10,240.00
5.1
Creating deployment
plan
3 days
Graphical user interface
developer,
Programmer_1
$2,400.00
5.2
Modification within the
system
4 days
Database developer,
Graphical user interface
developer
$3,200.00
5.3 Testing of compatibility 2 days Tester $640.00
5.4 Deployment of system 5 days
Database developer,
Programmer_2
$4,000.00
M5
Functional testing is
conducted
0 days $0.00
6
Documentation and
training
23 days $12,560.00
6.1
Development of training
manuals
2 days Project manager $1,360.00
Document Page
11
PROJECT MANAGEMENT
6.2
Development of training
program
3 days Administration officer $720.00
6.3 Providing staff training 10 days Project manager $6,800.00
6.4 Developing final reports 3 days Project manager $2,040.00
6.5 Documents sign off 1 day Project manager $680.00
6.6 System maintenance 4 days Administration officer $960.00
M6 Project Closure 0 days Project manager $0.00
4. Resource management
The resource management for the entire project is reflected in the table that is
provided below:
Resource
Name Type Materia
l Label
Initial
s
Grou
p
Max.
Units Std. Rate Ovt.
Rate
Cost/
Use
Accrue
At
Base
Calenda
r
Project
manager
Wor
k P 100
%
$85.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Business
analyst
Wor
k
100
%
$50.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Programmer_
1
Wor
k
100
%
$50.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Programmer_
2
Wor
k
100
%
$50.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Database
developer
Wor
k
100
%
$50.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Graphical user
interface
developer
Wor
k
100
%
$50.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Tester Wor
k
100
%
$40.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Administratio
n officer
Wor
k
100
%
$30.00/
hr
$0.00/
hr $0.00 Prorate
d
Standar
d
Document Page
12
PROJECT MANAGEMENT
5. Risk management
It is found that risk management plan is generally needed Implementation of CRM
system for foreseeing the risks and challenges of the project so that the impact as well as
probability that are associated with the project can be identified and the risks that are related
with the project can be successfully mitigated with the help of proper mitigation plan. The
risk management plan for the project is provided in the table below:
Risk Description Impact Probability Responsible
person
Mitigation
Inappropriate
schedule
If the
schedule of
the project is
not properly
developed
then it can
create lot of
issues.
Medium Medium Project
manager
It is essential
to track the
entire
schedule
regularly.
Shortage of
budget
Due to
budget
shortfall, the
project
manager
faces
difficulty in
finishing the
High High Financial
manager
The budget
of the project
must be
tracked with
the help of
earned value
analysis.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
13
PROJECT MANAGEMENT
project
Inappropriate
testing
Inappropriat
e testing can
lead to lot of
technical
issue
High Medium Tester It is
necessary to
conduct
proper
testing of the
system after
development.
Inappropriate
data
migration
Due to data
migration the
entire project
gets
negatively
impact due
to the
technical
challenge
that occur
within the
system
High High Database
developer
It is quite
necessary to
migrate the
data of the
project
properly.
6. Communication management plan
It is found that proper communication management plan is needed within the project
to have effective communication between the team members as well as higher authorities of
the organization. Thee communication management plan helps in defining the roles of the
person who are generally associated with the project. In addition to this, communication plan
Document Page
14
PROJECT MANAGEMENT
generally assists providing proper guidance about the meetings that is required to be
conducted within the project.
Audience Message Vehicle Frequency Owner
Project
planner
The
information
related with the
status of the
project are
shared.
Weekly E-mail,
conference
Team leader
Project manager Information
associated with
technical
challenges and
issues are
discussed
Monthly E-mail,
conference
Database
manager
Team member The project
manager gives
information
about the entire
scope as well as
overview of the
project.
Once Face to face Project manager
Document Page
15
PROJECT MANAGEMENT
References
Bucero, A. and Englund, R.L., 2015, October. Project sponsorship: Achieving management
commitment for project success. Project Management Institute.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
pp.291-298.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology
and project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Kucharska, W. and Kowalczyk, R., 2016. Trust, Collaborative Culture and Tacit Knowledge
Sharing in Project Management–a Relationship Model.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and
techniques for the practicing project manager. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
16
PROJECT MANAGEMENT
Riol, H. and Thuillier, D., 2015. Project management for academic research projects:
balancing structure and flexibility. International Journal of Project Organisation and
Management, 7(3), pp.251-269.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), pp.772-783.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.