Running head: PROJECT MANAGEMENT Project Management: Family Relocation to Perth project Name of the student: Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT Table of Contents 1. Introduction outlining purpose of the report................................................................................2 2. Project status detailing completion slips and delays....................................................................2 3. Current status based on the implication made on resources........................................................3 4. Adjustments implemented...........................................................................................................4 5. Personal reflection on the process...............................................................................................6 6. Updated project milestones (Please refer to Appendix 1 for updated milestones)......................6 7. List of tasks (Please refer to Appendix 2 for updated milestones)..............................................7 8. Gantt chart (Please refer to Appendix 3 for updated milestones)................................................7 References........................................................................................................................................8 Appendices....................................................................................................................................10 Appendix 1.................................................................................................................................10 Appendix 2.................................................................................................................................10 Appendix 3.................................................................................................................................13
2PROJECT MANAGEMENT 1. Introduction outlining purpose of the report This report defines and elaborates the crucial importance of using project management phases in order to deliver a proper initiation, planning and execution of a project. The purpose of the report is to show the progress and current status of “location shifting project.” Jeff has recently secured a new designation of Marketing director interstate and thus Jeff and Kelly along with their family started to plan a shifting from Maroochydore, on the Sunshine Coast, Qld to Perth. The new destination was already secured and they had to leave their current location on 20thJanuary, 2019. The new job was about to start on 5thFebruary. The days between 5th February and 20thJanuary they have planned to take an apartment as rent new Perth as they can shift to their new apartment on 29thJanuary. The total budget estimated for the entire shifting project was $15,000. Due to sudden difficulties the previously planned project was interrupted partly due to this reason the project progress details are also changed. The modified project plans including the progress report are elaborated below. The new school of Jeff and Kelly’s children will start on 31stJanuary therefore they have to shift to Perth before that. The modifications of the previously developed project plan is elaborated and detailed in the report section. 2. Project status detailing completion slips and delays As per the current status Australia has bit with a harmful epidemic flu and Kelly has become ill. Due to this reason Kelly cannot take any of the relocation responsibilities these days. The doctor has advised Kelly to take rest for two weeks starting from 15thJanuary. As they have to leave their current location on 20thJanuary therefore, they planned to stay intheir current
3PROJECT MANAGEMENT location for more 14 days (that is till 29thJanuary). Apart from this, the truck that was carrying the belongings of Jeff and Kelly was broken down near South Africa basically in n absolutely remotelocation.ItistheresponsibilityoftheJeffandKellyonlytotakerespective responsibilities to repair the broken truck. They planned to reach Perth by 27thJanuary first but then due to Kelly’s bad health condition it was delayed by 29thJanuary. Above all, due to the broken truck issue the entire scenario was delayed by 30thJanuary. On the other hand, due to Australia day celebration in Perth the numbers of flights are found to be limited. Due to this reason from Maroochydore, on the Sunshine Coast, Qld they will take flight on 29thJanuary night so that they can reach Perth by 30thJanuary and easily join the school on 31stJanuary. On 30thJanuary theory belongings will also be reached to Perth. 3. Current status based on the implication made on resources After analyzing the entire scenario of the family relocation project to Perth it is determined that Kelly’s flu and sudden breakdown of the Truck was the two major issues. These issues should be considered once again for re-planning and re-developing the project properly. The doctor told Kelly to take 2 weeks rest without travelling. Therefore, the numbers of days in Maroochydore, on the Sunshine Coast, Qld was extended by 14 days. After theses 14 days on 29thJanuary they will take their flight and reach Perth by 30thJanuary. Then the children will e easily able to join their new school session from 31stJanuary. As it was initially told that the net budget of the project cannot exceed the value of $1500 thus, the re-planning was also done based on those aspects. The resources assigned to the project arealignedtotheprojectrequirementsandsuccesscriteriaandotherassumptionsalso. Moreover, it is determined that the planned project will take total 29 days for successful
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT implementation. Currently, the project is its planning phase. Due to the bad health condition of Kelly the entire project was Re-planned. The re-planned schedule has successfully made adjustment in the net budget without over allocation of cost and over allocation of budget also. The modified resources are as follows: Name of the ResourceTypeStd. RateBase Calendar Jeff and KellyWork$0.00/hrStandard Project plannerWork$25.00/hrStandard Truck reloading and planningMaterial$2,000.00 Packaging CostMaterial$500.00 Logistic costMaterial$1,165.00 Truck repairing costMaterial$1,800.00 Others costMaterial$950.00 Doctors feesMaterial$20.00 medicine costMaterial$200.00 additional accommodation costMaterial$2,800.00 4. Adjustments implemented Though, the order of the project is sequential but still it is not mandatory that each time one activity will start with the completion of the previous activity. Simultaneously, two or more than two activities can move towards progress. As Kelly has to take bed rest for around 14 days therefore for the activity consulting to doctor for the bad health condition of Kelly the predecessor set on Start to Start (SS) with a lag of 1 day. It will increase the number of days by 0.5 days but without affecting the total budget estimated for the project. Apart from this, another adjustment was also done in flight ticket booking project activity. The predecessor set for this activity was adjusted with Start to Finish (SF) by 2 day (lag). With successful analysis of the case scenario it is defined that if these adjustments are done and implemented orderly then the project will be completed within 26.5 days instead of 29 days within the estimate budget of $15000. After making adjustment the changes that are occurred elaborated and listed below:
5PROJECT MANAGEMENT Task NameDurationPredecessors Updated schedule for Family relocation to Perth project26.5 days Project initialization3 days Initial planning for relocation0.5 days Determine final date to relocate0.5 days2 consulting to the project planner and agent1 day3 Confirmation of final date1 day4 Milestone 1: Date selection and final relocation plan completed0 days5 Planning17 days Activities outlining1 day6 Proper scheduling the activities0.5 days8 Consulting to doctor for Kelly's bad health0.5 days9 14 days bed rest in Maroochydore, on the Sunshine Coast, Qld14 days10SS+1 day Extending numbers of days in Sunshine Coast, Qld Apartment0.5 days11 Flight tickets booked on 29th night to Perth0.5 days12SF-2 days Planning contingency0.5 days13 resource allocation0.5 days13 Milestone 2: Approving all plans0 days15,14 Pre-relocation activity planning6.5 days Recruiting movers and packers0.5 days16,9 Selling the things that are not required2 days18 Pre-approval mortgage1 day19,9 Keeping Copious Notes0.5 days20 Relocating from the old apartment0.5 days21 Contact to agent for truck service0.5 days22 Truck send to garage near South Africa0.5 days22 Repairing of the Truck0.5 days23,24 Reloading truck with the belongings1 day25 Milestone 3: Truck reloading and final move to Perth0 days26 Post Relocation activities2 days Final arrival to new apartment in Perth0.5 days27 unloading Trucks0.5 days29 Belongings unpacking and accommodating those0.5 days30 Join School in Perth0.5 days31 Milestone 4: Successful completion of project closure phase0 days32
6PROJECT MANAGEMENT 5. Personal reflection on the process After analyzing the entire project case scenario it is defined that project plan s the most crucial thing that needs to be followed by the project participants always to avoid over allocation of time and over allocation of budget as well. Project delays and project slips can be easily avoided if the project is planned properly before implementation. Apart from project plan there are certain knowledge areas also those are to be followed accordingly by the project planner, Jeff ad Kelly as well to avoid any issues even during the project progress period also. Adjustment in day counts is one of the very important parts for this project. Thus, it is felt that time and cost management features should definitely be followed before implementing the project. The truck usingbythemtocarrytheirbelongingswasbrokendowninaremotelocationthus communication is the other important knowledge area should definitely be followed. Besides this, resource management is the other think must be followed by Jeff and Kelly while developing their family relocation project plan.Fr individual project activities proper resources are to be assigned and as soon as the resources are assigned it become their responsibilities to accomplish the activity within the assigned timeframe and budget as well. 6.Updatedprojectmilestones(PleaserefertoAppendix1forupdated milestones) Due to sudden attack of Flu to Kelly the previously planned project scenario was changed. Apart from this, sudden break down of the truck in a remote location is another issue which extended the numbers of days by 3. However, parallel work progresses are done in this project plan to avoid time consumptions and issues with additional cost.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT MANAGEMENT 7. List of tasks (Please refer to Appendix 2 for updated milestones) Though, the entire project is not changed accordingly but still some of the activities are modified to complete the project before 31stJanuary. Changes accommodated in some of the project activities are elaborated in the appendix section 2. 8. Gantt chart (Please refer to Appendix 3 for updated milestones) The updated Gantt chart will help Jeff and Kelly to visualize all the needful changes those are incorporated regarding the project activities. It is very important for the project planner, Jeff and Kelly to understand the complete project outline so that during implementation o error can occur. The details of the Gantt chart is elaborated in the below Appendix 3.
8PROJECT MANAGEMENT References Ahern, T., Leavy, B., and Byrne, P. J. 2014. Complex project management as complex problem solving: A distributed knowledge management perspective.International Journal of Project Management,32(8), 1371-1381. Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A. R., and Wang, Q. 2015. Implementing educational innovations at scale: Transforming researchers into continuous improvement scientists.Educational Policy,29(1), 257-277. Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., and de Almeida, L. F. M. 2014. Can agile project management be adopted by industries other than software development?.Project Management Journal,45(3), 21-34. Conger, S. 2015. Six sigma and business process management. InHandbook on Business Process Management 1(pp. 127-146). Springer, Berlin, Heidelberg. First, M. B. 2016. Adopting a continuous improvement model for future DSM revisions.World Psychiatry,15(3), 223-224. Heldman, K. 2015.PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley and Sons. Hornstein, H. A. 2015. The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298.
9PROJECT MANAGEMENT Joslin, R., and Müller, R. 2015. Relationships between a project management methodology and projectsuccessindifferentprojectgovernancecontexts.InternationalJournalofProject Management,33(6), 1377-1392. Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., and Villanueva, P. 2014. Project riskmanagementmethodologyforsmallfirms.InternationalJournalofProject Management,32(2), 327-340. Mir, F. A., and Pinnington, A. H. 2014. Exploring the value of project management: linking projectmanagementperformanceandprojectsuccess.Internationaljournalofproject management,32(2), 202-217. Sanchez, M. A. 2015. Integrating sustainability issues into project management.Journal of Cleaner Production,96, 319-330. Todorovic, M. L., Petrović, D. Č., Mihic, M. M., Obradovic, V. L., and Bushuyev, S. D. 2015. Projectsuccessanalysisframework:Aknowledge-basedapproachinproject management.International Journal of Project Management,33(4), 772-783.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT Appendices Appendix 1 WBSTask NameDurationStartFinishPredecessorsResource NamesCost 0 Updated schedule for Family relocation to Perth project 29 daysTue 1/1/19 Tue 1/29/19$15,000.00 M1 Milestone 1: Date selection and final relocation plan completed 0 daysThu 1/3/19 Thu 1/3/195Jeff and Kelly$0.00 M2 Milestone 2: Approving all plans 0 daysMon 1/21/19 Mon 1/21/1915,14$0.00 M3 Milestone 3: Truck reloading and final move to Perth 0 daysSun 1/27/19 Sun 1/27/1926Jeff and Kelly$0.00 M4 Milestone 4: Successful completion of project closure phase 0 daysTue 1/29/19 Tue 1/29/1932Jeff and Kelly$0.00 Appendix 2 WBSTask NameDurationStartFinishPredecessorsResource NamesCost 0 Updated schedule for Family relocation to Perth project 26.5 days Tue 1/1/19 Sun 1/27/19$15,000.00 1Project initialization3 daysTue 1/1/19 Thu 1/3/19$0.00 1.1Initial planning for 0.5 daysTue 1/1/19 Tue 1/1/19 Jeff and Kelly$0.00
11PROJECT MANAGEMENT relocation 1.2 Determine final date to relocate 0.5 daysTue 1/1/19 Tue 1/1/192Jeff and Kelly$0.00 1.3 consulting to the project planner and agent 1 dayWed 1/2/19 Wed 1/2/193Jeff and Kelly$0.00 1.4Confirmation of final date 1 dayThu 1/3/19 Thu 1/3/194Jeff and Kelly$0.00 M1 Milestone 1: Date selection and final relocation plan completed 0 daysThu 1/3/19 Thu 1/3/195Jeff and Kelly$0.00 2Planning17 daysFri 1/4/19 Sun 1/20/19$3,220.00 2.1Activities outlining1 dayFri 1/4/19 Fri 1/4/196Jeff and Kelly$0.00 2.2 Proper scheduling the activities 0.5 daysSat 1/5/19 Sat 1/5/198Jeff and Kelly$0.00 2.3 Consulting to doctor for Kelly's bad health 0.5 daysSat 1/5/19 Sat 1/5/199Jeff and Kelly$0.00 2.4 14 days bed rest in Maroochydore, on the Sunshine Coast, Qld 14 daysSun 1/6/19 Sun 1/20/1910SS+1 day Doctors fees[1],medicine cost[1] $220.00 2.5 Extending numbers of days in Sunshine Coast, Qld Apartment 0.5 daysSun 1/20/19 Sun 1/20/1911 additional accommodation cost[1] $2,800.00 2.6 Flight tickets booked on 29th night to Perth 0.5 daysFri 1/18/19 Fri 1/18/1912SF-2 daysJeff and Kelly$0.00 2.7Planning contingency0.5 daysFri 1/18/19 Fri 1/18/1913Project planner$100.00 2.8resource0.5 daysFriFri13Project planner, Jeff$100.00
12PROJECT MANAGEMENT allocation1/18/191/18/19and Kelly M2 Milestone 2: Approving all plans 0 daysFri 1/18/19 Fri 1/18/1915,14$0.00 3 Pre- relocation activity planning 6.5 daysSat 1/19/19 Fri 1/25/19$6,815.00 3.1 Recruiting movers and packers 0.5 daysSat 1/19/19 Sat 1/19/1916,9Jeff and Kelly$0.00 3.2 Selling the things that are not required 2 daysSat 1/19/19 Mon 1/21/1918Project planner$400.00 3.3 Pre- approval mortgage 1 dayMon 1/21/19 Tue 1/22/1919,9Others cost[1]$950.00 3.4Keeping Copious Notes0.5 daysTue 1/22/19 Tue 1/22/1920Jeff and Kelly$0.00 3.5 Relocating from the old apartment 0.5 daysWed 1/23/19 Wed 1/23/1921Jeff and Kelly$0.00 3.6 Contact to agent for truck service 0.5 daysWed 1/23/19 Wed 1/23/1922Jeff and Kelly$0.00 3.7 Truck send to garage near South Africa 0.5 daysWed 1/23/19 Wed 1/23/1922Logistic cost[1]$1,165.00 3.8Repairing of the Truck0.5 daysThu 1/24/19 Thu 1/24/1923,24Truck repairing cost[1]$1,800.00 3.9 Reloading truck with the belongings 1 dayThu 1/24/19 Fri 1/25/1925 Truck reloading and planning[1],Packaging Cost[1] $2,500.00 M3 Milestone 3: Truck reloading and final move to Perth 0 daysFri 1/25/19 Fri 1/25/1926Jeff and Kelly$0.00 4 Post Relocation activities 2 daysFri 1/25/19 Sun 1/27/19$4,965.00 4.1 Final arrival to new apartment in Perth 0.5 daysFri 1/25/19 Fri 1/25/1927Jeff and Kelly$0.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13PROJECT MANAGEMENT 4.2unloading Trucks0.5 daysSat 1/26/19 Sat 1/26/1929Logistic cost[1],Truck repairing cost[1]$2,965.00 4.3 Belongings unpacking and accommodating those 0.5 daysSat 1/26/19 Sat 1/26/1930Truck reloading and planning[1]$2,000.00 4.4Join School in Perth0.5 daysSun 1/27/19 Sun 1/27/1931Jeff and Kelly$0.00 M4 Milestone 4: Successful completion of project closure phase 0 daysSun 1/27/19 Sun 1/27/1932Jeff and Kelly$0.00 Appendix 3
14PROJECT MANAGEMENT Figure 1: Updated project Gantt chart (Source: Created by Author)