Running head: PROJECT MANAGEMENT
Project Management: Human Resource Management
Name of the student:
Name of the university:

1PROJECT MANAGEMENT
Table of Contents
1. Development of a human resource management plan.................................................................2
2. Creating a responsibility assessment matrix................................................................................4
3. Project closure and post implementation report..........................................................................5
3.1 End project report..................................................................................................................5
3.2 Project closure reflective report.............................................................................................7
4. Project evaluation report and post implementation report...........................................................7
4.1 Ongoing risks.........................................................................................................................8
5. Identification of findings and Lesson learned into future projects..............................................9
5.1 Control and tools..................................................................................................................10
6. Identification of skill development/training needs to be applied in HR communication and
stakeholder management...............................................................................................................10
References......................................................................................................................................11

2PROJECT MANAGEMENT
1. Development of a human resource management plan
The aim of the project is to upgrade the website destination for Archives’ Australia. In
order to accomplish the project successfully, the HR manager is required to hire professional,
skilled and experienced project team members. The website should have to be transferred to the
commonly available CMS from a proprietary. The procurement requests to redevelop, host and
maintain the services for the website development. Before the final implementation of the
website a project plan is developed with activities those are individually needed to be completed
within the estimated budget and time as well. The developed planning is given below:
Task Name Duration Start Finish Resource Names Cost
Human resource
management plan 130 days Mon 4/9/18 Fri 10/5/18 $17,232.00
Project initiation 30 days Mon 4/9/18 Fri 5/18/18 $4,832.00
Planning and
allocating human
resources to the project
5 days Mon 4/9/18 Fri 4/13/18 Project manager $560.00
Project feasibility
study 6 days Mon
4/16/18
Mon
4/23/18 Finance manager $480.00
Website analysis 8 days Tue 4/24/18 Thu 5/3/18 system analyst,
system developer $1,536.00
Contract with
service providers 7 days Tue 4/24/18 Wed 5/2/18 facility manager,
HR manager $1,120.00
Gathering
functional and non
functional
requirements
5 days Fri 5/4/18 Thu
5/10/18 Project manager $560.00
Identifying project
management tools and
other requirements
6 days Fri 5/11/18 Fri 5/18/18 system developer $576.00
Milestone 1:
Completio of project
initiation phase
0 days Fri 5/18/18 Fri 5/18/18 Project manager $0.00

3PROJECT MANAGEMENT
Project planning 58 days Mon
5/21/18 Wed 8/8/18 $7,824.00
Project scope
management plan 8 days Mon
5/21/18
Wed
5/30/18 facility manager $640.00
Quality
management plan 5 days Thu 5/31/18 Wed 6/6/18 Project
manager ,Sponsor $1,200.00
Communication
management plan 7 days Thu 6/7/18 Fri 6/15/18 HR manager $560.00
Allotting project
manager 6 days Mon
6/18/18
Mon
6/25/18 Sponsor $768.00
Hiring software
developer and software
analyst
3 days Mon
6/18/18
Wed
6/20/18 Project manager $336.00
Procurement
management planning 5 days Tue 6/26/18 Mon 7/2/18 Sponsor ,Project
manager $1,200.00
Facility
management planning 7 days Tue 7/3/18 Wed
7/11/18 HR manager $560.00
Training and
development program
planning
8 days Thu 7/12/18 Mon
7/23/18 HR manager $640.00
Team management
plan development 6 days Tue 7/24/18 Tue 7/31/18 facility manager,
Sponsor $1,248.00
Process
improvement planning 6 days Wed 8/1/18 Wed 8/8/18 Project manager $672.00
Milestone 2:
Completion of
project planning
phase
0 days Wed 8/8/18 Wed 8/8/18 Project manager $0.00
Project execution 27 days Thu 8/9/18 Fri 9/14/18 $3,056.00
Executing
management plan and
revision thereto
7 days Thu 8/9/18 Fri 8/17/18 system developer $672.00
Giving project
progress review 5 days Mon
8/20/18 Fri 8/24/18 system developer $480.00
Identifying project
team members 4 days Mon
8/27/18
Thu
8/30/18
Project
manager ,system
analyst
$832.00
Contract 5 days Fri 8/31/18 Thu 9/6/18 HR manager $400.00

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Human Resources: HR Planning, RAM Matrix, Closure Report, Project Evaluation
|12
|2910
|495

MANAGE HUMAN RESOURCE STRATEGIC PLANNING 6 6 MANAGE HUMAN RESOURCE STRATEGIC PLANNING
|5
|746
|342

Information System Project Management - Gantt Chart, Network Diagram, Milestones, Resource Table, Budget, RACI Table, Risk Register
|29
|5037
|199

Project Management for Moomba Festival Melbourne
|5
|625
|97

Project Management and System Engineering
|9
|1129
|34

Project Management qwertyuiopasdfghjklzxcvbnmqwertyuiopasdfghjklzxcvbnmqwertyuiopasdfghjklzxcvbnmqwertyuiopasdfghjklzxcvbnmqwertyuiopasdfghjklzxcvbnmqwertyuiop
|16
|3271
|96