Project Management
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Contents
PART 1: Project justification and structure.....................................................................................3
Introduction............................................................................................................................3
Project selection......................................................................................................................3
Project structure and skills......................................................................................................5
PART 2: Project documents.............................................................................................................6
Introduction............................................................................................................................6
Project brief and scope statement...........................................................................................6
WBS and Gantt chart..............................................................................................................7
Network diagram....................................................................................................................9
Stakeholder plan.....................................................................................................................9
Risk management plan.........................................................................................................10
Conclusion.....................................................................................................................................13
References......................................................................................................................................14
Appendix........................................................................................................................................15
Document Page
PART 1: Project justification and structure
Introduction
A project has a large number of actions that must be accomplished by the project team.
Project management is the process of planning, organizing, and controlling all of the activities.
The project manager is the individual who is in charge of overseeing all activities. The project
manager is responsible for ensuring that the project's goals and objectives are met and that the
project is completed efficiently while making the greatest use of available resources (Aliero and
et. al., 2021). The provided project report relates to the selection of appropriate home appliance
proposals for the business firm. The mentioned company operates with 20 stores for sales in the
UK and also provides after-sales services in Europe. This will be inclusive of selecting the
project based on rationales of quantitative as well as qualitative measures (Athanasiadis,
Papadopoulos and Doukas, 2021).
Project selection
The various project being available to the home appliance company including; Project
proposal 1- Smart (robot) vacuum cleaner, Project proposal 2- electric cattle, Project Proposal 3-
electric digital toaster and Project proposal 4- electric stand fan. The selection of the project was
done by using the following matrix table approach.
Must objectives Must meet if
impacts Proposal 1 Proposal 2 Proposal 3 Proposal 4 Proposal 5
Meets all legal, safety, energy-
consuming and environmental
standards
Y = yes
N = no
N/A = not
applicable
Y N Y Y Y
Receiving or eligible for CE marking Y = yes
N = no
N/A = not
applicable
Y N N N/A N
No adverse effect on other
operations (current and planned)
Y = yes
N = no
N/A = not
applicable
Y N N/A N/A N
Want objectives
Relative
Importance
1 - 100
Single project
impact
definitions
Weighted
Score
Weighted
Score
Weighted
Score
Weighted
Score
Weighted
Score
Document Page
Be nominated
for winning the UK’
home appliance
award of the Year
60
0 = No potential
1 = Low
potential
2 = High
potential
2 1 1 1 1
Create and attract
a strong media
attention 20
0 = No potential
1 = Low
potential
2 = High
potential
2 0 1 0 2
Time to market
50
0 = more than 1
year
1= between 7-
12 months
2 = less than 7
months
2 1 1 1 1
Generate profit
greater than 20% 80
0 < 20%
1 = 20-24%
2 >24%
2 1 0 0 0
Advance the state
of the art in home
appliances
innovation and
preserve the firm’s
reputation
40
0 = No impact
1 = Some impact
2 = Great impact
2 0 1 2 1
Provide the basis
for the
development of a
new home
appliance product
10
0 = No potential
1 = Low
potential
2 = High
potential
2 1 0 2 1
Total weighted score 3,120 1,040 1,040 1,560 1,560
Priority
From the analysis of the matrix table, Project proposal 1- Smart (robot) vacuum cleaner
was selected as observing weighted score of 3,120. In addition to this, there was greater ROI i.e.,
Return on Investment was being obtained which is also mentioned in the appendix of this report.
It suggests better profitability of the project work and guided better terms of operations when
operating in a business environment (Garg and et. al., 2021).
Project structure and skills
The structure and relative skills in a project firm is regulated through components of
project manager, project team, stakeholders and other important personnel participating in the
project. Each individuals body will follow particular duties and responsibilities in order to
efficiently implement the project in the firm (Heo and Kim, 2021). For the instance of a business
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
firm, the roles and responsibilities of various parties are outlined below in order to introduce the
selected quality assurance program for the customers’ support facing in the company:
Project manager: The project manager is a key player in the project's execution who is
the one in charge of effectively planning, executing, monitoring, regulating and closing out the
project. The project manager will be in charge of the whole project, including all resources and
financial requirements. The manager would guide his team toward the project's goals and
objectives.
Project team: The project team will be responsible for adhering to all of the project
manager's rules and procedures, as well as using all of their abilities to achieve the project's
objectives. They will also be responsible for contributing successfully to the project objectives
and planning of different project-related activities, as well as completing the tasks allocated to
them by the project manager and working to the quality standards required of them.
Stakeholders: The company's principal stakeholders will be accountable for preserving
the company's balance and performance. These could be inclusive sponsors of the project firm,
suppliers, customers, employees, managers, government and many such related individuals to the
project firm.
Top management: The project manager will get necessary project supervision from top
management, as well as the necessary resources. The provided element in the project structure is
guided by an appropriate skills-set to bind various project firm activities.
In the case of the home appliance company the Quality Assurance Program, the higher
authority, as well as the project sponsor of the chosen company, will be responsible for the scope
management and acceptance of the home appliance company’s project deliverables based on the
project implementation and feedback and input provided by the project manager and
stakeholders of the company (Holden, 2021).
PART 2: Project documents
Introduction
The term project document refers to proof of working criteria or the basis of the project
firm. Such documents are aimed at increasing the viability of the project firm and defining better
associated working in the business market. The provided project includes scope statement and
ensures the progress of the project through the development of the WBS and Gantt chart. In
Document Page
addition to this, an effective risk management plan was also drafted in for delivering better
efficiency of the project report (Iqbal and et. al., 2021).
Project brief and scope statement
The complete project scope statement for the home appliance company, to establish the
quality assurance program for customer support project, is mentioned below:
Description of the project's scope: The project scope is defined as a section of the project
plan that contains a complete analysis of the project goals and objectives that must be met in
order for the project to be implemented successfully. The goal of this initiative is to assist the
organization in maintaining its quality. It will aid in the implementation of a quality assurance
program for customer assistance.
Product acceptance criterion: A product acceptance criterion is a set of requirements that
a program must meet in order to be accepted by consumers. It can be a one-of-a-kind feature that
enables users or customers to accept it. In this project, the software will assist the organization in
managing its quality by assisting the team in managing and organizing their work, as well as
providing rigorous quality assurance for the customers' assistance by achieving the appropriate
requirements.
Project deliverables: They are the real and intangible goods and services created
throughout the project's successful completion. It might be a report, a paper, or any other type of
item. The project manager will document all of the project's requirements, and the project
deliverable will be a software program that will be implemented for quality assurance at the
chosen organization. The program will also be simple to use and dependable (Ji, Liao and Yang,
2021).
Project Exclusion: A project exclusion is a list of things, tasks, or activities that are not
included in the project scope. It can be a list of items that are supposed to be included but are not
clearly stated. The quantity of target systems or the speed characteristic are among the project
exclusions in this project.
Constraints of the project: Project constraints are described as limiting elements for a
project that might affect the quality and overall effective delivery of the project, perhaps leading
to project failure. Some of the most important restrictions in a project are:
Cost: One of the most important limitations for every project is cost. Completing the
project within the budget set by the project sponsors may sometimes put the project manager
Document Page
under pressure. The budget for the quality assurance software in this project was enough and
well-planned.
Time: Another restriction is time, which is one of the most prevalent constraints that the
project manager must deal with when completing the project, as time has a significant impact on
the project's quality. For this project, four months were allotted for implementation, which was
sufficient (Narendran and et. al., 2022).
Quality: The overall goal of this project is to assure the quality of the customer support
function; quality was successfully ensured throughout the project for improved results.
Scope: It outlined the project's specific requirements, such as what the project must accomplish.
The goal of this project was to introduce a program for quality assurance for customer support
operations.
Project assumptions: Project assumptions are the aspects of the project that are assumed
to be true or actual without any particular proof. Certain assumptions are critical for good project
planning. The list of assumptions that the project team and corporate stakeholders are working
under in order to finish the project comprises the following:
Resources: Consumers will be present to test at the times that they have agreed to, and
training rooms will be accessible as needed. A second software developer will also be present.
Delivery: The project servers are delivered fully configured.
Budget: The project cost will be as previously agreed, and any needed training will be
provided internally at no additional expense.
Scope: After receiving clearance from a higher authority, the project's scope will not alter.
WBS and Gantt chart
As the name implies, a work breakdown structure is one in which a project has been
broken down into smaller portions or tasks in order to finish it efficiently and on time. This
structure divides the tasks and assigns them to the best-suited team for the assignment, while also
keeping the overall project timeline in mind. This allows the project manager to set a target for
the staff, allowing the company to improve employee performance by looking for more efficient
ways to accomplish the project.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Document Page
Network diagram
Stakeholder plan
Stakeholder management is critical to the effective execution of a project. The presented
project plan necessitates a competent management strategy since it has a significant impact on
the influence and impact of numerous corporate stakeholders. This informs management that
they must develop appropriate methods to support project activities in accordance with the
project's planned outcomes (Rocha and et. al., 2021).
Risk management plan
Program managers have access to a number of techniques to assist them in monitoring
and resolving any issues and roadblocks. A risk register is an essential tool that task leaders use
to track and analyse threats that may influence their endeavors. Risk management is an essential
part of program administration because it helps the supervisor deal with deadlines and concerns
that may develop throughout the course of the program's execution. Risk management is crucial
for the current project of producing an entertainment smartphone application for retail firm in
order to protect the company from negative effects (Sharma and et. al., 2021). An example of a
risk registry is as follows:
Risk register
Risk Risk
Rating
Treatment/control methods Responsibility
Risks
associated
with time
planning
3 Durations and Network diagram scheduling
events might be used to manage the time spent
managing vulnerabilities. As a consequence,
Program
managing and
HRM division
Document Page
Risk Risk
Rating
Treatment/control methods Responsibility
employees will be more inclined to stick to
deadlines.
Risks related
to IP rights
3 The IT sector, as well as other suitable
authorities, shall get legislative authorization,
licenses, and trademark actions from the IT
office and other formal agencies that are
related to the home appliance company.
Law division
Risks
of assessment
and reporting
3 It is critical to effectively manage and report
all components so that they can assist in the
long term.
Program
managing
division
Functional
risks
5 There appear to be a lot of financial risks
linked with developing smartphone software
for the usage of recurrent Group events in
university; marketplace volatility is one of the
fiscal hazards that organizations face
throughout production since economic forces
affect them commercially. During economic
downturns, this is a common occurrence.
Program
managing
division
The risks of
technological
progression
4 There appear to be several technical concerns
whenever a program leader builds Smartphone
applications for use in university group events.
Technology would progress to a far greater
degree. Computerized systems have taken the
role of personal relationships.
IT division
Monetary risks 2 When a company is working on a project
involving smartphone software, they must
Fiscal division
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Risk Risk
Rating
Treatment/control methods Responsibility
collaborate on the firmware since operating
system development is expensive. They must
work together deftly so that they can produce
good apps for a fraction of the cost, with little
technological adjustments as the environment
evolves. They will be able to save money as a
result of this.
Risks
associated
with
effectiveness
assessment
4 The effectiveness evaluation must be
comprehensive, and the program leadership
group should take the required steps to
mitigate this risk.
Program
managing
division
Privacy risk 3 They must also concentrate on their budget
allocation for a single piece of technology that
is required for this program to run
successfully; if they have a clear strategy, the
organization will be able to effectively create
its core program. There appear to be a variety
of approaches to dealing with the technology
issue. Because we must update our application
with the most recent versions on a regular
basis to keep current with regulatory
obligations, login security is critical. To
improve the network's internet privacy, we
must also use information downloads that
include off-site backups (Wang and et. al.,
2021).
IT division
Risks to 4 To reduce this potential, a visual design Graphic
Document Page
Risk Risk
Rating
Treatment/control methods Responsibility
framework an
d function
business should be hired to provide numerous
possibilities for the layout and style of the user
smartphone app, which should proactively
engage learners (Wang and et. al., 2021).
division
The risk of a
dearth of
ability and
competence
5 This risk might be easily mitigated by
employing effective recruitment and
placement strategies, as the retail institution
program leadership group could hire young,
professional, and non-technical employees for
the project who are knowledgeable and
competent in the relevant field (Yatnalkar,
Gogate and Kotak, 2021).
HRM division
Conclusion
The above explanation leads to the conclusion that the project manager is critical to the
project's success. After the project manager receives the project they have two alternatives for
completing it or outsource it or do it with their team in a certain amount of time and within a
certain budget. In the instance of a home appliance company, they have opted to complete the
project on their own, using a variety of activities that are necessary to accomplish the project
effectively. The project manager is responsible for the project's personnel, resources, scope,
budget, and overall success or failure. The report involved the selection of a project out of
several options available which was done on the basis of suitability with the company’s
objectives and relevant operational standards.
Document Page
References
Books and Journals
Aliero, M.S., Qureshi, K.N., Pasha, M.F., Ghani, I. and Yauri, R.A., 2021. Systematic mapping
study on energy optimization solutions in smart building structure: Opportunities and
challenges. Wireless Personal Communications, 119(3), pp.2017-2053.
Athanasiadis, C.L., Papadopoulos, T.A. and Doukas, D.I., 2021. Real-time non-intrusive load
monitoring: A light-weight and scalable approach. Energy and Buildings, 253,
p.111523.
Garg, R., Kumar, P., Tomar, S., Deep, V. and Mehrotra, D., 2021. Voice assisted smart home
automation system.
Heo, S. and Kim, H., 2021. Toward load identification based on the hilbert transform and
sequence to sequence long short-term memory. IEEE Transactions on Smart
Grid, 12(4), pp.3252-3264.
Holden, C., 2021. Bitter harvest: housing conditions of migrant and seasonal farmworkers.
In The Human Cost of Food (pp. 169-195). University of Texas Press.
Iqbal, H.K., Malik, F.H., Muhammad, A., Qureshi, M.A., Abbasi, M.N. and Chishti, A.R., 2021.
A critical review of state-of-the-art non-intrusive load monitoring datasets. Electric
Power Systems Research, 192, p.106921.
Ji, X., Liao, B. and Yang, S., 2021. A variable neighborhood search algorithm for human
resource selection and optimization problem in the home appliance manufacturing
industry. Journal of Combinatorial Optimization, pp.1-19.
Narendran, P., Reddy, V., Saju, S., Suriya, L.U. and Ravi Kumar Pandi, V., 2022. Smart Home
with Condition Monitoring. In Inventive Communication and Computational
Technologies (pp. 653-667). Springer, Singapore.
Rocha, H.R., Honorato, I.H., Fiorotti, R., Celeste, W.C., Silvestre, L.J. and Silva, J.A., 2021. An
Artificial Intelligence based scheduling algorithm for demand-side energy
management in Smart Homes. Applied Energy, 282, p.116145.
Sharma, N., Mangla, M., Mohanty, S.N. and Satpathy, S., 2021, March. A Gesture based Remote
Control for Home Appliances. In 2021 8th International Conference on Computing
for Sustainable Global Development (INDIACom) (pp. 42-47). IEEE.
Wang, S., Chen, H., Guo, L. and Xu, D., 2021. Non-intrusive load identification based on the
improved voltage-current trajectory with discrete color encoding background and
deep-forest classifier. Energy and Buildings, 244, p.111043.
Wang, X., Jing, T., Yi, Z., Xie, Y., Li, D., Wang, S. and Zhai, Y., 2021, September. Two-Stage
Cooperative Operation Strategy for Home Management Systems with Smart
Appliances. In 2021 6th International Conference on Power and Renewable Energy
(ICPRE) (pp. 939-944). IEEE.
Yatnalkar, G., Gogate, V. and Kotak, V., 2021. Investigation on the Real Time Appliance
Management and Control System for Smart Home/Office Automation. Current
Approaches in Science and Technology Research Vol. 9, pp.120-134.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Appendix
Project proposal 1- Smart (robot) vacuum cleaner
chevron_up_icon
1 out of 14
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]