logo

Project Management Just For Project Managers

   

Added on  2022-08-18

31 Pages4694 Words10 Views
Running head: PROJECT MANAGEMENT
Project management plan
Name of the Student
Name of the University
Author’s Note

PROJECT MANAGEMENT
1
Table of Contents
1. Project Overview.........................................................................................................................2
1.1 Project background and description.......................................................................................2
1.2 Project scope..........................................................................................................................2
1.3 Key stakeholders....................................................................................................................3
1.4 High level timeline schedule.................................................................................................4
2. Business case...............................................................................................................................8
2.1 Executive summary...............................................................................................................8
2.2 Introduction............................................................................................................................8
2.3 Project scope..........................................................................................................................8
2.4 Inclusion................................................................................................................................9
2.5 Exclusion...............................................................................................................................9
2.6 Objectives..............................................................................................................................9
2.7 Key milestones.....................................................................................................................10
2.8 Deliverables.........................................................................................................................10
2.9 Technical resources.............................................................................................................11
2.10 Funding schedule...............................................................................................................11
2.11 Assumptions, constraints and risk management issues.....................................................13
2.12 Proposed solution and changes..........................................................................................14
2.13 Recommendations..............................................................................................................14
3. Risk mitigation...........................................................................................................................15
3.1 Executive summary.............................................................................................................15
3.2 Identified risks.....................................................................................................................15
3.3 Risk matrix...........................................................................................................................16
3.4 Risk management plan.........................................................................................................16
3.5 Risk tracking........................................................................................................................19
4. Project communication plan.....................................................................................................20
4.1 Project communication table...............................................................................................20
4.2 Team structure.....................................................................................................................23
5. Change management process.....................................................................................................24
5.1 Project closing executive summary.....................................................................................24
5.2 Scorecard.............................................................................................................................24
5.3 Methodologies and tools......................................................................................................27
Bibliography..................................................................................................................................29

PROJECT MANAGEMENT
2
1. Project Overview
1.1 Project background and description
JBH software solutions is a company that mainly aims to upgrade its total customer
service system so that they can be able to provide proper and efficient services to the customers.
In addition to this, the organization also wants to train the new associate during the progress of
the project. The upgradation of the entire system will be done in 24 months by using budget of
around $15 million. Moreover, in order to complete the system upgradation successfully, the
upper management of the organization is looking for proper guidance from the senior project
manager.
The project plan that is developed for the organization JBH software solutions in order to
upgrade its customer service system, it is necessary to include documentation including business
case, communication plan, scope statement, risk mitigation plan as well as project timeline.
Furthermore, the paper also elaborates different types of methodologies as well as tools that are
mainly utilized for successfully managing the project.
1.2 Project scope
The scope of the project is to upgrade the entire customer service system of JBH software
solutions for providing better services to the customers. Additionally, the project scope also
includes training sessions for the new associate of the organization during the time of project
progress. Furthermore, the upgradation of the system will need time span of 24 months starting
from 03-09-20 to 01-07-22.

PROJECT MANAGEMENT
3
1.3 Key stakeholders
Internal stakeholder
The internal stakeholders who are involved with the customer service system upgradation
are mainly listed below:
Management team
Customer service team
Project manager
IT team
Application manager
Database administrator
Tester
Financial manager
External stakeholder
The external stakeholders are listed below:
Data Warehouse
Sponsor

PROJECT MANAGEMENT
4
1.4 High level timeline schedule
The timeline schedule that is given below for upgrading the customer service system of
JBH software solution generally reflects on activities, sub activities, starting date, completion
date as well as project resources that are associated with the project.
WBS Task Name Duration Start Finish
Resource
Names
Cost
0
Customer service
system
upgradation for
JBH Software
Solutions
24 mons 3/9/2020 1/7/2022 $ 15,000,000.00
1 Initiation phase 4.85 mons 3/9/2020 7/21/2020 $ 46,280.00
1.1
Business case
development
22 days 3/9/2020 4/7/2020 Project manager $ 9,680.00
1.2
Feasibility
study
25 days 4/8/2020 5/12/2020
Financial
manager
$ 7,400.00
1.3
Establishment
of charter
30 days 5/13/2020 6/23/2020
Management
team, Project
manager
$ 22,800.00
1.4
Appointing
project team
1 mon 6/24/2020 7/21/2020
Management
team
$ 6,400.00
1.5 Milestone 1:
Completion of
0 days 7/21/2020 7/21/2020 $ 0.00

PROJECT MANAGEMENT
5
initiation phase
2 Planning phase 7.6 mons 7/22/2020 2/18/2021 $ 61,600.00
2.1
Development of
project plan
2 mons 7/22/2020 9/15/2020 Project manager $ 17,600.00
2.2
Resource plan
development
25 days 9/16/2020 10/20/2020
Management
team
$ 8,000.00
2.3 Financial plan 30 days 10/21/2020 12/1/2020
Financial
manager
$ 8,880.00
2.4
Development of
quality plan
27 days 12/2/2020 1/7/2021
Management
team
$ 8,640.00
2.5
Development of
risk management
plan
30 days 1/8/2021 2/18/2021
IT manager,
Management
team
$ 18,480.00
2.6
Milestone 2:
Completion of
planning phase
0 days 2/18/2021 2/18/2021 $ 0.00
3 Execution phase 10.5 mons 2/19/2021 12/9/2021 $ 14,880,640.00
3.1
Developing
design for the
upgraded system
45 days 2/19/2021 4/22/2021
Data Warehouse,
IT manager
$ 28,440.00
3.2 Coding 40 days 4/23/2021 6/17/2021 Application
manager,
Customer
$ 4,019,656.00

PROJECT MANAGEMENT
6
service team,
Software [1]
3.3
Database
development
30 days 6/18/2021 7/29/2021
Database
administrator
$ 9,360.00
3.4 Code validation 30 days 7/30/2021 9/9/2021
Application
manager, Data
Warehouse
$ 19,680.00
3.5
Adding project
features
45 days 9/10/2021 11/11/2021
IT manager,
Management
team, Hardware
[1]
$ 3,794,384.00
3.6
Training team
members
1 mon 11/12/2021 12/9/2021
Additional cost
[1], Trainer
$ 7,005,920.00
3.7 Testing 10 days 11/12/2021 11/25/2021 Sponsor, Tester $ 3,200.00
3.8
Milestone 3:
Completion of
execution phase
0 days 11/25/2021 11/25/2021 $ 0.00
4 Closure phase 1.55 mons 11/26/2021 1/7/2022 $ 11,480.00
4.1
Post project
review
10 days 11/26/2021 12/9/2021 Project manager $ 4,400.00
4.2
Stakeholder
sign off
2 days 12/10/2021 12/13/2021
Management
team
$ 640.00
4.3 Documentation 15 days 12/14/2021 1/3/2022 Customer $ 4,680.00

PROJECT MANAGEMENT
7
service team
4.4
Releasing
stakeholders
4 days 1/4/2022 1/7/2022 Project manager $ 1,760.00
4.5
Milestone 4:
Completion of
closure phase
0 days 1/7/2022 1/7/2022 $ 0.00
2. Business case
2.1 Executive summary
The paper mainly focuses on the upgradation of customer service system for JBH
software system. It is found that the company also wants to provide training facility to the new
associates during the time of project progress. The business case which is developed for the
project generally reflects introduction, project scope, objectives, key milestones as well as
different types of resource related requirements so that the project manager can use such
information and details during the execution of the project.
2.2 Introduction
Project name: Upgradation of customer service system for JBH software solutions
Project sponsor/ Executive: CEO of JBH software system
Project manager: <Please fill>
2.3 Project scope
JBH Software solutions undertakes customer service system upgradation within 24
months and it is found that the project will commence on 8th March 2020 and will get completed
by 7th January 2022. The amount of money that is required for upgrading the customer system

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management Task Assessment
|25
|3584
|13

ICT Project Management: Description, Scope, and Stakeholder Expectations
|22
|2579
|383

Education Management System for Maths Classes
|28
|6321
|281

Project Management Plan for Globex Corporation
|13
|2065
|375

Information Technology – Software Upgrade Project Proposal
|14
|2698
|68

Queensland Health Payroll System Project Management Plan
|29
|6487
|332