Project Management: B&W Systems Case Study Solution
VerifiedAdded on 2023/04/11
|6
|625
|145
Project
AI Summary
This document presents a project management solution for a case study involving B&W Systems and the development of an internet-based forecasting system. The solution addresses key project management aspects, including scheduling, cost analysis, and project crashing. The assignment begi...

Running head: PROJECT MANAGEMENT
Project Management
Name of the Student:
Name of the University:
Project Management
Name of the Student:
Name of the University:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Question 3
a) Additional cost for reducing the project time to required 35 weeks
The expected time required for each task is calculated as:
Expected time = (Most optimistic time+4*most likely time + most pessimistic time) /6
Task
Most
optimistic
time
Most likely
time
Most
pessimistic time
Expecte
d time
A 2 3 4 3.00
B 4 7 10 7.00
C 5 6 9 6.33
D 6 7 16 8.33
E 7 9 10 8.83
F 4 5 6 5.00
G 3 6 10 6.17
H 2 4 7 4.17
I 2 2 2 2.00
J 3 4 14 5.50
K 2 3 4 3.00
Question 3
a) Additional cost for reducing the project time to required 35 weeks
The expected time required for each task is calculated as:
Expected time = (Most optimistic time+4*most likely time + most pessimistic time) /6
Task
Most
optimistic
time
Most likely
time
Most
pessimistic time
Expecte
d time
A 2 3 4 3.00
B 4 7 10 7.00
C 5 6 9 6.33
D 6 7 16 8.33
E 7 9 10 8.83
F 4 5 6 5.00
G 3 6 10 6.17
H 2 4 7 4.17
I 2 2 2 2.00
J 3 4 14 5.50
K 2 3 4 3.00

2PROJECT MANAGEMENT
Activity graph
Task
Expecte
d time
Earliest
start
time
Earliset
finish
time
Latest
start
time
Latest
finish
time Slack
A 3.00 0.00 3.00 0.00 3.00 0.00
B 7.00 3.00 10.00 19.50 26.50 16.50
C 6.33 3.00 9.33 3.00 9.33 0.00
D 8.33 9.33 17.67 9.33 17.67 0.00
E 8.83 17.67 26.50 17.67 26.50 0.00
F 5.00 26.50 31.50 26.50 31.50 0.00
G 6.17 17.67 23.83 25.33 31.50 7.67
H 4.17 26.50 30.67 27.33 31.50 0.83
I 2.00 10.00 12.00 29.50 31.50 19.50
J 5.50 31.50 37.00 31.50 37.00 0.00
K 3.00 37.00 40.00 37.00 40.00 0.00
Figure 1: Activity graph
(Source: Created by author)
Additional cost for reducing the project time to required 35 weeks is shown in following
table as:
Activity graph
Task
Expecte
d time
Earliest
start
time
Earliset
finish
time
Latest
start
time
Latest
finish
time Slack
A 3.00 0.00 3.00 0.00 3.00 0.00
B 7.00 3.00 10.00 19.50 26.50 16.50
C 6.33 3.00 9.33 3.00 9.33 0.00
D 8.33 9.33 17.67 9.33 17.67 0.00
E 8.83 17.67 26.50 17.67 26.50 0.00
F 5.00 26.50 31.50 26.50 31.50 0.00
G 6.17 17.67 23.83 25.33 31.50 7.67
H 4.17 26.50 30.67 27.33 31.50 0.83
I 2.00 10.00 12.00 29.50 31.50 19.50
J 5.50 31.50 37.00 31.50 37.00 0.00
K 3.00 37.00 40.00 37.00 40.00 0.00
Figure 1: Activity graph
(Source: Created by author)
Additional cost for reducing the project time to required 35 weeks is shown in following
table as:
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
Task
Expecte
d time
Crash
time
(weeks)
Max
numbe
r of
crashes
Normal
cost ($)
Crash
cost ($)
Crash
increas
e
Crash
cost per
week ($)
Numbe
r of
week
cashed
Crashing
cost ($)
A 3.00 3 0 10,000 10,000 0 0 0 0
B 7.00 6 1.00 20,000 25,000 5,000 5000 0 0
C 6.33 5 1.33 15,000 30,000 15,000 11278.2 0.67 7,500
D 8.33 6 2.33 45,000 65,000 20,000 8583.691 2.33 20000
E 8.83 8 0.83 10,000 20,000 10,000 12048.19 0 0
F 5.00 4 1.00 15,000 18,000 3,000 3000 1 3000
G 6.17 4 2.17 20,000 30,000 10,000 4608.295 0 0
H 4.17 3 1.17 10,000 15,000 5,000 4273.504 0.17 714.285
I 2.00 2 0.00 5,000 5,000 0 0 0 0
J 5.50 5 0.50 40,000 50,000 10,000 20000 0 0
K 3.00 2 1.00 15,000 25,000 10,000 10000 1 10000
5.17 41214.285
The additional cost is: $41,214.85.
b) Specific tasks recommend crashing in order to achieve the milestone
Task
Expecte
d time
Crash
time
(weeks)
Max
numbe
r of
crashes
Normal
cost ($)
Crash
cost ($)
Crash
increas
e
Crash
cost per
week ($)
Numbe
r of
week
cashed
A 3.00 3 0 10,000 10,000 0 0 0
B 7.00 6 1.00 20,000 25,000 5,000 5000 0
C 6.33 5 1.33 15,000 30,000 15,000 11278.2 0.67
D 8.33 6 2.33 45,000 65,000 20,000 8583.691 2.33
E 8.83 8 0.83 10,000 20,000 10,000 12048.19 0
F 5.00 4 1.00 15,000 18,000 3,000 3000 1
G 6.17 4 2.17 20,000 30,000 10,000 4608.295 0
H 4.17 3 1.17 10,000 15,000 5,000 4273.504 0.17
I 2.00 2 0.00 5,000 5,000 0 0 0
J 5.50 5 0.50 40,000 50,000 10,000 20000 0
K 3.00 2 1.00 15,000 25,000 10,000 10000 1
5.17
Task
Expecte
d time
Crash
time
(weeks)
Max
numbe
r of
crashes
Normal
cost ($)
Crash
cost ($)
Crash
increas
e
Crash
cost per
week ($)
Numbe
r of
week
cashed
Crashing
cost ($)
A 3.00 3 0 10,000 10,000 0 0 0 0
B 7.00 6 1.00 20,000 25,000 5,000 5000 0 0
C 6.33 5 1.33 15,000 30,000 15,000 11278.2 0.67 7,500
D 8.33 6 2.33 45,000 65,000 20,000 8583.691 2.33 20000
E 8.83 8 0.83 10,000 20,000 10,000 12048.19 0 0
F 5.00 4 1.00 15,000 18,000 3,000 3000 1 3000
G 6.17 4 2.17 20,000 30,000 10,000 4608.295 0 0
H 4.17 3 1.17 10,000 15,000 5,000 4273.504 0.17 714.285
I 2.00 2 0.00 5,000 5,000 0 0 0 0
J 5.50 5 0.50 40,000 50,000 10,000 20000 0 0
K 3.00 2 1.00 15,000 25,000 10,000 10000 1 10000
5.17 41214.285
The additional cost is: $41,214.85.
b) Specific tasks recommend crashing in order to achieve the milestone
Task
Expecte
d time
Crash
time
(weeks)
Max
numbe
r of
crashes
Normal
cost ($)
Crash
cost ($)
Crash
increas
e
Crash
cost per
week ($)
Numbe
r of
week
cashed
A 3.00 3 0 10,000 10,000 0 0 0
B 7.00 6 1.00 20,000 25,000 5,000 5000 0
C 6.33 5 1.33 15,000 30,000 15,000 11278.2 0.67
D 8.33 6 2.33 45,000 65,000 20,000 8583.691 2.33
E 8.83 8 0.83 10,000 20,000 10,000 12048.19 0
F 5.00 4 1.00 15,000 18,000 3,000 3000 1
G 6.17 4 2.17 20,000 30,000 10,000 4608.295 0
H 4.17 3 1.17 10,000 15,000 5,000 4273.504 0.17
I 2.00 2 0.00 5,000 5,000 0 0 0
J 5.50 5 0.50 40,000 50,000 10,000 20000 0
K 3.00 2 1.00 15,000 25,000 10,000 10000 1
5.17
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
The activities to crash for achieving the project milestone is:
C- 0.67 weeks
D- 2.33 weeks
F- 1 week
H- 0.17 weeks
K- 1 week
The activities to crash for achieving the project milestone is:
C- 0.67 weeks
D- 2.33 weeks
F- 1 week
H- 0.17 weeks
K- 1 week

5PROJECT MANAGEMENT
Bibliography
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Bibliography
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 6

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.