Additional Cost for Reducing Project Time to Required 35 Weeks

Verified

Added on  2023/04/11

|6
|625
|145
AI Summary
This document discusses the calculation of additional cost for reducing the project time to the required 35 weeks. It also provides recommendations on specific tasks that need to be crashed in order to achieve the milestone. The document includes a table showing the expected time, crash time, normal cost, crash cost, crash increase, crash cost per week, and number of weeks crashed for each task. The additional cost is calculated to be $41,214.85.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Project Management
Name of the Student:
Name of the University:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Question 3
a) Additional cost for reducing the project time to required 35 weeks
The expected time required for each task is calculated as:
Expected time = (Most optimistic time+4*most likely time + most pessimistic time) /6
Task
Most
optimistic
time
Most likely
time
Most
pessimistic time
Expecte
d time
A 2 3 4 3.00
B 4 7 10 7.00
C 5 6 9 6.33
D 6 7 16 8.33
E 7 9 10 8.83
F 4 5 6 5.00
G 3 6 10 6.17
H 2 4 7 4.17
I 2 2 2 2.00
J 3 4 14 5.50
K 2 3 4 3.00
Document Page
2PROJECT MANAGEMENT
Activity graph
Task
Expecte
d time
Earliest
start
time
Earliset
finish
time
Latest
start
time
Latest
finish
time Slack
A 3.00 0.00 3.00 0.00 3.00 0.00
B 7.00 3.00 10.00 19.50 26.50 16.50
C 6.33 3.00 9.33 3.00 9.33 0.00
D 8.33 9.33 17.67 9.33 17.67 0.00
E 8.83 17.67 26.50 17.67 26.50 0.00
F 5.00 26.50 31.50 26.50 31.50 0.00
G 6.17 17.67 23.83 25.33 31.50 7.67
H 4.17 26.50 30.67 27.33 31.50 0.83
I 2.00 10.00 12.00 29.50 31.50 19.50
J 5.50 31.50 37.00 31.50 37.00 0.00
K 3.00 37.00 40.00 37.00 40.00 0.00
Figure 1: Activity graph
(Source: Created by author)
Additional cost for reducing the project time to required 35 weeks is shown in following
table as:
Document Page
3PROJECT MANAGEMENT
Task
Expecte
d time
Crash
time
(weeks)
Max
numbe
r of
crashes
Normal
cost ($)
Crash
cost ($)
Crash
increas
e
Crash
cost per
week ($)
Numbe
r of
week
cashed
Crashing
cost ($)
A 3.00 3 0 10,000 10,000 0 0 0 0
B 7.00 6 1.00 20,000 25,000 5,000 5000 0 0
C 6.33 5 1.33 15,000 30,000 15,000 11278.2 0.67 7,500
D 8.33 6 2.33 45,000 65,000 20,000 8583.691 2.33 20000
E 8.83 8 0.83 10,000 20,000 10,000 12048.19 0 0
F 5.00 4 1.00 15,000 18,000 3,000 3000 1 3000
G 6.17 4 2.17 20,000 30,000 10,000 4608.295 0 0
H 4.17 3 1.17 10,000 15,000 5,000 4273.504 0.17 714.285
I 2.00 2 0.00 5,000 5,000 0 0 0 0
J 5.50 5 0.50 40,000 50,000 10,000 20000 0 0
K 3.00 2 1.00 15,000 25,000 10,000 10000 1 10000
5.17 41214.285
The additional cost is: $41,214.85.
b) Specific tasks recommend crashing in order to achieve the milestone
Task
Expecte
d time
Crash
time
(weeks)
Max
numbe
r of
crashes
Normal
cost ($)
Crash
cost ($)
Crash
increas
e
Crash
cost per
week ($)
Numbe
r of
week
cashed
A 3.00 3 0 10,000 10,000 0 0 0
B 7.00 6 1.00 20,000 25,000 5,000 5000 0
C 6.33 5 1.33 15,000 30,000 15,000 11278.2 0.67
D 8.33 6 2.33 45,000 65,000 20,000 8583.691 2.33
E 8.83 8 0.83 10,000 20,000 10,000 12048.19 0
F 5.00 4 1.00 15,000 18,000 3,000 3000 1
G 6.17 4 2.17 20,000 30,000 10,000 4608.295 0
H 4.17 3 1.17 10,000 15,000 5,000 4273.504 0.17
I 2.00 2 0.00 5,000 5,000 0 0 0
J 5.50 5 0.50 40,000 50,000 10,000 20000 0
K 3.00 2 1.00 15,000 25,000 10,000 10000 1
5.17

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
The activities to crash for achieving the project milestone is:
C- 0.67 weeks
D- 2.33 weeks
F- 1 week
H- 0.17 weeks
K- 1 week
Document Page
5PROJECT MANAGEMENT
Bibliography
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
1 out of 6
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]