Project Management Plan (PMP) Mobile Application Development <Course Number and Name> Prepared By <Names> <Date> Example – Communications Planv1.0.1Page1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Management Plan (PMP) 1.Executive Summary.............................................................................................3 1.1 Introduction.........................................................................................................................3 1.2 Purpose...............................................................................................................................3 1.3 Scope.................................................................................................................................3 2. Project Overview..................................................................................................4 2.1...Project Description............................................................................................................4 2.2...Problem Statement............................................................................................................4 2.3...Goals...............................................................................................................................4 2.4...Project Background...........................................................................................................5 2.5...Product Objectives............................................................................................................5 2.6...Assumptions, Constraints and Dependencies........................................................................6 2.7...Project Deliverables..........................................................................................................6 2.8...Schedule and Budget Summary..........................................................................................7 2.9...Evolution of the Plan.........................................................................................................7 2.10 Definitions and Acronyms...................................................................................................7 3.Stakeholder Register.............................................................................................9 References.............................................................................................................11 Example – Communications Planv1.0.1Page2
Project Management Plan (PMP) 1.Executive Summary 1.1 Introduction The document is a Project Management Plan (PMP) that is prepared for a software development project. The project is the development of a mobile application for a banking firm. The mobile application will be developed for iOS as well as Android platforms. The banking firm is in its expansion phase and there are numerous activities that need to be upgraded. It is essential for the firm to incorporate the latest technologies to gain competitive edge in the market. The primary aim of the project is to provide the organization with the same by streamlining all the business operations and improving the customer relations through the mobile application. The PMP includes the guidelines for the management of various project areas. 1.2 Purpose The purpose of the plan is to provide the managers and project leaders with the guidelines to manage the project activities. 1.3 Scope The scope of the document includes the coverage of project management details in the areas as project overview, project stakeholders, schedule, resources, costs, and major project areas. Example – Communications Planv1.0.1Page3
Project Management Plan (PMP) 2. Project Overview 2.1Project Description The project includes the development of a mobile application for a banking firm. The firm is in the expansion phase and there will be an increase in the business processes and operations with the expansion of the business. It will be essential for the banking firm to make use of the technology to reach out to a maximum number of customers and to streamline the business operations. The project will include the development and deployment of a mobile application for the organization that will run on both iOS and Android platforms. 2.2Problem Statement The organization is a small-scale banking firm and it needs to expand its business operations and develop enhanced customer base. Mobile applications are desired by every customer in the present scenario and the absence of the same may appear as a barrier for the organization in its professional and business growth. The development of the mobile application will provide the organization with a competitive edge in the market (Matos & Lopes, 2013). 2.3Goals The goal of the project is to adhere to the estimated schedule, time, and scope to design, develop, and deploy a mobile application for the banking firm. Example – Communications Planv1.0.1Page4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project Management Plan (PMP) 2.4Project Background The project is a software development project that is being carried out for a banking firm. The firm is a small-scale organization that is in its expansion phase. The project will include the design, development, and deployment of the mobile application for the organization. The application will be used by the employees and stakeholders of the banking firm. It will allow the employees to manage customer relations and streamline the business operations (Joslin & Muller, 2015). The data management and handling services will also become easier. The project will follow the software development lifecycle by covering the phases, such as planning, requirements analysis, design, development, testing & deployment, implementation, and closure. The project will overcome the current issues at the banking firm in terms of the inability to streamline the business operations and challenges in data management. The customer relations will also improve with the deployment of the application. 2.5Product Objectives The following objectives will be fulfilled by the mobile application that is being developed: To incorporate the functional, non-functional, and user requirements & specifications that have been defined for the application. To make sure that information security and privacy is maintained at all times (Rose, 2013). To adhere to the estimates and quality standards To make sure that the resources in the project team and the project activities that are carried out are in compliance with the regulatory, legal, and ethical policies. Example – Communications Planv1.0.1Page5
Project Management Plan (PMP) 2.6Assumptions, Constraintsand Dependencies The following assumptions and constraints have been considered for the project: The resources will remain available for 40 hours in a week The absenteeism rate for the resources will be low The project client will provide the funds for the execution of the project activities The project will be required to be completed in a total timeframe of 351 days. The total costs allotted to the project are $345,500 and the same shall be adhered during the project timeline. The environment set-up for the project will be successfully done to provide the resources with the platform to carry out the project tasks and activities (Fanning, 2014). 2.7Project Deliverables Project Charter: Document describing the project highlights and the results of feasibility determination. Project Plan: A detailed description of the project guidelines to manage various project areas. Requirements Document: Description of the requirements in the categories as functional, non-functional, and user. Design Document: Document comprising of the system design diagrams, wireframes, and UI aspects. Source code: The source code of the mobile application (Morris, 2010). Test Plan: Detailed description of the testing activities to be carried out along with the details of test tool and responsibilities. The details of the defect logging process will also be mentioned in the plan. Defect Report: Summary of the defects that are reported by the test team along with the status of each defect. Closure Report: The final report submitted for the project that will mark the end of the project. It will include the details of the project activities carried out, performance evaluation results, and lessons acquired with areas of improvement. Example – Communications Planv1.0.1Page6
Project Management Plan (PMP) 2.8Schedule and Budget Summary The total duration of the project that is estimated is 351 days. The start date of the project is 1stFebruary 2019 and the end date is 5th June 2020. The total costs that are estimated for the project are $345,220. The schedule and budget includes all the project activities along with the cost of the materials as well as the resources. The project costs cover the cost of project designing, planning, development, testing, implementation, and closure. The probable risks and changes to the project have been considered while estimating the project schedule and costs (Radujkovic & Sjekavica, 2017). The technique that has been used to estimate the values of project schedule and project costs is bottom-up project estimations. 2.9Evolution of the Plan The project management plan prepared for the project is carried out in phases. The initiation and planning phase are the project phases that are carried out first and the project plan is prepared in these phases. The plan involves the guidelines for the project areas, such as project scope, schedule, costs, resources, stakeholders, risks, communication, and changes. The details from the initiation phase were referred to prepare the project plan in the project planning phase. There were changes that were made in the project plan. The changes were carried out in the execution, control, and closure phases for the project. 2.10 Definitions and Acronyms PMP: Project Management Plan Example – Communications Planv1.0.1Page7
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Management Plan (PMP) UI: User Interface Example – Communications Planv1.0.1Page8
Project Management Plan (PMP) 3.Stakeholder Register Example – Communications Planv1.0.1Page9
Project Management Plan (PMP) References Fanning,F.(2014).AdaptingPMBoKGuidancetoPublicSectorProjects.Organization,TechnologyAndManagementIn Construction: An International Journal,6(3). doi: 10.5592/otmcj.2014.3.3 Joslin, R., & Muller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts.International Journal Of Project Management,33(6), 1377-1392. doi: 10.1016/j.ijproman.2015.03.005 Matos,S.,&Lopes,E.(2013).Prince2orPMBOK–AQuestionofChoice.ProcediaTechnology,9,787-794.doi: 10.1016/j.protcy.2013.12.087 Morris, P. (2010). Research and the future of project management.International Journal Of Managing Projects In Business,3(1), 139-146. doi: 10.1108/17538371011014080 Radujkovic, M., & Sjekavica, M. (2017). Development of a project management performance enhancement model by analysing risks, changes,andlimitations.JournalOfTheCroatianAssociationOfCivilEngineers,69(02),105-120.doi: 10.14256/jce.1866.2016 Rose, K. (2013). A Guide to the Project Management Body of Knowledge (PMBOK® Guide)-Fifth Edition.Project Management Journal,44(3), e1-e1. doi: 10.1002/pmj.21345 Example – Communications Planv1.0.1Page10