Project management plan
Task Name Duration Start Finish Predecessors
Research Project 3 days Wed 6/6/18 Fri 6/8/18
Preparation phase of
ERP plan 3 days Wed 6/6/18 Fri 6/8/18
Choosing a theme or
subject 2 days Wed 6/6/18 Thu 6/7/18
Defining project scope and
objectives 1 day Wed 6/6/18 Wed 6/6/18
Select subject or
problematic in carrying
out installation
1 day Mon 6/11/18 Mon 6/11/18 1
Stakeholders 1 day Wed 6/6/18 Wed 6/6/18
Location period 1 day Mon 6/11/18 Mon 6/11/18 1,2
Price examining 1 day Fri 6/8/18 Fri 6/8/18 3
Distribution of reserve 1 day Thu 6/7/18 Thu 6/7/18 4
Application step of
development 3 days Wed 6/6/18 Fri 6/8/18
Technical infrastructure
preparation 4 days Tue 6/12/18 Fri 6/15/18 5
Identifying development
environment 4 days Tue 6/12/18 Fri 6/15/18 5
Quality assurance
environment 2 days Tue 6/12/18 Wed 6/13/18 6,7
Training environment 2 days Mon 6/11/18 Tue 6/12/18 8
Business blueprint 1 day Fri 6/8/18 Fri 6/8/18 9
AS-IS business process
analysis 1 day Wed 6/6/18 Wed 6/6/18
Identifying end to end
current business process 3 days Mon 6/11/18 Wed 6/13/18 10
Identify process
integration point 1 day Mon 6/18/18 Mon 6/18/18 11
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Mapping ERP process to
business 3 days Mon 6/18/18 Wed 6/20/18 12,13
Defining TO-BE process 1 day Wed 6/13/18 Wed 6/13/18 14
Configuration of system
according to design from
business blueprint.
3 days Wed 6/13/18 Fri 6/15/18 14,15
Configure solution 1 day Thu 6/7/18 Thu 6/7/18 16
Write units test script 2 days Thu 6/14/18 Fri 6/15/18 17
Configure solution 2 days Tue 6/19/18 Wed 6/20/18 17,18
Unit test configuration 4 days Thu 6/21/18 Tue 6/26/18 18,19
Concluding point of ERP
project 1 day Tue 6/19/18 Tue 6/19/18 18
Portrayal the valid
assumption 5 days Thu 6/21/18 Wed 6/27/18 19,20
Providing effective
endorsements 4 days Thu 6/14/18 Tue 6/19/18 20
Certification of assignment 4 days Thu 6/14/18 Tue 6/19/18 20
Submission the ready
project 4 days Mon 6/18/18 Thu 6/21/18 21
Document Page
Figure 1: Gantt chart
Figure 2: Gantt chart
Document Page
Figure 3: Network Diagram
[Source: The Project Management Plan (PMP), 2018]