Running head: PROJECT MANAGEMENT PLANNING
Project Management Planning Assignment
Name of the University:
Course name:
Project name: Dream Home construction Project plan
The date submitted:

1PROJECT MANAGEMENT PLANNING
Table of Contents
Project Background.........................................................................................................................2
Project Scope...................................................................................................................................3
Work Breakdown Structure.............................................................................................................4
WBS dictionary...............................................................................................................................6
Project Gantt chart...........................................................................................................................7
Critical Path Network Diagram.....................................................................................................10
Risk management plan...................................................................................................................10
Quality management plan..............................................................................................................13
Communication management plan................................................................................................16
Human Resource management plan..............................................................................................20
RAM..........................................................................................................................................21
Project Budget...............................................................................................................................22
References......................................................................................................................................28

2PROJECT MANAGEMENT PLANNING
Project Background
Stagnant wages as well as inflating range of home prices are these days becoming a
major issue in Canada. In other words the affordability for homes is becoming unattainable day
by day. However, the rate of population in industrial area are rapidly increasing and thus people
with high income in Canada are looking for constructing dream home in a dream riverfront
location. The dream home that is planned to construct in this paper is located in Windsor city,
Ontario, Canada. The land price of Windsor city, Ontario, Canada is these days running low and
thus, the owners has planned to construct the home.
Before initiating the project a detail project scope, WBS, Gantt chart, network diagram
using CPM, risk management plan, quality management plan, communication management,
human resource management and project budget management plan are elaborated in this paper.
In order to begin the dream home construction project the owner established a contract with a
building contractor. It is determined that, the builder will share a project status report
periodically to the other project team associates. Real estate agent will help the owner to select
the location. Once the paper works, government permission and other final documents are clearly
done, the construction work will be initiated.
Project Scope
The scope of the project is to construct a dream home in a riverfront location of Windsor
city, Ontario, Canada. The budget and time estimated for the dream home construction work are
$300,000 and 14 months. Therefore, the aim of the contractors and other construction
stakeholders are to complete the work within estimated timeline and budget only. The budget

3PROJECT MANAGEMENT PLANNING
specified for the project is enough. The amount of pollution in Canada is lesser than any other
neighbourhood countries and in order to maintain the pollution free environmental balance in the
riverside location the home is planned to build considering green building concept. In order to
build the green home precious natural green resources are considered so that both climatic and
quality of life gets improved. The builders and contractors will use renewable resource in terms
of solar energy. It is duty of the construction manager to use the natural renewable resources
effectively and efficiently to enable its usability. It would help to keep the indoor environment
pollution free. The materials those are used for construction of a green home include non toxic,
ethical and sustainable materials. The design will enable adaption for changing the overall
environment. In order to complete the construction works both technical and non technical
experts are required. It is assumed that successful completion of the dream home construction
work will meet expectation of clients and give positive, pollution free environment.
For this project a scope baseline in terms of a benchmark or reference must be considered
by the project manager and maintained by team throughout the project development life cycle
period. The scope for the dream home construction project holds a WBS dictionary and a detail
document. Project scope has to be formally approved by the construction lead and project
sponsor. The scope set for this project can be changed through different forma control
procedures.
Work Breakdown Structure
WBS item Dependencies Duration Assigned
resources
1.1 Landscaping

4PROJECT MANAGEMENT PLANNING
1.1.1 Site selection Site supervision and
government permission
2 2
1.1.2 Feasibility analysis and timeline setup 1.1.1 2 5
1.1.3 Addition of ornamental features through
tree plantation
1.1.2 6 3
1.2 House structure
1.2.1 Concrete 1.1.1 5 1
1.2.2 Floor, slab and roof structure
presentation
1.3.2 8 1
1.2.3 Selecting best construction tools 1.3.2 4 2
1.3 Inside work
1.3.1 Excavation and PCC 1.1.1 4 3
1.3.2 Installing tiles 1.1.3, 1.6.1 4 8
1.3.3 Complete drywall and exterior design 1.2.2, 1.2.3, 1.4.3,
1.5.2
2 1
1.4 Infrastructure
1.4.1 Windows and doors framing 1.6.1 5 3
1.4.2 Painting and Tile setting 1.3.2, 1.4.1, 1.5.1 3 6
1.4.3 Plumbing and electricity installation 1.4.2, 1.5.2 3 2
1.5 Management
1.5.1 Communication management plan 1.6.1 4 4
1.5.2 Human resource management plan 1.5.1 2 1
1.5.3 Quality management plan 1.5.2 4 8

5PROJECT MANAGEMENT PLANNING
1.6 Others
1.6.1 Inspection 1.1.2, 1.2.1, 1.3.1 2 2
1.6.2 Milestone 1: Completion of pre
construction and construction stage
1.4.2 0 0
1.6.3 Milestone 2: Completion of project
construction stage
1.2.2, 1.3.3, 1.4.3 0 0
WBS dictionary
i. Task name Design and construction of a dream home in Canada
ii. Task assumption
It is assumed that, the construction task has to be competed in bank approved given
budget rate of $300,000.
iii. Task constraints
The project is divided into 6 phases: landscape, house construction, inside work,
infrastructure, management and others. Triple project constraints in terms of scope, budget and
time for the individual phases are considered in this project. The budget for the 6 respective
phases are – $80000, $70, 000, $60,000 $45, 000, $10,000 and $30,000.
iv. Task project requirements:
The requirement examples needed for the project are as follows:
Smart home building equipments and appliances
Green home building appliances

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
The Building of dream home
|16
|3164
|20

Analysis of Construction Project Cost Management
|12
|3528
|20

Leading Lean Projects: Implementing lean project management to build your dream home
|13
|3867
|59

Leading Lean Projects
|12
|3513
|51

Implementing Lean Project Management for Dream Home Construction
|14
|3963
|445

Project Management: WBS, OBS, RAM, Gantt Chart, Risk Register
|11
|1372
|427