Project Management Risk Management Quiz

   

Added on  2023-06-11

4 Pages977 Words391 Views
1. Three common risk categories are Scope risk, Schedule risk and Resource risk.
Which of the following statements most accurately describes one of these risk
categories?
(Select one best answer)
Scope risk refers to deliverables, objectives, project charter
Schedule risk refers to the project budget
Resource risk refers to the Procurement Plan
2. Risks can be ranked as unacceptable, undesirable, tolerable or broadly
acceptable, and you must act upon them accordingly. Which of the following
definitions of these rankings is not correct?
(Select the one incorrect answer)
An unacceptable classification requires stopping the activity
An undesirable classification requires that the risk is treated based on its ranking
A tolerable classification requires the risk to be transferred
A broadly acceptable classification allows the risk to be tolerated
3. The following lists components of a Risk Management Plan and their purpose in
the risk management process. Which of these definitions most accurately
describes a Risk Management Plan component? (Select one best answer)
RISK CONTEXT Identified risks and their categories
RISK IDENTIFICATION Identifies risk standards and their context
RISK ANALYSIS classifies risk
Risk SWOT responds to changes in the risk environment
RISK REGISTER records risk objectives
RISK MONITORING Looks at risk qualitatively and quantitatively
4. Which of the following accurately describes contemporary methods of risk
prioritisation in project management? (Select the one best answer)
Project Management Risk Management Quiz_1
Risk prioritisation is generally based on the probability of occurrence and severity
of impact of each identified risk
Some organisations place a higher priority on risks that are likely to happen soon
Organisations place higher priority on those risks that fall on the critical path and
have poor current controls to mitigate the risk
All of these
5. Match the following terms (refer to word list) to their correct meaning.
Word List: Risk Probability, Risk Likelihood, Risk Impact, Risk Consequence, Risk Ranking,
Risk Classification, Inherent Risk, Residual Risk, Qualitative Risk, Quantitative Risk
Meaning Definition
Developing and applying a scale of a 5 x 5 array of elements
with each element representing a different of likelihood and
impact values
Qualitative risk
The probability of the risk even occurring. Risk mitigation
strategies reduce the probability or likelihood of the risk
occurring
Risk probability
This refers to the impact of the risk event, if it occurs Risk impact
This process looks at the risks that have received a high
priority ranking, and then examines the effect of these risks
Quantitative risk
Same as for risk impact Risk consequence
Same as for risk probability Risk likelihood
The score given to a risk by multiplying its probability and
impact
Risk ranking
Defining the classifications by which risk can then be
calculated and analysed
Risk classification
A risk inherited from a previous project Inherent risk
The risk that remains after mitigation and controls are taken
into account
Residual risk
6. Carefully read the following table from an Internet Project Risk Register, and answer
the following question.
ID Risk Event Likelihood Severity
A Project requires new technology and support
structure
Medium Low
B Web infrastructure lacks sufficient transaction
capacity
Medium High
Project Management Risk Management Quiz_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
STRATEGIC MANAGEMENT AND LEADERSHIP Assignment 1
|13
|2412
|268

MANAGEMENT AND RISK MANAGEMENT l ASSIGNMENT
|14
|2794
|21