Project Management for Salisbury House at University of Wales Trinity Saint David
VerifiedAdded on 2023/06/11
|13
|3287
|425
AI Summary
This report assessment will be comprised of essential knowledge regarding the determined concept in context of The University of Wales Trinity Saint David. Furthermore, it will be presenting various different elements associated with effective project management practices.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Project Management
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents
Introduction......................................................................................................................................3
Main Body.......................................................................................................................................3
Project Brief............................................................................................................................3
Project Scope..........................................................................................................................4
Budget assumption.................................................................................................................5
Constraints..............................................................................................................................6
Stakeholder and their involvement.........................................................................................7
Project organisation structure and roles and responsibility....................................................8
Project control Mechanism.....................................................................................................9
Reporting framework............................................................................................................10
Project planning with milestone...........................................................................................10
Conclusion.....................................................................................................................................11
References......................................................................................................................................13
Introduction......................................................................................................................................3
Main Body.......................................................................................................................................3
Project Brief............................................................................................................................3
Project Scope..........................................................................................................................4
Budget assumption.................................................................................................................5
Constraints..............................................................................................................................6
Stakeholder and their involvement.........................................................................................7
Project organisation structure and roles and responsibility....................................................8
Project control Mechanism.....................................................................................................9
Reporting framework............................................................................................................10
Project planning with milestone...........................................................................................10
Conclusion.....................................................................................................................................11
References......................................................................................................................................13
Introduction
Project Management could be determined as process of managing processes and
workforce towards accomplishment of a determined project. For instance, the meaningful
process of project management is majorly comprised of various different functions including
planning, development of strategies, implementation, and close-out. All these activities and
practices further facilitate in ensuring effective implementation of desired project in order to
achieve desired goals and objectives. In addition to that, primary aspects in project management
are comprised of creating project goals, managing risks, setting up standards for performance,
maintaining healthy communication. This report assessment will be comprised of essential
knowledge regarding the determined concept in context of The University of Wales Trinity Saint
David. Furthermore, it will be presenting various different elements associated with effective
project management practices (Kerzner, 2022).
Main Body
Project Brief
The University of Wales Trinity Saint David has established their additional block i.e.,
Salisbury House. For instance, this newly established building block of university is situated near
the main block of that particular University. In order to execute the process of project
management in an effective manner, infrastructure of the building block will take into account
for further evaluation. Therefore, it will ensure effective and efficient completion of the same in
order to contribute additional values towards respective business organisation.
Project Goals
The primary and major aim or goal behind the mentioned scenario lies in establishing
additional space for increasing number of students by providing them with more number of
rooms within University Campus.
Objectives
To establish a building block within University Campus comprised of reception space,
faculty office, kitchenette, etc. in order to provide facilities to increasing number of
students.
Project Management could be determined as process of managing processes and
workforce towards accomplishment of a determined project. For instance, the meaningful
process of project management is majorly comprised of various different functions including
planning, development of strategies, implementation, and close-out. All these activities and
practices further facilitate in ensuring effective implementation of desired project in order to
achieve desired goals and objectives. In addition to that, primary aspects in project management
are comprised of creating project goals, managing risks, setting up standards for performance,
maintaining healthy communication. This report assessment will be comprised of essential
knowledge regarding the determined concept in context of The University of Wales Trinity Saint
David. Furthermore, it will be presenting various different elements associated with effective
project management practices (Kerzner, 2022).
Main Body
Project Brief
The University of Wales Trinity Saint David has established their additional block i.e.,
Salisbury House. For instance, this newly established building block of university is situated near
the main block of that particular University. In order to execute the process of project
management in an effective manner, infrastructure of the building block will take into account
for further evaluation. Therefore, it will ensure effective and efficient completion of the same in
order to contribute additional values towards respective business organisation.
Project Goals
The primary and major aim or goal behind the mentioned scenario lies in establishing
additional space for increasing number of students by providing them with more number of
rooms within University Campus.
Objectives
To establish a building block within University Campus comprised of reception space,
faculty office, kitchenette, etc. in order to provide facilities to increasing number of
students.
To carry out effective project management process in order to establish the desired
building block in such a manner that it fulfils needs and requirements of respective
University.
To serve increasing number of students with sufficient amount of resource in order to
develop effective and efficient learning environment.
Critical Success Factors
It is basically referred to positive factors and aspects associated with a business
organisation which facilitates in ensuring success for that particular operation. In addition to that,
there are various success factors associated with respective university in carrying out the
mentioned project which are as follows:
Upright executive support in execution of activities and practices.
Presence of skilled and professional workforce that contributes additional values towards
the same.
With consideration of clarity in business aims and objectives, it allows workforce in
being aimed at the same (Kerzner, 2018).
Project Scope
Referring to above mentioned information, establishment of a suitable building block is
the primary aim of the determined project in order to fulfil need and requirements of increasing
number of students or learners in University. There are various different essential parameters in
the determined project which are as follows;
Time: The time incurred in completion of the mentioned project plays a crucial role as it
is directly connected with cost or budget of that particular business organisation. For
instance, the increase in time for completion of project directly influences cost incurred in
the same.
Cost: Each and every project organised in a business have a certain amount of budget
which allows their administrative representatives to execute the project according to their
needs and requirements. In addition to that, it is developed according to their financial
ability of spending upon a particular project.
Quality: This has been considered as one of the most essential aspect in carrying out a
particular project as it is based upon quality of products or procedures. In addition to that,
building block in such a manner that it fulfils needs and requirements of respective
University.
To serve increasing number of students with sufficient amount of resource in order to
develop effective and efficient learning environment.
Critical Success Factors
It is basically referred to positive factors and aspects associated with a business
organisation which facilitates in ensuring success for that particular operation. In addition to that,
there are various success factors associated with respective university in carrying out the
mentioned project which are as follows:
Upright executive support in execution of activities and practices.
Presence of skilled and professional workforce that contributes additional values towards
the same.
With consideration of clarity in business aims and objectives, it allows workforce in
being aimed at the same (Kerzner, 2018).
Project Scope
Referring to above mentioned information, establishment of a suitable building block is
the primary aim of the determined project in order to fulfil need and requirements of increasing
number of students or learners in University. There are various different essential parameters in
the determined project which are as follows;
Time: The time incurred in completion of the mentioned project plays a crucial role as it
is directly connected with cost or budget of that particular business organisation. For
instance, the increase in time for completion of project directly influences cost incurred in
the same.
Cost: Each and every project organised in a business have a certain amount of budget
which allows their administrative representatives to execute the project according to their
needs and requirements. In addition to that, it is developed according to their financial
ability of spending upon a particular project.
Quality: This has been considered as one of the most essential aspect in carrying out a
particular project as it is based upon quality of products or procedures. In addition to that,
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
management representatives engaged in that particular project initiates additional efforts
towards enhancement of that particular project (Kerzner, 2019).
Budget assumption
Particulars Unit cost (£) Amount (£)
Raw material 40000
Employees Benefit Expenses 30000
Tools and modern technology 8000
Training to project team members 36000
miscellaneous Expenditures 1500
Cost of scheduling 3500
Other cost 2000
Total cost 5
0
0
0
0
Referring to the above analysis, it has been concluded that it will cost respective
university a total amount of approximately 90000 pounds in completion of the desired project.
Hence, management representatives are required to be aimed at reducing operational cost in
order to attain positive outcomes from carrying out these operations (Rowe, 2020).
Available financial information:
Projected cost £50000
Projected benefit £65000
Cost of capital 15%
PV of projected cost:
= 50000/ (1+15%)1
= £43,478
PV of projected benefit
= 65000/ (1+15%)1
= £56521.74
towards enhancement of that particular project (Kerzner, 2019).
Budget assumption
Particulars Unit cost (£) Amount (£)
Raw material 40000
Employees Benefit Expenses 30000
Tools and modern technology 8000
Training to project team members 36000
miscellaneous Expenditures 1500
Cost of scheduling 3500
Other cost 2000
Total cost 5
0
0
0
0
Referring to the above analysis, it has been concluded that it will cost respective
university a total amount of approximately 90000 pounds in completion of the desired project.
Hence, management representatives are required to be aimed at reducing operational cost in
order to attain positive outcomes from carrying out these operations (Rowe, 2020).
Available financial information:
Projected cost £50000
Projected benefit £65000
Cost of capital 15%
PV of projected cost:
= 50000/ (1+15%)1
= £43,478
PV of projected benefit
= 65000/ (1+15%)1
= £56521.74
Cost benefit analysis: £56521.74/£43,478
= 1.3
Constraints
The projects’ main purpose
As per the given Sailsbury House (SH) project, the main purpose of the project is to create a new
building with rooms for the students and offices for the staff management. The focus will be on
making spacious rooms, classrooms, toilet facilities, lecture rooms, student lounge, and many
others.
identifying risk and other constraints that impacted the project
In any working environment, risks and constraints are there that is why the management should
be aware of such situations that can affect the project goals. Some of the constraints and risks are
explained below-
Economic Constraints
These constraints are related to the budget limit and management of money because of the
budget limit the Sailsbury House project can be affected. The resources are not managed
properly when the budget is not sufficient. Therefore, the given project must create a balance
between quality and cost. The economic constraints also comprise the level of competition in the
education field and about the local workforce and rules of taxation.
Legal Constraints
These constraints are related to the rules and regulations related to the given project and it
consists of various laws such as safety requirements, employment laws, and many others.
some risk analysis and created a robust risk register.
Other Constraints
The various risks that are identified while implementing the project system are fewer students,
poor management teachers regarding classes, unavailability of technologies used for learners,
measures of safety and security of the students and teachers, poor medical assistance, financial
losses, space-related challenges, risks related to hygienic and food in the university.
Risk analysis
The term risk analysis is defined as the process in which the potential problems can be identified
and the potential threats are highlighted. In addition to this, it is explained as the study of
= 1.3
Constraints
The projects’ main purpose
As per the given Sailsbury House (SH) project, the main purpose of the project is to create a new
building with rooms for the students and offices for the staff management. The focus will be on
making spacious rooms, classrooms, toilet facilities, lecture rooms, student lounge, and many
others.
identifying risk and other constraints that impacted the project
In any working environment, risks and constraints are there that is why the management should
be aware of such situations that can affect the project goals. Some of the constraints and risks are
explained below-
Economic Constraints
These constraints are related to the budget limit and management of money because of the
budget limit the Sailsbury House project can be affected. The resources are not managed
properly when the budget is not sufficient. Therefore, the given project must create a balance
between quality and cost. The economic constraints also comprise the level of competition in the
education field and about the local workforce and rules of taxation.
Legal Constraints
These constraints are related to the rules and regulations related to the given project and it
consists of various laws such as safety requirements, employment laws, and many others.
some risk analysis and created a robust risk register.
Other Constraints
The various risks that are identified while implementing the project system are fewer students,
poor management teachers regarding classes, unavailability of technologies used for learners,
measures of safety and security of the students and teachers, poor medical assistance, financial
losses, space-related challenges, risks related to hygienic and food in the university.
Risk analysis
The term risk analysis is defined as the process in which the potential problems can be identified
and the potential threats are highlighted. In addition to this, it is explained as the study of
uncertainty which includes the factors that could adversely influence the growth and success of
the overall project. About the Sailsbury House project, the risks are explained below-
Risk Register
No Risk Effect Possibility Mitigation
1 Uncertainty Moderate Low Forecasting future uncertainties in
advance and formulating plans to deal
with them.
2 Negative impact on
society and
environment
Low Moderate Focusing on environmental safety and
security.
3 Improper
management of
lectures
High Low Making arrangements for the lectures
as per the need of students.
4 Safety and security Low High Guaranteeing security and safety of
learners in their journey of learning.
5 Safety of staff High Moderate Taking preventive safety measures for
the people associated with the
university.
6 Improper parking
arrangements
Moderate Low For both students and teachers, Make
proper parking arrangements for
vehicles.
7 Hygiene of food High Moderate Keep the level of hygiene in food for
people
Stakeholder and their involvement
Stakeholders in a project are people who have an interest in it and can affect or be influenced by
it. Stakeholders participate actively in the project, which leads to its implementation or
completion (Zwikael, and Smyrk, 2019). Teachers, students, employees, higher-ups, the
government, society, and others are all important participants in the project. Internal stakeholders
the overall project. About the Sailsbury House project, the risks are explained below-
Risk Register
No Risk Effect Possibility Mitigation
1 Uncertainty Moderate Low Forecasting future uncertainties in
advance and formulating plans to deal
with them.
2 Negative impact on
society and
environment
Low Moderate Focusing on environmental safety and
security.
3 Improper
management of
lectures
High Low Making arrangements for the lectures
as per the need of students.
4 Safety and security Low High Guaranteeing security and safety of
learners in their journey of learning.
5 Safety of staff High Moderate Taking preventive safety measures for
the people associated with the
university.
6 Improper parking
arrangements
Moderate Low For both students and teachers, Make
proper parking arrangements for
vehicles.
7 Hygiene of food High Moderate Keep the level of hygiene in food for
people
Stakeholder and their involvement
Stakeholders in a project are people who have an interest in it and can affect or be influenced by
it. Stakeholders participate actively in the project, which leads to its implementation or
completion (Zwikael, and Smyrk, 2019). Teachers, students, employees, higher-ups, the
government, society, and others are all important participants in the project. Internal stakeholders
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
include students, teachers, staff, university management, professors, and others, whereas external
stakeholders include government, society, and higher authorities.
High power and high interest: Teachers, staffs and professors, and university
management fall into this category since they have a lot of power and a lot of interest.
These stakeholders contribute funds and have a high degree of interest in the project,
which has a significant impact on its success. As a result, they have a lot of interest and
influence, and they need to be controlled properly.
Low power and low interest: Although society is careful within each category, it should
be managed, and excessive communication and energy waste should be prevented.
High power and low interest: Government and other higher authorities are covered in
this category of stakeholder analysis. Even if they have a minimal level of interest, they
are focused on fulfilling them. As a result, they should be updated in the project as well
as other appropriate information on a regular basis.
Low power and high interest: This is the category in which students are classified. They
have a strong interest in the project, and as a result, they ensure its success. As a result,
such a group cannot be avoided. They should be given balanced information
to satisfy their interest (Aanbari, and Kwak, 2018).
Project organisation structure and roles and responsibility
Projected organisational structure
The determined structure is referred to approach of determining systematic approach of working
in an organisation. For instance, it includes a systematic manner of guiding and determining
system of working in an organisation in order to execute actions in the same manner (Bredillet,
Tywoniak, and Tootoonchy, 2018). The primary and major aim behind consideration of this
organisational structure is to promote the chances of success of that particular project as well as
eliminating deviations and errors that could result in being a barrier in that particular project.
In order to ensure effective completion of the mentioned project, management
representatives engaged in the same are required to regulate effective communication in
workplace in order to coordinate with workforce in an efficient manner. For instance, it will
allow them to ensure trust of employees towards working organisation which shows a positive
indication of upright leadership applied in that particular project. With the presence of effective
stakeholders include government, society, and higher authorities.
High power and high interest: Teachers, staffs and professors, and university
management fall into this category since they have a lot of power and a lot of interest.
These stakeholders contribute funds and have a high degree of interest in the project,
which has a significant impact on its success. As a result, they have a lot of interest and
influence, and they need to be controlled properly.
Low power and low interest: Although society is careful within each category, it should
be managed, and excessive communication and energy waste should be prevented.
High power and low interest: Government and other higher authorities are covered in
this category of stakeholder analysis. Even if they have a minimal level of interest, they
are focused on fulfilling them. As a result, they should be updated in the project as well
as other appropriate information on a regular basis.
Low power and high interest: This is the category in which students are classified. They
have a strong interest in the project, and as a result, they ensure its success. As a result,
such a group cannot be avoided. They should be given balanced information
to satisfy their interest (Aanbari, and Kwak, 2018).
Project organisation structure and roles and responsibility
Projected organisational structure
The determined structure is referred to approach of determining systematic approach of working
in an organisation. For instance, it includes a systematic manner of guiding and determining
system of working in an organisation in order to execute actions in the same manner (Bredillet,
Tywoniak, and Tootoonchy, 2018). The primary and major aim behind consideration of this
organisational structure is to promote the chances of success of that particular project as well as
eliminating deviations and errors that could result in being a barrier in that particular project.
In order to ensure effective completion of the mentioned project, management
representatives engaged in the same are required to regulate effective communication in
workplace in order to coordinate with workforce in an efficient manner. For instance, it will
allow them to ensure trust of employees towards working organisation which shows a positive
indication of upright leadership applied in that particular project. With the presence of effective
communication among employers and employees, management representatives will be able to
deliver the purpose and aim behind the same in order to ensure efforts initiated towards group
goals and objectives (Crawford, 2021). In the context of the university, it follows a hierarchical
organisational structure in which management instructions are given from top-level management
to lower-level management. The following are the jobs and obligations of everyone at the
university:
President- major responsibility in the university is to provide the institution with a vision
as well as regular guidance and leadership in order to plan and administer all elements of
the college's programmes and services. Another responsibility of the university president
is to create an agenda in collaboration with committee chairs, academics, and
management. Other tasks of the president within the university include coordinating the
preparation, review, and distribution of minutes, as well as reviewing the acts of
professors within the administration (Zhang, and et. al., 2020).
Vice President: A vice president's function within a university is to assist the president
in managing and accessing the campus's activities after a pandemic. Working with the
deans to plan, execute, and co-ordinate the college's educational creativities.
Department heads- Within the university, the department head's role in the project is to
lead, develop, and manage the campus's development to ensure that it meets the highest
standards of excellence in providing information about the delivery of lectures to the
learners. It should also preserve the department's students' and staff's discipline.
Staffs: In the framework of the given project, the primary responsibility of staff is to
deliver lectures to university students. They are also in charge of academic advising,
student counselling, and curriculum development through evaluation, among other things.
Project control Mechanism
Work breakdown structure- This strategy is aimed at breaking down the entire work into
smaller parts in order to be assigned to different employees according to their skills and abilities.
For instance, it will facilitate employees in performing their assigned roles and responsibilities in
an efficient manner. This positive initiative contributes additional values towards
accomplishment of organisational goals and objectives.
deliver the purpose and aim behind the same in order to ensure efforts initiated towards group
goals and objectives (Crawford, 2021). In the context of the university, it follows a hierarchical
organisational structure in which management instructions are given from top-level management
to lower-level management. The following are the jobs and obligations of everyone at the
university:
President- major responsibility in the university is to provide the institution with a vision
as well as regular guidance and leadership in order to plan and administer all elements of
the college's programmes and services. Another responsibility of the university president
is to create an agenda in collaboration with committee chairs, academics, and
management. Other tasks of the president within the university include coordinating the
preparation, review, and distribution of minutes, as well as reviewing the acts of
professors within the administration (Zhang, and et. al., 2020).
Vice President: A vice president's function within a university is to assist the president
in managing and accessing the campus's activities after a pandemic. Working with the
deans to plan, execute, and co-ordinate the college's educational creativities.
Department heads- Within the university, the department head's role in the project is to
lead, develop, and manage the campus's development to ensure that it meets the highest
standards of excellence in providing information about the delivery of lectures to the
learners. It should also preserve the department's students' and staff's discipline.
Staffs: In the framework of the given project, the primary responsibility of staff is to
deliver lectures to university students. They are also in charge of academic advising,
student counselling, and curriculum development through evaluation, among other things.
Project control Mechanism
Work breakdown structure- This strategy is aimed at breaking down the entire work into
smaller parts in order to be assigned to different employees according to their skills and abilities.
For instance, it will facilitate employees in performing their assigned roles and responsibilities in
an efficient manner. This positive initiative contributes additional values towards
accomplishment of organisational goals and objectives.
Monitored the project cost- With effective monitoring and controlling practices, it will
facilitate managers in respective university in controlling their cost incurred in completion of the
overall project. Furthermore, all the activities and practices associated with that particular project
are taken into account in order to reduce cost incurred in the same.
Risk management- With the identification and determination of risks associated with the
particular project, it allows respective business organisation in preventing the same with
implementation of suitable and appropriate strategies.
Reporting framework
Each and every stakeholder related to the mentioned project are aimed at upright
engagement in workplace in order to accomplish the same in a significant manner. For
instance, it also effective approach of communication in order to exchange essential
information according to their needs and requirement (Picciotto, 2020).
Stakeholder Name Engagement Channel Frequency
Senior Project
Manager
Maintains upright
management
Communicate upon
frequent and regular
basis in order to
maintain coordination
and collaboration
Daily-basis
Investors and sponsors Keep Satisfied With the use of E-
mails and other formal
documents
Quarterly basis
Suppliers Keep Advised Use of Memos and
Mails
Formerly
Administration staff Monitor Consideration of news
report for
administration
Weekly basis
facilitate managers in respective university in controlling their cost incurred in completion of the
overall project. Furthermore, all the activities and practices associated with that particular project
are taken into account in order to reduce cost incurred in the same.
Risk management- With the identification and determination of risks associated with the
particular project, it allows respective business organisation in preventing the same with
implementation of suitable and appropriate strategies.
Reporting framework
Each and every stakeholder related to the mentioned project are aimed at upright
engagement in workplace in order to accomplish the same in a significant manner. For
instance, it also effective approach of communication in order to exchange essential
information according to their needs and requirement (Picciotto, 2020).
Stakeholder Name Engagement Channel Frequency
Senior Project
Manager
Maintains upright
management
Communicate upon
frequent and regular
basis in order to
maintain coordination
and collaboration
Daily-basis
Investors and sponsors Keep Satisfied With the use of E-
mails and other formal
documents
Quarterly basis
Suppliers Keep Advised Use of Memos and
Mails
Formerly
Administration staff Monitor Consideration of news
report for
administration
Weekly basis
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project planning with milestone
Initiation: This has been considered as the initial stage in the process of project management
which encompasses recognition of needs and requirements in order to be taken into consideration
further in fulfilling the same. For instance, it includes various different elements of business
which are as follows;
Number of rooms required to meet the needs of increasing number of students or
learners.
Administration office in order to provide faculty with suitable space in the University.
Identification of stakeholders that will be impacted with the determined project.
With the consideration of these ideas and purpose of carrying out the determined project, it is
further taken into consideration in order to plan suitable strategies for the same in order to be
executed further which facilitates in accomplishment of organisational goals and objectives
(Tonchia, Tonchia and Mahagaonkar, 2018).
Planning: This stage of project management is inclusive of activities and practices based upon
planning of operations and activities that are required to be carried out towards accomplishment
of the same. In order to be precise, it includes budget, activities and practices, scheduled
activities, etc. which further facilitates in effective and efficient completion of the same.
Furthermore, these planned strategies will be taken into account for further execution according
to their particular needs and requirements.
Execution: This stage of project management includes execution of the planned strategies in
order to accomplish desired goals and objectives. Moreover, it provides a systematic approach to
carry out the determined strategies in the most suitable manner. In addition to that, Management
representatives engaged in that particular are aimed at consideration of employees with suitable
skills and abilities in order to ensure effective completion of the same.
Closure: This stage is considered as achievement of desired goals and objectives of business
which facilitates in contribution of additional values towards accomplishment of goals and
objectives. Furthermore, it includes stopping up contribution efforts and regulating effective
business operations and activities.
Conclusion
From the above report, it can be concluded that project management is vital in any organisation
since it ensures correct strategic alignment of the project's activities. The above-mentioned report
Initiation: This has been considered as the initial stage in the process of project management
which encompasses recognition of needs and requirements in order to be taken into consideration
further in fulfilling the same. For instance, it includes various different elements of business
which are as follows;
Number of rooms required to meet the needs of increasing number of students or
learners.
Administration office in order to provide faculty with suitable space in the University.
Identification of stakeholders that will be impacted with the determined project.
With the consideration of these ideas and purpose of carrying out the determined project, it is
further taken into consideration in order to plan suitable strategies for the same in order to be
executed further which facilitates in accomplishment of organisational goals and objectives
(Tonchia, Tonchia and Mahagaonkar, 2018).
Planning: This stage of project management is inclusive of activities and practices based upon
planning of operations and activities that are required to be carried out towards accomplishment
of the same. In order to be precise, it includes budget, activities and practices, scheduled
activities, etc. which further facilitates in effective and efficient completion of the same.
Furthermore, these planned strategies will be taken into account for further execution according
to their particular needs and requirements.
Execution: This stage of project management includes execution of the planned strategies in
order to accomplish desired goals and objectives. Moreover, it provides a systematic approach to
carry out the determined strategies in the most suitable manner. In addition to that, Management
representatives engaged in that particular are aimed at consideration of employees with suitable
skills and abilities in order to ensure effective completion of the same.
Closure: This stage is considered as achievement of desired goals and objectives of business
which facilitates in contribution of additional values towards accomplishment of goals and
objectives. Furthermore, it includes stopping up contribution efforts and regulating effective
business operations and activities.
Conclusion
From the above report, it can be concluded that project management is vital in any organisation
since it ensures correct strategic alignment of the project's activities. The above-mentioned report
detailed the development of a project management strategy based on the establishing the
additional block i.e., Salisbury House. There is a description of the fundamental elements that are
involved with project operations in this project management plan. An organisational structure
chart, as well as roles and duties, were created as part of the stakeholder analysis. Furthermore,
project control techniques have been explored in this study, as well as a reporting framework that
covers the flow of communication. In addition, a risk management strategy has been developed
with the help of risk register.
additional block i.e., Salisbury House. There is a description of the fundamental elements that are
involved with project operations in this project management plan. An organisational structure
chart, as well as roles and duties, were created as part of the stakeholder analysis. Furthermore,
project control techniques have been explored in this study, as well as a reporting framework that
covers the flow of communication. In addition, a risk management strategy has been developed
with the help of risk register.
References
Books and Journals
Aanbari, F. T. and Kwak, Y. H., 2018, June. Impact on project management of allied disciplines.
Project Management Institute.
Bredillet, C., Tywoniak, S. and Tootoonchy, M., 2018. Why and how do project management
offices change? A structural analysis approach. International Journal of Project
Management, 36(5), pp.744-761.
Crawford, J. K., 2021. Project management maturity model. Auerbach Publications.
Dykstra, A., 2018. Construction project management: A complete introduction. Kirshner
Publishing Company.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. John Wiley & Sons.
Kerzner, H., 2022. Project management case studies. John Wiley & Sons.
Picciotto, R., 2020. Towards a ‘New Project Management’movement? An international
development perspective. International Journal of Project Management, 38(8), pp.474-
485.
Rowe, S. F., 2020. Project management for small projects. Berrett-Koehler Publishers.
Tonchia, S., Tonchia and Mahagaonkar, 2018. Industrial project management. Berlin: Springer.
Zhang, Q., Yang, S., Liao, P. C. and Chen, W., 2020. Influence mechanisms of factors on project
management capability. Journal of Management in Engineering, 36(5), p.04020045.
Zwikael, O. and Smyrk, J. R., 2019. Project management: A benefit realisation approach.
Springer.
Books and Journals
Aanbari, F. T. and Kwak, Y. H., 2018, June. Impact on project management of allied disciplines.
Project Management Institute.
Bredillet, C., Tywoniak, S. and Tootoonchy, M., 2018. Why and how do project management
offices change? A structural analysis approach. International Journal of Project
Management, 36(5), pp.744-761.
Crawford, J. K., 2021. Project management maturity model. Auerbach Publications.
Dykstra, A., 2018. Construction project management: A complete introduction. Kirshner
Publishing Company.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. John Wiley & Sons.
Kerzner, H., 2022. Project management case studies. John Wiley & Sons.
Picciotto, R., 2020. Towards a ‘New Project Management’movement? An international
development perspective. International Journal of Project Management, 38(8), pp.474-
485.
Rowe, S. F., 2020. Project management for small projects. Berrett-Koehler Publishers.
Tonchia, S., Tonchia and Mahagaonkar, 2018. Industrial project management. Berlin: Springer.
Zhang, Q., Yang, S., Liao, P. C. and Chen, W., 2020. Influence mechanisms of factors on project
management capability. Journal of Management in Engineering, 36(5), p.04020045.
Zwikael, O. and Smyrk, J. R., 2019. Project management: A benefit realisation approach.
Springer.
1 out of 13
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.