Project Management: Status, Timeline, Cost, and Adjustments
Verified
Added on 2023/04/20
|16
|2407
|200
AI Summary
This report examines the status of a project, including the timeline, cost variations, resource changes, and adjustments made. It provides insights into project management and the challenges faced in real-time projects.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT Project management Name of the student Name of the university Author note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT Table of Contents Introduction................................................................................................................................2 Project status..............................................................................................................................3 Project timeline......................................................................................................................3 Variation in cost.....................................................................................................................7 Resource changes...................................................................................................................7 Slipping tasks.........................................................................................................................8 Details of all adjustments...........................................................................................................9 Personal reflection....................................................................................................................10 Bibliography.............................................................................................................................11 Appendices...............................................................................................................................13 An updated milestone plan (as an appendix).......................................................................13 An updated task list (as an appendix) and who is responsible for each task.......................14 A revised Gantt chart (as an appendix)................................................................................15
2PROJECT MANAGEMENT Introduction This report has aimed to examine the status of the project undertaken. The initial plan of the project was to relocate a family to Perth from the Queensland Sunshine Coast. The family consists of four members, out of which two members are children and remaining two are adults. Relocation had been performed to facilitate Jeff to move to a different job where he has been appointed as the marketing director. The job location is in Perth. Initially, it was necessary to relocate within seven days but the main issues were that they family needed to vacate their existing house by 20thJanuary. The initial project plan was developed to complete the overall relocation within four days by using crashing technique to reduce the time by allocating more resources. The report has developed the status report on the relocation to examine the completion of important milestones in the project, the slips and delays in the project.Australia has been hit by the worst epidemic in years which has made Kelly ill. This means that no tasks can be assigned to Kelly. On the other hand, the truck carrying the belongings have broken down in a remote place near the western Australian border and it has taken three days to repair the truck.This has caused a delay in furniture arrival to 30thJanuary and the report has addressed all these variations from the original plan to develop status plan.
3PROJECT MANAGEMENT Project status Project timeline WBSTask NameDurationStartFinishCost Baseline Duration % CompleteActual Duration 0 Relocating with family to a new house 23.5 days Tue01- 01-19 Thu31- 01-19 $ 19,960.0025 days78%18.43 days 1Initiation phase5 days Tue01- 01-19 Mon07- 01-19 $ 1,920.005 days100%5 days 1.1 Development of initial plan for relocation 3 days Tue 01-01- 19 Thu 03-01- 19 $ 1,200.003 days100%3 days 1.2 Making the financial plan for relocation 2 days Fri04-01- 19 Mon07- 01-19 $ 720.002 days100%2 days 1.3Milestone1: Completion of initiation 0 daysMon07-Mon07-$ 0.000 days100%0 days
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT phase01-1901-19 2Planning phase7 days Tue08- 01-19 Wed16- 01-19 $ 2,560.007 days100%7 days 2.1 Making plan as per the required time 3 days Tue 08-01- 19 Thu 10-01- 19 $ 1,200.003 days100%3 days 2.2 Making plan for the required budget 2 days Fri11-01- 19 Mon14- 01-19 $ 720.002 days100%2 days 2.3 Developing plan for managing risks 2 days Tue 15-01- 19 Wed16- 01-19 $ 640.002 days100%2 days 2.4 Milestone2: Completion of planning phase 0 days Wed16- 01-19 Wed16- 01-19 $ 0.000 days100%0 days 3Execution phase10.5 daysThu17-Wed30-$ 14,440.0011 days76%8 days
5PROJECT MANAGEMENT 01-1901-19 3.1 Solicitor appointment 1 day Thu 17-01- 19 Thu 17-01- 19 $ 320.001 day100%1 day 3.2Identifying surveyor2 days Fri18-01- 19 Mon21- 01-19 $ 800.002 days100%2 days 3.3 Making booking for the new house 3 days Tue 22-01- 19 Thu 24-01- 19 $ 1,200.003 days100%3 days 3.4 Vacating the present house 1 day Fri25-01- 19 Fri25-01- 19 $ 720.001 day100%1 day 3.5 Moving to the new housewithall belongings 2.5 days Sun 27-01- 19 Tue 29-01- 19 $ 11,400.001 day40%1 day 3.6Milestone3: Completion of execution 1 dayTue 29-01-Wed30-$ 0.000 days0%0 days
6PROJECT MANAGEMENT phase1901-19 4Closure phase2 days Tue29- 01-19 Thu31- 01-19 $ 1,040.002 days0%0 days 4.1 Settling to the new house 2 days Tue 29-01- 19 Thu 31-01- 19 $ 640.002 days0%0 days 4.2 Completing paper works 1 day Tue 29-01- 19 Wed30- 01-19 $ 400.001 day0%0 days 4.3 Milestone4: Completionofclosure phase 0 days Wed30- 01-19 Wed30- 01-19 $ 0.000 days0%0 days Table 1: Status report
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
9PROJECT MANAGEMENT Details of all adjustments During the execution of the project, there has been deviation in the actual project time and status even after the crashing. The crashing facilitated in reducing the time of the project by allocating more resources. In this scenario, due to the breakdown of the truck there has been delay in moving of all goods and furniture to the Perth. There has been a delay of three days due to the breakdown on the border of Western Australia.This is the reason that there has a significant change in the timeline of task from 3.6 onwards. The project status date was chosen as 27thJanuary, 2018 and it was the expected finish date. However, it can be seen that project has achieved only 78% completion and one of the tasks is progress. Moving to the new house is still going on and only 25% of this task has been completed. Crashing has been used in this task to reduce the duration of the task and reduce the overall timeline. The incorporation of truck mechanic as an excess resource has reduced the original of 4 days to 2.5 days. However, further addition of resources would increase the overall cost of the project. This incident has increased the overall cost of the project by $ 5,120.00 and this is necessary so that the lost time could be made up. There has also been delay in the closure phase of the project where the tasks have not commenced due to its dependency on the previous tasks. There has been 1.5 day of increase in the overall time span of the project. The earlier adjustment of the project was proposed to reduce the time span of the overall project. However, the use of the excess resources was not the ideal solution of the project. The study clearly shows that the milestone 3 is slipping due to the delay in the final stage of the project. The difference in the forecasted finish date and the baseline finish date shows that excess will have to be used as a contingency risk to meet the deadline.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT Personal reflection I have been engaged with this relocation project of moving a family from Queensland to Perth. Jeff, one of the two adults is relocating due to a new job offer. The project timeline has already been developed based on the requirement but there has been delay in the project due to breakdown of the truck on the borders of Western Australia.I have gained vast amount of knowledge regarding different aspect of managing a project which consists of tracking of project timeline, developing status report, checking completion of different stages of tasks and analysing the delay in the project. Contingency and unknown risk factors have to be taken into account while developing the project timeline. I have learnt about the concept of buffer time and its use in keeping the project on track. I have learnt to update changes and compare it to the baseline of the project. The use of contingency plan to solve the issues in the project delay is one of the most vital learnings for me. I have little idea about delay and slippage but this project has given enough knowledge that would help in future projects to evaluate delay and slippage. I have gained immense knowledge and skills from this project which has provided an overview of the real-time issues in practical projects. I have to be prepared with contingency plans and risk management plan to avoid delays and use buffer time to make sure that the overall delay does not affect the baseline time of the project. Change management can be of different types and this project has provided a value experience on managing changing within projects effectively. The experience and knowledge that I have gained in the project would help me in professional projects. In this given project, I have learnt the use of tracking of different activities which can be beneficial in my professional career as a project manager.
11PROJECT MANAGEMENT Bibliography Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. de Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its effectson project success: Cross-country and cross-industry comparisons.International Journal of Project Management,33(7), pp.1509-1522. Tonchia, S., 2018. Project Execution. InIndustrial Project Management(pp. 241-267). Springer, Berlin, Heidelberg. Dang, X., Scotcher, J., Wu, S., Chu, R.K., Tolić, N., Ntai, I., Thomas, P.M., Fellers, R.T., Early, B.P., Zheng, Y. and Durbin, K.R., 2014. The first pilot project of the consortium for top‐down proteomics: a status report.Proteomics,14(10), pp.1130-1140. Singh, A., 2014. Resource constrained multi-project scheduling with priority rules & analytic hierarchy process.Procedia engineering,69, pp.725-734. Wilson Jr, J.F. and Honeycutt, G.T., Pride Falls, LLC, 2015.Pre-constructed building unit construction and transportation structure and method. U.S. Patent 9,062,451.\ Braglia,M.andFrosolini,M.,2014.Anintegratedapproachtoimplementproject management information systems within the extended enterprise.International Journal of Project Management,32(1), pp.18-29. Hu, X., Cui, N. and Demeulemeester, E., 2015. Effective expediting to improve project due date and cost performance through buffer management.International Journal of Production Research,53(5), pp.1460-1471.
12PROJECT MANAGEMENT Hu, X., Cui, N., Demeulemeester, E. and Bie, L., 2016. Incorporation of activity sensitivity measures into buffer management to manage project schedule risk.European Journal of Operational Research,249(2), pp.717-727. Carstens, D.S., Richardson, G.L. and Smith, R.B., 2016.Project management tools and techniques: A practical guide. CRC Press. Harrison, F. and Lock, D., 2017.Advanced project management: a structured approach. Routledge.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.