This document provides information on project selection, network design, crashing the project, risk planning, and minimizing project delay in the field of project management.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT Project Management Name of Student- Name of University- Author’s Note-
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT Section A- Project Selection 1. Payback Period Project OptionPayback Period Option A10.9535years Option B4.5283years Option C4.9940 years 2. NPV Calculation Project OptionNet Present value Option A$10,822,645.18 Option B$4,627,809.53 Option C$1,840,185.95 3. Preferred best Option The best option for selecting the project is option B. Option B is considered as the best project as the payback period for the project is 4.5283 years. The lower the payback period, the best is the project. Moreover, the total net present value of project B is positive as positive value for a project is greater than the anticipated cost. Positive NPV in a project is profitable and the other two project have negative NPV value that will result in loss of the project.
2PROJECT MANAGEMENT Section B- Network Design 1) Network Diagram 2) Forward pass, backward pass and Slack time Forward pass- Early start + Duration Backward pass- Late Finish - Duration 3) Critical path
3PROJECT MANAGEMENT 4) Critical Path Sensitivity Sensitive analysis is the quantitative assumption as well as computations that are changes systematically for access their effect. The evaluation of the risk or the identification of the critical factors are involved in sensitive analysis. Section C- Crashing the Project 1) Data Table and Activity Log IDActivityPred eces sor Cost TypeDur atio n Normal Cost Crash Durati on Crash Cost ASW DecisionGeneral26002600 BStakeholder InputAUnskilled10200083600 CID data SetupASkilled390021400 DDB SetupAUnskilled24001450 EDraft UI DesignBSkilled6180052500 FData CleaningCUnskilled102000102000
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT GSpec WorkstationEGeneral12001200 HUI TestingESkilled154500154500 IData ValidationFSkilled123600123600 JDB TestD, FUnskilled5100051000 KOrder WorkstationGUnskilled201000105000 LUI SignoffHGeneral13001300 MLoad dataI, JUnskilled48004800 NInstall WorkstationsKUnskilled8160081600 OIntegrate UI, DatabaseL, MSkilled5150051500 PFinal Use TestN, OGeneral8240082400 2) Cost of project The new direct cost is $40,000 and the indirect cost of the project after crashing is $500. The total cost of the project is $40,000. 3) Project duration If the project duration was not reduced, then the project crashing would have been done by outsourcing the skilled and the unskilled labour in the project. 4) Risks The new risks that have been introduced after crashing the project is increasing the cost of the project as per the schedule of the project. There might be risks at not following the rules and regulation of the project and making the worker make work over time. There might also be a
5PROJECT MANAGEMENT risk of decreasing the quality of the project. The project manager might miss out some objective while completing the task in a hurry. Section D: Risk Planning 1) Identified Risks 2) Risk Assessment Three important risks that are associated with the project are: Quality Issue risks, increasing time risk, and increasing the budget of the project. 4) Minimizing the project delay
6PROJECT MANAGEMENT For minimizing the project delay, the project was to be divided in many sub tasks so that the task would be divided in to different resources so the work gets completed on time.