The project is for upgrading 3G to 4G in Kathmandu for improving the data quality and large area coverage. In context to this, the present file has included project scope and determination of the resources. Along with this, the study has added quality planning and risk management plan for offering high quality and error free project to the client. For analyzing the stakeholder, project has involved stakeholder analysis properly. In the end, deployment plan has included within the project for effective implementation process.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running Head: PROJECT MANAGEMENT
1
Project Management
[Author]
[Institution]
EXECUTIVE SUMMARY
1
Project Management
[Author]
[Institution]
EXECUTIVE SUMMARY
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
The project is for upgrading 3G to 4G in Kathmandu for improving the data quality and
large area coverage. In context to this, the present file has included project scope and
determination of the resources. Along with this, the study has added quality planning and risk
management plan for offering high quality and error free project to the client. For analyzing the
stakeholder, project has involved stakeholder analysis properly. In the end, deployment plan has
included within the project for effective implementation process.
Table of Contents
large area coverage. In context to this, the present file has included project scope and
determination of the resources. Along with this, the study has added quality planning and risk
management plan for offering high quality and error free project to the client. For analyzing the
stakeholder, project has involved stakeholder analysis properly. In the end, deployment plan has
included within the project for effective implementation process.
Table of Contents
EXECUTIVE SUMMARY.............................................................................................................2
INTRODUCTION...........................................................................................................................4
Determination of project scope....................................................................................................4
Estimation of time for project......................................................................................................5
Determination of resources needs for project..............................................................................8
Gantt chart and Network Diagram...............................................................................................9
Estimation of cost for project......................................................................................................9
Quality planning for project.......................................................................................................10
Stakeholder analysis..................................................................................................................11
Communication Plan.................................................................................................................12
Risk Management Plan..............................................................................................................13
Project Deployment Plan...........................................................................................................15
Recommendations......................................................................................................................16
CONCLUSION..............................................................................................................................17
REFERENCES..............................................................................................................................19
INTRODUCTION...........................................................................................................................4
Determination of project scope....................................................................................................4
Estimation of time for project......................................................................................................5
Determination of resources needs for project..............................................................................8
Gantt chart and Network Diagram...............................................................................................9
Estimation of cost for project......................................................................................................9
Quality planning for project.......................................................................................................10
Stakeholder analysis..................................................................................................................11
Communication Plan.................................................................................................................12
Risk Management Plan..............................................................................................................13
Project Deployment Plan...........................................................................................................15
Recommendations......................................................................................................................16
CONCLUSION..............................................................................................................................17
REFERENCES..............................................................................................................................19
Table of Figures
Figure 1: Gantt chart......................................................................................................................10
Figure 2: Network Diagram...........................................................................................................10
List of Table
Table 1: Cost Estimation.................................................................................................................9
Figure 1: Gantt chart......................................................................................................................10
Figure 2: Network Diagram...........................................................................................................10
List of Table
Table 1: Cost Estimation.................................................................................................................9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
INTRODUCTION
Technology in the field of mobile and related applications is growing fast with time. It
was one of the major jumps in the field of technology when the wireless networks transformed
from analog to the digital. Wireless telephone technology i.e. mobile telecommunication includes
list of generations which are 1G, 2G, 3G and 4G. Each generation is believed to be faster, more
secure and more reliable than the previous one. 3G is offering faster data, speed and at least
200KB per seconds for multimedia use. The 3G was long time standard for the wireless
transmissions until 4G does not released. After the release of 4G, people are upgrading their
services for getting much faster speed and services. With respect to this, the present project plan
is based on the Mobile 3G to 4G Upgrade in Kathmandu. In context to this, the file includes
project scope, time and cost estimation, quality planning, risk assessment and implementation
(Kerzner & Kerzner, 2017).
Determination of project scope
In 2G, there was facility of making calls and sending text messages. Later, the 3G
released with the features of web browsing, email, video downloading, picture sharing and many
more. The 3G network was capable enough to handle approximate 2 megabits per second.
Individuals around the world were highly satisfied with the third generation network. Now, the
technological world has brought new 4G in the market with higher speed and more features. The
speed and standards of 4g is about 100 Megabits per second and up to 1 Gigabits per second. 4G
is pure data connection as it possesses end to end internet protocol connection. In the present
time, Kathmandu is facing issues due to availability of 2G and 3G network. Due to the absence
of skilled and necessary resources, the city is unable to upgrade its network from 2G and 3G to
4G. With respect to this, the people are facing network issues due to which they are unable to
call and access internet. On the other hand, irregular topography of Kathmandu is another reason
behind the usage of 2G and 3G. Thus, the aim of the present project plan is to upgrade the
technology from 3G to 4G in Kathmandu (Fleming & Koppelman, 2016).
Aim: To upgrade mobile network from 3G to 4G in Kathmandu
Objectives:
Technology in the field of mobile and related applications is growing fast with time. It
was one of the major jumps in the field of technology when the wireless networks transformed
from analog to the digital. Wireless telephone technology i.e. mobile telecommunication includes
list of generations which are 1G, 2G, 3G and 4G. Each generation is believed to be faster, more
secure and more reliable than the previous one. 3G is offering faster data, speed and at least
200KB per seconds for multimedia use. The 3G was long time standard for the wireless
transmissions until 4G does not released. After the release of 4G, people are upgrading their
services for getting much faster speed and services. With respect to this, the present project plan
is based on the Mobile 3G to 4G Upgrade in Kathmandu. In context to this, the file includes
project scope, time and cost estimation, quality planning, risk assessment and implementation
(Kerzner & Kerzner, 2017).
Determination of project scope
In 2G, there was facility of making calls and sending text messages. Later, the 3G
released with the features of web browsing, email, video downloading, picture sharing and many
more. The 3G network was capable enough to handle approximate 2 megabits per second.
Individuals around the world were highly satisfied with the third generation network. Now, the
technological world has brought new 4G in the market with higher speed and more features. The
speed and standards of 4g is about 100 Megabits per second and up to 1 Gigabits per second. 4G
is pure data connection as it possesses end to end internet protocol connection. In the present
time, Kathmandu is facing issues due to availability of 2G and 3G network. Due to the absence
of skilled and necessary resources, the city is unable to upgrade its network from 2G and 3G to
4G. With respect to this, the people are facing network issues due to which they are unable to
call and access internet. On the other hand, irregular topography of Kathmandu is another reason
behind the usage of 2G and 3G. Thus, the aim of the present project plan is to upgrade the
technology from 3G to 4G in Kathmandu (Fleming & Koppelman, 2016).
Aim: To upgrade mobile network from 3G to 4G in Kathmandu
Objectives:
The objectives of the present project plan are as follows:
To implement 4g network in the environment of Kathmandu
To provide large area network coverage
To provide affordable services to the people
Estimation of time for project
Project schedule is one of the important tool by which project manager can easily
estimate the total required time for completing the project. Project schedule for the current
project is as follows:
WB
S Task Name Durati
on Start Finish Predecess
ors
Resource
Names Cost
1
Mobile
network
project from
3G to 4G in
Kathmandu
136
days
Mon
5/28/1
8
Mon
12/3/1
8
$1,500,000.
00
1.1
Project
Initiation
and
conception
25
days
Mon
5/28/1
8
Fri
6/29/1
8
$20,000.00
1.1.
1
Project
Charter
10
days
Mon
5/28/1
8
Fri
6/8/18 Project Manager $8,000.00
1.1.
2
Project
initiation
15
days
Mon
6/11/1
8
Fri
6/29/1
8
3 Project Manager $12,000.00
1.2
Project
definition
and
planning
47
days
Mon
7/2/18
Tue
9/4/18 $27,840.00
1.2. Scope 10 Mon Fri 3,4 Project Manager $8,000.00
To implement 4g network in the environment of Kathmandu
To provide large area network coverage
To provide affordable services to the people
Estimation of time for project
Project schedule is one of the important tool by which project manager can easily
estimate the total required time for completing the project. Project schedule for the current
project is as follows:
WB
S Task Name Durati
on Start Finish Predecess
ors
Resource
Names Cost
1
Mobile
network
project from
3G to 4G in
Kathmandu
136
days
Mon
5/28/1
8
Mon
12/3/1
8
$1,500,000.
00
1.1
Project
Initiation
and
conception
25
days
Mon
5/28/1
8
Fri
6/29/1
8
$20,000.00
1.1.
1
Project
Charter
10
days
Mon
5/28/1
8
Fri
6/8/18 Project Manager $8,000.00
1.1.
2
Project
initiation
15
days
Mon
6/11/1
8
Fri
6/29/1
8
3 Project Manager $12,000.00
1.2
Project
definition
and
planning
47
days
Mon
7/2/18
Tue
9/4/18 $27,840.00
1.2. Scope 10 Mon Fri 3,4 Project Manager $8,000.00
1 Budget days 7/2/18 7/13/1
8
1.2.
2
Developi
ng project
plan
15
days
Mon
7/16/1
8
Fri
8/3/18 6 Project Manager $12,000.00
1.2.
3
Estimatin
g resources
10
days
Mon
8/6/18
Fri
8/17/1
8
7 Team member 1 $1,600.00
1.2.
4
Commun
ication Plan
12
days
Mon
8/20/1
8
Tue
9/4/18 8 Assistant
project manager $3,840.00
1.2.
5
Risk
Management
10
days
Mon
8/20/1
8
Fri
8/31/1
8
7,8 Risk Manager $2,400.00
1.3
Project
launch and
execution
32
days
Wed
9/5/18
Thu
10/18/
18
$1,424,160.
00
1.3.
1
Status &
Tracking
12
days
Wed
9/5/18
Thu
9/20/1
8
9,10
Project
Manager,
Technical
resources [1]
$1,420,960.
00
1.3.
2 KPIs 5 days
Fri
9/21/1
8
Thu
9/27/1
8
12 Team member 1 $800.00
1.3.
3 Quality 10
days
Fri
9/28/1
8
Thu
10/11/
18
13 Team member 2 $1,600.00
1.3.
4 Forecasts 5 days
Fri
10/12/
18
Thu
10/18/
18
13,14 Team member 1 $800.00
1.4 Project 42 Fri Mon $23,200.00
8
1.2.
2
Developi
ng project
plan
15
days
Mon
7/16/1
8
Fri
8/3/18 6 Project Manager $12,000.00
1.2.
3
Estimatin
g resources
10
days
Mon
8/6/18
Fri
8/17/1
8
7 Team member 1 $1,600.00
1.2.
4
Commun
ication Plan
12
days
Mon
8/20/1
8
Tue
9/4/18 8 Assistant
project manager $3,840.00
1.2.
5
Risk
Management
10
days
Mon
8/20/1
8
Fri
8/31/1
8
7,8 Risk Manager $2,400.00
1.3
Project
launch and
execution
32
days
Wed
9/5/18
Thu
10/18/
18
$1,424,160.
00
1.3.
1
Status &
Tracking
12
days
Wed
9/5/18
Thu
9/20/1
8
9,10
Project
Manager,
Technical
resources [1]
$1,420,960.
00
1.3.
2 KPIs 5 days
Fri
9/21/1
8
Thu
9/27/1
8
12 Team member 1 $800.00
1.3.
3 Quality 10
days
Fri
9/28/1
8
Thu
10/11/
18
13 Team member 2 $1,600.00
1.3.
4 Forecasts 5 days
Fri
10/12/
18
Thu
10/18/
18
13,14 Team member 1 $800.00
1.4 Project 42 Fri Mon $23,200.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
performanc
e and
control
days 9/28/1
8
11/26/
18
1.4.
1
Objectiv
es 5 days
Fri
9/28/1
8
Thu
10/4/1
8
12,13 Program
Manager $2,400.00
1.4.
2
Quality
Deliverables
10
days
Fri
10/12/
18
Thu
10/25/
18
14,17 Telecommunica
tion engineer $3,200.00
1.4.
3
Effort &
Cost tracking
12
days
Fri
10/26/
18
Mon
11/12/
18
18 Project Manager $9,600.00
1.4.
4
Performa
nce
10
days
Tue
11/13/
18
Mon
11/26/
18
19 Project Manager $8,000.00
1.5 Project
close 5 days
Tue
11/27/
18
Mon
12/3/1
8
$4,800.00
1.5.
1
Reportin
g 5 days
Tue
11/27/
18
Mon
12/3/1
8
20
Project
Manager, Team
Member 1
$4,800.00
As per the above project schedule the current project will complete in minimum 136
days. Above plan has included the total time, resources and cost of the project.
Determination of resources needs for project
The resources which are required for upgrading 3G to 4G network at Katmandu are as
follows:
Human Resources: It is necessary to have human resources for completing the project. The
companies will need skilled, talented and knowledgeable employees having information
regarding the 4G services. The project team will include project manager, program manager, risk
e and
control
days 9/28/1
8
11/26/
18
1.4.
1
Objectiv
es 5 days
Fri
9/28/1
8
Thu
10/4/1
8
12,13 Program
Manager $2,400.00
1.4.
2
Quality
Deliverables
10
days
Fri
10/12/
18
Thu
10/25/
18
14,17 Telecommunica
tion engineer $3,200.00
1.4.
3
Effort &
Cost tracking
12
days
Fri
10/26/
18
Mon
11/12/
18
18 Project Manager $9,600.00
1.4.
4
Performa
nce
10
days
Tue
11/13/
18
Mon
11/26/
18
19 Project Manager $8,000.00
1.5 Project
close 5 days
Tue
11/27/
18
Mon
12/3/1
8
$4,800.00
1.5.
1
Reportin
g 5 days
Tue
11/27/
18
Mon
12/3/1
8
20
Project
Manager, Team
Member 1
$4,800.00
As per the above project schedule the current project will complete in minimum 136
days. Above plan has included the total time, resources and cost of the project.
Determination of resources needs for project
The resources which are required for upgrading 3G to 4G network at Katmandu are as
follows:
Human Resources: It is necessary to have human resources for completing the project. The
companies will need skilled, talented and knowledgeable employees having information
regarding the 4G services. The project team will include project manager, program manager, risk
manager, accountant, telecommunication engineer, network architect and many more for
accomplishing the objectives of the present project. With the help of proper management and
planning, the organizations will able to upgrade their network services for meeting the needs of
the people in Kathmandu (Turner, 2016).
Financial Resources: There is need of proper money for spending in the form of cash, liquid
securities and credit lines for implementing the project effectively at Kathmandu. With respect to
this, project will need sufficient resources. The financial resources help in paying the skilled
workforce, network planning and many other processes with respect to the current project. The
initial estimation of the costs is 1.5 million dollars.
Technical Resources: The project needs latest tools and techniques for implementing the plan in
Kathmandu. These technological resources include Software radio technology, mobile
communication standards like GSM, CDMA and TDMA, switching technology, positioning
technology, smart antenna technology, reconfigurable/self-healing network technology and many
more (Mir & Pinnington, 2014).
Physical Resources: The project needs infrastructure, different machines, equipment and vehicle
for implementing the project successfully within the Kathmandu.
All the above resources help in upgrading the mobile network from 3G to 4G at
Kathmandu effectively.
Gantt chart and Network Diagram
Gantt chart:
accomplishing the objectives of the present project. With the help of proper management and
planning, the organizations will able to upgrade their network services for meeting the needs of
the people in Kathmandu (Turner, 2016).
Financial Resources: There is need of proper money for spending in the form of cash, liquid
securities and credit lines for implementing the project effectively at Kathmandu. With respect to
this, project will need sufficient resources. The financial resources help in paying the skilled
workforce, network planning and many other processes with respect to the current project. The
initial estimation of the costs is 1.5 million dollars.
Technical Resources: The project needs latest tools and techniques for implementing the plan in
Kathmandu. These technological resources include Software radio technology, mobile
communication standards like GSM, CDMA and TDMA, switching technology, positioning
technology, smart antenna technology, reconfigurable/self-healing network technology and many
more (Mir & Pinnington, 2014).
Physical Resources: The project needs infrastructure, different machines, equipment and vehicle
for implementing the project successfully within the Kathmandu.
All the above resources help in upgrading the mobile network from 3G to 4G at
Kathmandu effectively.
Gantt chart and Network Diagram
Gantt chart:
Figure 1: Gantt chart
Network Diagram:
Figure 2: Network Diagram
Estimation of cost for project
Table 1: Cost Estimation
WBS Task Name Cost
1 Mobile network project from 3G to 4G in
Kathmandu $1,500,000.00
1.1 Project Initiation and conception $20,000.00
1.2 Project definition and planning $27,840.00
1.3 Project launch and execution $1,424,160.00
1.4 Project performance and control $23,200.00
Network Diagram:
Figure 2: Network Diagram
Estimation of cost for project
Table 1: Cost Estimation
WBS Task Name Cost
1 Mobile network project from 3G to 4G in
Kathmandu $1,500,000.00
1.1 Project Initiation and conception $20,000.00
1.2 Project definition and planning $27,840.00
1.3 Project launch and execution $1,424,160.00
1.4 Project performance and control $23,200.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
1.5 Project close $4,800.00
Quality planning for project
It is necessary to maintain the quality of project for accomplishing the desired objectives.
With respect to the current project, companies of Kathmandu need highly qualified and skilled
employees. The project needs to provide high quality 4G services without any disturbance and
network issue. As per this, the team members of the firm work together for meeting all the
requirements of the project and upgrading the 3G services to the 4G in the Kathmandu. Proper
testing, verification and validation are conducted by the team members for checking the quality
of the project. Any mistake or error within the project can result to failure and big loss to the
firm. Along with this, it is responsibility of the quality manager to check the quality of the
project for avoiding any mistake in future. Proper quality planning also helps in delivering the
project on time (Hornstein, 2015). The quality management plan for the current project is as
follows:
Quality Objectives: The quality objective of this project to is to upgrade mobile network 3G to
4G by using quality tools and technologies. Along with this, the secondary objective is to deliver
the project in decided time period by meeting all the requirements.
Quality control and assurance activities: It is the duty of the quality manager to control and
maintain the quality of the entire project by conducting testing, verification, and related
activities.
Quality roles and responsibilities: The purpose of the quality manager is to maintain the
quality of the project by handling errors and using appropriate resources. By keeping the quality,
firms will able to deliver quality services of 4G to the people of Kathmandu (Svejvig &
Andersen, 2015).
Quality Planning Quality Control Quality
Assurance
Quality
Improvement
What is
done
To identify the quality of
project and how it can be
achieved
Monitoring the
project for
determining if they
To evaluate if
quality
measurement is
To increase the
effectiveness and
efficiency
Quality planning for project
It is necessary to maintain the quality of project for accomplishing the desired objectives.
With respect to the current project, companies of Kathmandu need highly qualified and skilled
employees. The project needs to provide high quality 4G services without any disturbance and
network issue. As per this, the team members of the firm work together for meeting all the
requirements of the project and upgrading the 3G services to the 4G in the Kathmandu. Proper
testing, verification and validation are conducted by the team members for checking the quality
of the project. Any mistake or error within the project can result to failure and big loss to the
firm. Along with this, it is responsibility of the quality manager to check the quality of the
project for avoiding any mistake in future. Proper quality planning also helps in delivering the
project on time (Hornstein, 2015). The quality management plan for the current project is as
follows:
Quality Objectives: The quality objective of this project to is to upgrade mobile network 3G to
4G by using quality tools and technologies. Along with this, the secondary objective is to deliver
the project in decided time period by meeting all the requirements.
Quality control and assurance activities: It is the duty of the quality manager to control and
maintain the quality of the entire project by conducting testing, verification, and related
activities.
Quality roles and responsibilities: The purpose of the quality manager is to maintain the
quality of the project by handling errors and using appropriate resources. By keeping the quality,
firms will able to deliver quality services of 4G to the people of Kathmandu (Svejvig &
Andersen, 2015).
Quality Planning Quality Control Quality
Assurance
Quality
Improvement
What is
done
To identify the quality of
project and how it can be
achieved
Monitoring the
project for
determining if they
To evaluate if
quality
measurement is
To increase the
effectiveness and
efficiency
are meeting the
performance
measurements
appropriate
When it
need to
done
Project Planning Phase
Processes:
Project scope
and
requirement
analysis
Team building
Schedule
development
Resource
Development
Project
Acquisition
Strategy (Joslin
& Müller,
2015)
Project Execution
and Control phase
Processes
Project
execution
Project
Control
Project Execution
and Control phase
Processes
Project
execution
Project
Control
Project planning,
Project Execution and
Control phase
Processes
Change
Management
Stakeholder analysis
The stakeholder analysis for the present project is as follows:
Companies: Nepal Telecom, CG Company Pvt Ltd and Axiata Company. These organizations
implement the project for providing network sustainability, high quality data and high speed to
the customers. In response to this, firms will get reputation, economic benefits, brand awareness
and profitability.
Employees: The workers are essential assets of the organization. The team members like project
manager, program manager, accountant, risk manager, etc works together for accomplishing the
objectives of the project.
performance
measurements
appropriate
When it
need to
done
Project Planning Phase
Processes:
Project scope
and
requirement
analysis
Team building
Schedule
development
Resource
Development
Project
Acquisition
Strategy (Joslin
& Müller,
2015)
Project Execution
and Control phase
Processes
Project
execution
Project
Control
Project Execution
and Control phase
Processes
Project
execution
Project
Control
Project planning,
Project Execution and
Control phase
Processes
Change
Management
Stakeholder analysis
The stakeholder analysis for the present project is as follows:
Companies: Nepal Telecom, CG Company Pvt Ltd and Axiata Company. These organizations
implement the project for providing network sustainability, high quality data and high speed to
the customers. In response to this, firms will get reputation, economic benefits, brand awareness
and profitability.
Employees: The workers are essential assets of the organization. The team members like project
manager, program manager, accountant, risk manager, etc works together for accomplishing the
objectives of the project.
Government: While implementing the project, it is necessary for following all laws and
regulations developed by the government of Nepal.
Customers: People of Kathmandu are facing network issues; it is their requirement to have high
speed and high quality data for using better services in mobile telecommunication. The main
purpose of this project is to satisfy the customers and improving the present situation of
Kathmandu (Todorović and et.al., 2015).
Communication Plan
The communication plan for the present project is as follows:
Audience Message Medium Schedule Responsible
Top level
management
Reports;
Strategies;
decision making;
issues;
requirements of
technology;
changes to
corporate business
processes
Meeting, formal
reports, demos
Monthly Project leader,
project team
Management
Committee
Project Overview;
implementation
scope, risk,
budget, user
training; reporting;
change
management
Meeting, formal
reports, demos
As per the need Project leader,
project team
Project
Implementation
Team
Roles and
responsibilities;
progress reports;
strategies; issue
resolution
(Newton,
Email, telephone,
workshops, notice
board
Weekly Project leader,
project team
regulations developed by the government of Nepal.
Customers: People of Kathmandu are facing network issues; it is their requirement to have high
speed and high quality data for using better services in mobile telecommunication. The main
purpose of this project is to satisfy the customers and improving the present situation of
Kathmandu (Todorović and et.al., 2015).
Communication Plan
The communication plan for the present project is as follows:
Audience Message Medium Schedule Responsible
Top level
management
Reports;
Strategies;
decision making;
issues;
requirements of
technology;
changes to
corporate business
processes
Meeting, formal
reports, demos
Monthly Project leader,
project team
Management
Committee
Project Overview;
implementation
scope, risk,
budget, user
training; reporting;
change
management
Meeting, formal
reports, demos
As per the need Project leader,
project team
Project
Implementation
Team
Roles and
responsibilities;
progress reports;
strategies; issue
resolution
(Newton,
Email, telephone,
workshops, notice
board
Weekly Project leader,
project team
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Greenberg &
See, 2017)
Departmental
Administrators
System overview,
objectives, forms,
deadlines, training
status and details,
job
responsibilities,
access
Email, training
sessions
At every stage Project leader,
project team,
training
administrator
End Users FAQ, feedbacks,
reviews
Email, telephone After usage Project leader,
project team
Risk Management Plan
For offering high quality project, it is necessary to manage risks effectively at every stage
of project planning. The risk management plan for upgrading 3G to 4G at Kathmandu is as
follows:
Type of Risk Priority Impact of risk Mitigation Plan Assigned to
Delay in getting
approval
High Delay in getting
approval for the
project can result
to influence its
cost and delivery
of time
To chose effective
communication
channel for sharing
real time
information
Team members of
the project
Changes in the
requirements
High Any change within
the requirements
of the project
results to affect the
quality of the
project. Changes
will also lead to
affect the entire
planning and
The scope of the
project created and
defined as per the
requirements of
the project and end
users (Too &
Weaver, 2014)
Project Manager
See, 2017)
Departmental
Administrators
System overview,
objectives, forms,
deadlines, training
status and details,
job
responsibilities,
access
Email, training
sessions
At every stage Project leader,
project team,
training
administrator
End Users FAQ, feedbacks,
reviews
Email, telephone After usage Project leader,
project team
Risk Management Plan
For offering high quality project, it is necessary to manage risks effectively at every stage
of project planning. The risk management plan for upgrading 3G to 4G at Kathmandu is as
follows:
Type of Risk Priority Impact of risk Mitigation Plan Assigned to
Delay in getting
approval
High Delay in getting
approval for the
project can result
to influence its
cost and delivery
of time
To chose effective
communication
channel for sharing
real time
information
Team members of
the project
Changes in the
requirements
High Any change within
the requirements
of the project
results to affect the
quality of the
project. Changes
will also lead to
affect the entire
planning and
The scope of the
project created and
defined as per the
requirements of
the project and end
users (Too &
Weaver, 2014)
Project Manager
enhance the
workload for the
team members
Delay in getting
proper tools and
technologies
High Delay in necessary
tools and
techniques will
result to affect the
processes by
keeping them at
hold. This risk will
enhance the time
of delivery and
cost of the project
To select reliable
vendor who can
deliver machines,
equipments and
technologies on
time as per the
need
Project manager
and team
Lack of talented
and skilled
employees
Low Lack of
experienced and
talented workforce
will affect the
quality of work
and development
of the project. The
company will not
able to accomplish
its objective
behind the
formation of
project (de
Carvalho, Patah
& de Souza
Bido, 2015)
By providing
proper training
sessions to the
employees, firms
enhance their
knowledge and
information
regarding the
project
Project Staff
Implementation
failure
Medium This will affect the
delivery time of
the project along
with the cost
The
implementation of
the project will
depend upon the
Manager
workload for the
team members
Delay in getting
proper tools and
technologies
High Delay in necessary
tools and
techniques will
result to affect the
processes by
keeping them at
hold. This risk will
enhance the time
of delivery and
cost of the project
To select reliable
vendor who can
deliver machines,
equipments and
technologies on
time as per the
need
Project manager
and team
Lack of talented
and skilled
employees
Low Lack of
experienced and
talented workforce
will affect the
quality of work
and development
of the project. The
company will not
able to accomplish
its objective
behind the
formation of
project (de
Carvalho, Patah
& de Souza
Bido, 2015)
By providing
proper training
sessions to the
employees, firms
enhance their
knowledge and
information
regarding the
project
Project Staff
Implementation
failure
Medium This will affect the
delivery time of
the project along
with the cost
The
implementation of
the project will
depend upon the
Manager
requirements of
the project in
effective manner
Banking Problem High This will affect the
financial base of
the project which
will result to keep
the entire project
at hold and affect
its quality and
delivery time
Popular bank with
proper
consultation will
be selected by the
project manager
for getting
financial help
whenever needed
Project Manager
The above plan will help in handling and assessing the risks of the project effectively and
lead to deliver error free and high quality project to the end users.
Project Deployment Plan
The project deployment plan for upgrading the 3G mobile network to 4G in Kathmandu
is as follows:
Deployment
Processes
Actions Taken Responsibility Target
Date
Resource
Needed
Project
Initiation and
conception
Project Charter
Project initiation
Project Manager 5th June
2018
Human
resources
and
physical
resources
Project
definition and
planning
Scope Budget
Work Breakdown
Schedule
Gantt Chart
Communication
Plan
Risk Management
Risk Manager
Accountant
Telecommunication
engineer
1st August
2018
Human
financial
and
technical
resources
Project launch
and execution
Status & Tracking Project Manager 30th
September
Human
financial,
the project in
effective manner
Banking Problem High This will affect the
financial base of
the project which
will result to keep
the entire project
at hold and affect
its quality and
delivery time
Popular bank with
proper
consultation will
be selected by the
project manager
for getting
financial help
whenever needed
Project Manager
The above plan will help in handling and assessing the risks of the project effectively and
lead to deliver error free and high quality project to the end users.
Project Deployment Plan
The project deployment plan for upgrading the 3G mobile network to 4G in Kathmandu
is as follows:
Deployment
Processes
Actions Taken Responsibility Target
Date
Resource
Needed
Project
Initiation and
conception
Project Charter
Project initiation
Project Manager 5th June
2018
Human
resources
and
physical
resources
Project
definition and
planning
Scope Budget
Work Breakdown
Schedule
Gantt Chart
Communication
Plan
Risk Management
Risk Manager
Accountant
Telecommunication
engineer
1st August
2018
Human
financial
and
technical
resources
Project launch
and execution
Status & Tracking Project Manager 30th
September
Human
financial,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
KPIs
Quality
Forecasts
Program Manager
Network Architect
System Administrator
2018 physical
and
technical
resources
Project
performance
and control
Objectives
Quality
Deliverables
Effort & Cost
tracking
Performance
(Chih & Zwikael,
2015)
Project Manager 30th
October
2018
Human
financial
and
technical
resources
Project close Reporting Project Manager
Program Manager
21st
November
2018
Human
resources
and
technical
resources
Recommendations
The suggestions which project team needs to follow for better implementation of the
project plan are as follows:
Project manager and team members should conduct market research properly before
starting the plan. The information will help in developing the plan as per the need and by
following all the necessary aspects.
Risk and quality manager should check for risk and quality at every stage of project
development process for avoiding failure, delay or any other issue (Bucero & Englund,
2015).
The project manager should select an appropriate vendor for supplying needed materials
and equipment for avoiding delay and increase in cost.
Quality
Forecasts
Program Manager
Network Architect
System Administrator
2018 physical
and
technical
resources
Project
performance
and control
Objectives
Quality
Deliverables
Effort & Cost
tracking
Performance
(Chih & Zwikael,
2015)
Project Manager 30th
October
2018
Human
financial
and
technical
resources
Project close Reporting Project Manager
Program Manager
21st
November
2018
Human
resources
and
technical
resources
Recommendations
The suggestions which project team needs to follow for better implementation of the
project plan are as follows:
Project manager and team members should conduct market research properly before
starting the plan. The information will help in developing the plan as per the need and by
following all the necessary aspects.
Risk and quality manager should check for risk and quality at every stage of project
development process for avoiding failure, delay or any other issue (Bucero & Englund,
2015).
The project manager should select an appropriate vendor for supplying needed materials
and equipment for avoiding delay and increase in cost.
CONCLUSION
Thus, from the above study it is concluded that, Kathmandu needs 4G network for better
area coverage and customer satisfaction. With respect to this, effective communication plan, risk
management plan and quality management plan will help in accomplishing the objectives of the
project. Along with this, effective deployment plan will lead to accomplish the objectives of the
project.
Thus, from the above study it is concluded that, Kathmandu needs 4G network for better
area coverage and customer satisfaction. With respect to this, effective communication plan, risk
management plan and quality management plan will help in accomplishing the objectives of the
project. Along with this, effective deployment plan will lead to accomplish the objectives of the
project.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
REFERENCES
Bucero, A., & Englund, R. L. (2015, October). Project sponsorship: Achieving management
commitment for project success. Project Management Institute.
Chih, Y. Y., & Zwikael, O. (2015). Project benefit management: A conceptual framework of
target benefit formulation. International Journal of Project Management, 33(2), 352-362.
de Carvalho, M. M., Patah, L. A., & de Souza Bido, D. (2015). Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), 1509-1522.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Newton, V., Greenberg, A., & See, J. (2017, July). Project Management Implications and
Implementation Roadmap of Human Readiness Levels. In International Conference on
HCI in Business, Government, and Organizations (pp. 99-111). Springer, Cham.
Bucero, A., & Englund, R. L. (2015, October). Project sponsorship: Achieving management
commitment for project success. Project Management Institute.
Chih, Y. Y., & Zwikael, O. (2015). Project benefit management: A conceptual framework of
target benefit formulation. International Journal of Project Management, 33(2), 352-362.
de Carvalho, M. M., Patah, L. A., & de Souza Bido, D. (2015). Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), 1509-1522.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), 202-217.
Newton, V., Greenberg, A., & See, J. (2017, July). Project Management Implications and
Implementation Roadmap of Human Readiness Levels. In International Conference on
HCI in Business, Government, and Organizations (pp. 99-111). Springer, Cham.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290.
Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D. (2015).
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
1382-1394.
Turner, R. (2016). Gower handbook of project management. Routledge.
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290.
Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D. (2015).
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
1382-1394.
Turner, R. (2016). Gower handbook of project management. Routledge.
1 out of 21
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.