This case study analyzes the project management of a reality show, "Rock-n-Bands." It begins with an initial project schedule, network diagram, and critical path analysis, revealing a 12-week timeline. The client's requirement of a 10-week completion is not initially met. The study then explores resource allocation to reduce the project duration to 10 weeks, satisfying the client. A revised schedule, Gantt chart, and resource allocation table are presented, highlighting the addition of resources to specific tasks. The case study demonstrates how effective resource management and timeline adjustments can lead to project success and client satisfaction, using a real-world example. The study concludes with a bibliography of relevant project management literature.
Document Page
Running head: PROJECT MANAGEMENT
Case Study- Rock-n- Bands
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT
Table of Contents
Answer to question number A.........................................................................................................2
Answer to question number B.........................................................................................................5
Answer to question number C.........................................................................................................8
Bibliography..................................................................................................................................10
Document Page
2
PROJECT MANAGEMENT
Answer to question number A
Initial Network diagram
The network diagram for the initial schedule of “Rock –n-Band” Reality project is shown
below:
Figure 1: Network Diagram
(Source: Created by Author)
Project duration
It is identified that the planners ‘ R US takes 12 weeks in order to make all the
arrangements for undertaking the reality show named “Rock-n -Bands”. The initial duration of
the project is provided in the table below:
Document Page
3
PROJECT MANAGEMENT
Task Name Duration Start Finish
Rock'n bands reality 12 wks Tue 3/20/18 Mon 6/11/18
Contract negotiation with selected
music group
3 wks Tue 3/20/18 Mon 4/9/18
Find a construction firm and build
the stage
5 wks Tue 4/3/18 Mon 5/7/18
Contract negotiation with roadies 2 wks Tue 3/20/18 Mon 4/2/18
Screen and hire security personnel 3 wks Tue 3/20/18 Mon 4/9/18
Ticket distribution arrangements 1 wk Tue 4/10/18 Mon 4/16/18
Organize advertising brochures
and souvenir program printing
4 wks Tue 4/10/18 Mon 5/7/18
Logistical arrangements for music
group transportation
1 wk Tue 4/17/18 Mon 4/23/18
Sound equipment arrangements 3 wks Tue 4/10/18 Mon 4/30/18
Processing of travel visas 5 wks Tue 5/8/18 Mon 6/11/18
Hire packaging staff, and make
parking arrangements
4 wks Tue 5/8/18 Mon 6/4/18
Distribute media passes and
arrange for MTV recording
5 wks Tue 4/24/18 Mon 5/28/18
Arrange for con concession sales
and restroom facilities
2 wks Tue 5/8/18 Mon 5/21/18
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
Critical path
The critical path diagram for the initial schedule of “Rock –n-Band” Reality project is
shown below:
Figure 2: Critical path
(Source: Created by Author)
Document Page
5
PROJECT MANAGEMENT
Satisfaction of the client
The planners of the project “Rock-n-Bands” generally requires 12 weeks in order to
complete it successfully. However, the clients generally want to complete the arrangements
within 10 weeks that is 2 weeks before the festival. As the project activities are not completed
successfully within 10 weeks, the clients are not satisfied with the project. In order to satisfy the
clients, it is very much necessary to complete the entire project work within 10 weeks by
allocating resources properly within the project.
Answer to question number B
After proper allocation of resources, the expected timeframe of the client is met within
the project. It is identified that the entire project will be completed successfully within 10 weeks
as per the requirements of the client. The duration of the project after resource allocation is
reflected in the table below:
WB
S
Task Name Duration Start Finish Predecessors
Resource
Names
0
Rock'n and Band
Reality
10 wks
Tue
3/20/18
Mon
5/28/18
A
Contract negotiation
with selected music
group
1 wk Tue 4/3/18
Mon
4/9/18
Worker
1,Additional
worker
B Find a construction firm
and build the stage
2.5 wks Thu
4/12/18
Mon
4/30/18
3 Worker
3,Additional
Document Page
6
PROJECT MANAGEMENT
worker
C
Contract negotiation
with roadies
2 wks
Tue
3/20/18
Mon
4/2/18
Worker 4
D
Screen and hire security
personnel
1.5 wks
Tue
3/20/18
Thu
3/29/18
Worker
2,Additional
worker
E
Ticket distribution
arrangements
1 wk
Tue
4/10/18
Mon
4/16/18
1 Worker 1
F
Organize advertising
brochures and souvenir
program printing
2 wks
Tue
4/10/18
Mon
4/23/18
4
Worker
3,Additional
worker
G
Logistical arrangements
for music group
transportation
1 wk
Tue
4/17/18
Mon
4/23/18
5 Worker 2
H
Sound equipment
arrangements
3 wks Tue 4/3/18
Mon
4/23/18
3,4 Worker 1
I
Processing of travel
visas
5 wks
Tue
4/24/18
Mon
5/28/18
6,8 Worker 2
J
Hire packaging staff,
and make parking
arrangements
4 wks Tue 5/1/18
Mon
5/28/18
5,2,8 Worker 1
K Distribute media passes
and arrange for MTV
5 wks Tue Mon 7 Worker 4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
recording 4/24/18 5/28/18
L
Arrange for con
concession sales and
restroom facilities
2 wks
Tue
5/15/18
Mon
5/28/18
6 Worker 2
Tasks that apply additional resources
The tasks in which additional resources are added are highlighted with yellow in the table
below. It is identified that by adding additional resources within the project schedule, the
intended completion time of the project is met successfully. The entire project will be completed
within 10 weeks that is two weeks before the initiation of the festival.
WBS Task Name Duration Start Finish Predecessors Resource
Names
0 Rock'n and Band
Reality 10 wks Tue
3/20/18
Mon
5/28/18
A
Contract negotiation
with selected music
group
1 wk Tue
4/3/18
Mon
4/9/18
Worker
1,Additional
worker
B Find a construction
firm and build the stage 2.5 wks Thu
4/12/18
Mon
4/30/18 3
Worker
3,Additional
worker
C Contract negotiation
with roadies 2 wks Tue
3/20/18
Mon
4/2/18 Worker 4
D Screen and hire
security personnel 1.5 wks Tue
3/20/18
Thu
3/29/18
Worker
2,Additional
worker
E Ticket distribution
arrangements 1 wk Tue
4/10/18
Mon
4/16/18 1 Worker 1
F
Organize advertising
brochures and souvenir
program printing
2 wks Tue
4/10/18
Mon
4/23/18 4
Worker
3,Additional
worker
G
Logistical
arrangements for music
group transportation
1 wk Tue
4/17/18
Mon
4/23/18 5 Worker 2
Document Page
8
PROJECT MANAGEMENT
H Sound equipment
arrangements 3 wks Tue
4/3/18
Mon
4/23/18 3,4 Worker 1
I Processing of travel
visas 5 wks Tue
4/24/18
Mon
5/28/18 6,8 Worker 2
J
Hire packaging staff,
and make parking
arrangements
4 wks Tue
5/1/18
Mon
5/28/18 5,2,8 Worker 1
K
Distribute media
passes and arrange for
MTV recording
5 wks Tue
4/24/18
Mon
5/28/18 7 Worker 4
L
Arrange for con
concession sales and
restroom facilities
2 wks Tue
5/15/18
Mon
5/28/18 6 Worker 2
Answer to question number C
Figure 3: Gantt chart
(Source: Created by Author)
It is identified that the objectives of the client are successfully met.. The entire project of
Rock-n –Band is completed within 10 weeks that is 2 weeks before the festival in order to avoid
Document Page
9
PROJECT MANAGEMENT
any type of problem or issue. The organization wants to employ at most 5 workers so that
maximum two workers can be engaged within an activity in order to execute it successfully
within the assumed time and as per the demand 5 employs are employed for executing the
project successfully.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
Bibliography
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning
from and with each other. Routledge.
Chih, Y. Y., & Zwikael, O. (2015). Project benefit management: A conceptual framework of
target benefit formulation. International Journal of Project Management, 33(2), 352-362.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), 1377-1392.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project
risk management methodology for small firms. International journal of project
management, 32(2), 327-340.
Riol, H., & Thuillier, D. (2015). Project management for academic research projects: balancing
structure and flexibility. International Journal of Project Organisation and
Management, 7(3), 251-269.
Snyder, C. S. (2014). A guide to the project management body of knowledge: PMBOK (®)