This report explains the project management approach for developing a web portal for Lizzie Leather Belt Company. It suggests Agile methodology for efficient development and highlights the strengths and weaknesses of teamwork. It also discusses the communication plan and professional and legal issues involved. The report provides a Gantt chart and schedule of activities for successful project delivery.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Project Management
Name of Student
Name of the University
Author Note
Project Management
Name of Student
Name of the University
Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT MANAGEMENT
Table of Contents
Introduction......................................................................................................................................3
Project Management Approach.......................................................................................................3
Schedule of the Activities................................................................................................................3
Strength of Team Work...................................................................................................................6
Weaknesses of Team Work.............................................................................................................6
Communication Plan.......................................................................................................................7
Professional and Legal Issues..........................................................................................................7
Conclusion.......................................................................................................................................8
Table of Contents
Introduction......................................................................................................................................3
Project Management Approach.......................................................................................................3
Schedule of the Activities................................................................................................................3
Strength of Team Work...................................................................................................................6
Weaknesses of Team Work.............................................................................................................6
Communication Plan.......................................................................................................................7
Professional and Legal Issues..........................................................................................................7
Conclusion.......................................................................................................................................8
PROJECT MANAGEMENT
Introduction
Lizzie Leather belt Company has been expanding the business through developing a web
portal that will be helping in connectivity with the customers available online. This will be
helpful in reaching the customers globally and allowing them to avail the products and services
being offered. This report highlights on the project management approach that will be helpful in
delivering the objectives of the project, as it is one of the necessary element for the delivery of
the project. Other crucial component of the project delivery is the teamwork and this report
focuses on explaining the strengths and weaknesses of the teamwork.
Project Management Approach
According to Schwalbe (2015), for the development of the Web Portal, ‘Agile’
methodology can be suggested as the most appropriate approach for the successful development.
Utilizing other approach could be more complex and leaving certain sectors those could affect
the overall growth and development of the project. In manner to have higher efficiency, Agile
was supposed to be better than other methodologies. It will be helpful in meeting the goals of the
project of Web Portal development and will be effectively meeting with the business
requirements of the Lizzie Leather belt Company. It focuses on the accomplishment of the
project activities in a linear method and accomplishment of all the activities within the schedule.
It is also change acceptable and thus, new requirements approaching while delivery of the
project; it can be incorporated within the project in smooth manner (Whetten and Cameron
2014). It will also be helpful in managing the risks and uncertainties those could possibly affect
the growth of the project.
Introduction
Lizzie Leather belt Company has been expanding the business through developing a web
portal that will be helping in connectivity with the customers available online. This will be
helpful in reaching the customers globally and allowing them to avail the products and services
being offered. This report highlights on the project management approach that will be helpful in
delivering the objectives of the project, as it is one of the necessary element for the delivery of
the project. Other crucial component of the project delivery is the teamwork and this report
focuses on explaining the strengths and weaknesses of the teamwork.
Project Management Approach
According to Schwalbe (2015), for the development of the Web Portal, ‘Agile’
methodology can be suggested as the most appropriate approach for the successful development.
Utilizing other approach could be more complex and leaving certain sectors those could affect
the overall growth and development of the project. In manner to have higher efficiency, Agile
was supposed to be better than other methodologies. It will be helpful in meeting the goals of the
project of Web Portal development and will be effectively meeting with the business
requirements of the Lizzie Leather belt Company. It focuses on the accomplishment of the
project activities in a linear method and accomplishment of all the activities within the schedule.
It is also change acceptable and thus, new requirements approaching while delivery of the
project; it can be incorporated within the project in smooth manner (Whetten and Cameron
2014). It will also be helpful in managing the risks and uncertainties those could possibly affect
the growth of the project.
PROJECT MANAGEMENT
Schedule of the Activities
W
BS
Task Name Durati
on
Start Finish PC
0 Development of Cloud Based Web
Portal for Lizzie Leather belt Company
90
days
Thu 11/9/17 Wed 3/14/18
1 Project Initiation 12
days
Thu 11/9/17 Fri 11/24/17
1.1 Analysis of Project Requirement 2 days Thu 11/9/17 Fri 11/10/17
1.2 Analysis of Existing Issues in the
Organization
2 days Mon 11/13/17 Tue 11/14/17 2
1.3 Analysis of the Benefit from the
Proposed New Cloud Based web portal
2 days Wed 11/15/17 Thu 11/16/17 3,2
1.4 Analysis of the Need for New
Accounting System
3 days Fri 11/17/17 Tue 11/21/17 4,2
1.5 Preparation of a Draft Project Plan 3 days Wed 11/22/17 Fri 11/24/17 5,4
2 Project Planning 20
days
Mon 11/27/17 Fri 12/22/17
2.1 Appointment of Stakeholders for the
Project
5 days Mon 11/27/17 Fri 12/1/17 6
2.2 Analysis of the Initial Project Plan 2 days Mon 12/4/17 Tue 12/5/17 6,8
2.3 Discussion between Stakeholders 2 days Wed 12/6/17 Thu 12/7/17 8,9
2.4 Cost Estimation 2 days Fri 12/8/17 Mon
12/11/17
10
2.5 Time Estimation 2 days Tue 12/12/17 Wed
12/13/17
10,
2.6 Preparation of Final Project Plan 5 days Thu 12/14/17 Wed
12/20/17
10
2.7 Selection of Development Team 2 days Thu 12/21/17 Fri 12/22/17 13
3 Project Development 38
days
Mon 12/25/17 Wed 2/14/18
Schedule of the Activities
W
BS
Task Name Durati
on
Start Finish PC
0 Development of Cloud Based Web
Portal for Lizzie Leather belt Company
90
days
Thu 11/9/17 Wed 3/14/18
1 Project Initiation 12
days
Thu 11/9/17 Fri 11/24/17
1.1 Analysis of Project Requirement 2 days Thu 11/9/17 Fri 11/10/17
1.2 Analysis of Existing Issues in the
Organization
2 days Mon 11/13/17 Tue 11/14/17 2
1.3 Analysis of the Benefit from the
Proposed New Cloud Based web portal
2 days Wed 11/15/17 Thu 11/16/17 3,2
1.4 Analysis of the Need for New
Accounting System
3 days Fri 11/17/17 Tue 11/21/17 4,2
1.5 Preparation of a Draft Project Plan 3 days Wed 11/22/17 Fri 11/24/17 5,4
2 Project Planning 20
days
Mon 11/27/17 Fri 12/22/17
2.1 Appointment of Stakeholders for the
Project
5 days Mon 11/27/17 Fri 12/1/17 6
2.2 Analysis of the Initial Project Plan 2 days Mon 12/4/17 Tue 12/5/17 6,8
2.3 Discussion between Stakeholders 2 days Wed 12/6/17 Thu 12/7/17 8,9
2.4 Cost Estimation 2 days Fri 12/8/17 Mon
12/11/17
10
2.5 Time Estimation 2 days Tue 12/12/17 Wed
12/13/17
10,
2.6 Preparation of Final Project Plan 5 days Thu 12/14/17 Wed
12/20/17
10
2.7 Selection of Development Team 2 days Thu 12/21/17 Fri 12/22/17 13
3 Project Development 38
days
Mon 12/25/17 Wed 2/14/18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT MANAGEMENT
3.1 Allocation of Resources 5 days Mon 12/25/17 Fri 12/29/17 13
3.2 Procurement of Necessary Hardware 3 days Mon 1/1/18 Wed 1/3/18 13
3.3 Procurement of Necessary Software 3 days Mon 1/1/18 Wed 1/3/18 13,
16
3.4 Initiation of Development 5 days Thu 1/4/18 Wed 1/10/18 13,
17,
18
3.5 Subscription to Cloud Services 2 days Thu 1/11/18 Fri 1/12/18 19
3.6 Development of the Online Accounting
System
15
days
Mon 1/15/18 Fri 2/2/18 19,
20
3.7 Development of Online Intelligent
Portal
8 days Mon 2/5/18 Wed 2/14/18 21
4 Project Testing 5 days Thu 2/15/18 Wed 2/21/18
4.1 Testing of the Developed Accounting
System
3 days Thu 2/15/18 Mon 2/19/18 21,
22
4.2 Testing of the Portal 2 days Tue 2/20/18 Wed 2/21/18 24
5 Project Execution 7 days Thu 2/22/18 Fri 3/2/18
5.1 Execution of the Developed Software 3 days Thu 2/22/18 Mon 2/26/18 21,
22,
23,
24
5.2 Identification of Bugs and Glitches 2 days Tue 2/27/18 Wed 2/28/18 27
5.3 Risk Analysis 2 days Tue 2/27/18 Wed 2/28/18 27
5.4 Risk Management 2 days Thu 3/1/18 Fri 3/2/18 29,
28
6 Project Closure 8 days Mon 3/5/18 Wed 3/14/18
6.1 Project Completion 2 days Mon 3/5/18 Tue 3/6/18 30
6.2 Project Documentation 3 days Wed 3/7/18 Fri 3/9/18 32
6.3 Stakeholder Sign Off 2 days Mon 3/12/18 Tue 3/13/18 33
6.4 Project Manager Sign Off 1 day Wed 3/14/18 Wed 3/14/18 34
3.1 Allocation of Resources 5 days Mon 12/25/17 Fri 12/29/17 13
3.2 Procurement of Necessary Hardware 3 days Mon 1/1/18 Wed 1/3/18 13
3.3 Procurement of Necessary Software 3 days Mon 1/1/18 Wed 1/3/18 13,
16
3.4 Initiation of Development 5 days Thu 1/4/18 Wed 1/10/18 13,
17,
18
3.5 Subscription to Cloud Services 2 days Thu 1/11/18 Fri 1/12/18 19
3.6 Development of the Online Accounting
System
15
days
Mon 1/15/18 Fri 2/2/18 19,
20
3.7 Development of Online Intelligent
Portal
8 days Mon 2/5/18 Wed 2/14/18 21
4 Project Testing 5 days Thu 2/15/18 Wed 2/21/18
4.1 Testing of the Developed Accounting
System
3 days Thu 2/15/18 Mon 2/19/18 21,
22
4.2 Testing of the Portal 2 days Tue 2/20/18 Wed 2/21/18 24
5 Project Execution 7 days Thu 2/22/18 Fri 3/2/18
5.1 Execution of the Developed Software 3 days Thu 2/22/18 Mon 2/26/18 21,
22,
23,
24
5.2 Identification of Bugs and Glitches 2 days Tue 2/27/18 Wed 2/28/18 27
5.3 Risk Analysis 2 days Tue 2/27/18 Wed 2/28/18 27
5.4 Risk Management 2 days Thu 3/1/18 Fri 3/2/18 29,
28
6 Project Closure 8 days Mon 3/5/18 Wed 3/14/18
6.1 Project Completion 2 days Mon 3/5/18 Tue 3/6/18 30
6.2 Project Documentation 3 days Wed 3/7/18 Fri 3/9/18 32
6.3 Stakeholder Sign Off 2 days Mon 3/12/18 Tue 3/13/18 33
6.4 Project Manager Sign Off 1 day Wed 3/14/18 Wed 3/14/18 34
PROJECT MANAGEMENT
Gantt Chart:
Figure 1: Gantt Chart
Gantt Chart:
Figure 1: Gantt Chart
PROJECT MANAGEMENT
Source: Created by Author Using MS Project
The activities mentioned in the above table will be helpful in delivering the project of
highest standard. It will be helpful in providing the customers best quality services through
eliminating all the glitches and bugs that might be raised in the project. Since a risk management
and monitoring and controlling activity has been incorporated, the project delivery will be of
highest quality (Kerzner and Kerzner 2017). Accomplishment of the above activities in an
efficient and effective manner will be helpful in managing the code quality if this transformation
within the existing system of the Lizzie Leather belt Company.
Strength of Team Work
Finkleman (2015) explained that the team would have many experiences as the team
member will be different backgrounds and will be helpful in managing the different sectors of
the job. Same had been stated by Laudon and Laudon (2016), explaining that the experiences
gain by them can be helpful in accomplishing the activities within the project in an effective and
efficient manner. Above discussion is helpful in stating that the workload can be subdivided
among them and hence, the job could be accomplished in less time and the efficiency can be
enhanced. It will allow in managing the activities in less interval of time through distributing the
workloads among the team members.
Weaknesses of Team Work
There is only one deficiency of the teamwork that can be stated as if an individual lags in
the accomplishment of hos or sector of the job whole team member will have to face the loss
(Abrahamasson et al. 2017). This is the one weakness however; it can affect the overall
Source: Created by Author Using MS Project
The activities mentioned in the above table will be helpful in delivering the project of
highest standard. It will be helpful in providing the customers best quality services through
eliminating all the glitches and bugs that might be raised in the project. Since a risk management
and monitoring and controlling activity has been incorporated, the project delivery will be of
highest quality (Kerzner and Kerzner 2017). Accomplishment of the above activities in an
efficient and effective manner will be helpful in managing the code quality if this transformation
within the existing system of the Lizzie Leather belt Company.
Strength of Team Work
Finkleman (2015) explained that the team would have many experiences as the team
member will be different backgrounds and will be helpful in managing the different sectors of
the job. Same had been stated by Laudon and Laudon (2016), explaining that the experiences
gain by them can be helpful in accomplishing the activities within the project in an effective and
efficient manner. Above discussion is helpful in stating that the workload can be subdivided
among them and hence, the job could be accomplished in less time and the efficiency can be
enhanced. It will allow in managing the activities in less interval of time through distributing the
workloads among the team members.
Weaknesses of Team Work
There is only one deficiency of the teamwork that can be stated as if an individual lags in
the accomplishment of hos or sector of the job whole team member will have to face the loss
(Abrahamasson et al. 2017). This is the one weakness however; it can affect the overall
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PROJECT MANAGEMENT
development and growth of the proposed transformation within the existing system of the Lizzie
Leather belt Company.
Communication Plan
According to Laudon and Laudon (2016), brainstorming can be an effective approach
towards receiving the feedback and suggestion from the team members. Moreover, innovative
and unique approaches can be represented by the members through this process that can be
helpful in implementing innovation to the project.
Regular meetings with the team member can be appreciated for the accomplishment of
the effective communication with the team members. It will allow to listen to the problems and
suggestions from the team members.
Survey or individual meetings will ensure the privacy of the team members and they can
provide suggestions, solutions, or compliant without any hesitation. It will allow the team
members to present their problems and point of view without any pressure (Nicholas and Steven
2017).
Suggestion valet can also be implemented for getting reviews from them and get more
suggestions and approaches from their side. It will promote them to indulge more towards
enhancing the cooperation within the team.
Professional and Legal Issues
Hosting a Web Portal needs to be passed by several legislative processes that should must
be considered in the prior of launching the portal. The individuals might not feel appropriate of
leaving the traditional operational way and might not want to switch to the transformed scenario
development and growth of the proposed transformation within the existing system of the Lizzie
Leather belt Company.
Communication Plan
According to Laudon and Laudon (2016), brainstorming can be an effective approach
towards receiving the feedback and suggestion from the team members. Moreover, innovative
and unique approaches can be represented by the members through this process that can be
helpful in implementing innovation to the project.
Regular meetings with the team member can be appreciated for the accomplishment of
the effective communication with the team members. It will allow to listen to the problems and
suggestions from the team members.
Survey or individual meetings will ensure the privacy of the team members and they can
provide suggestions, solutions, or compliant without any hesitation. It will allow the team
members to present their problems and point of view without any pressure (Nicholas and Steven
2017).
Suggestion valet can also be implemented for getting reviews from them and get more
suggestions and approaches from their side. It will promote them to indulge more towards
enhancing the cooperation within the team.
Professional and Legal Issues
Hosting a Web Portal needs to be passed by several legislative processes that should must
be considered in the prior of launching the portal. The individuals might not feel appropriate of
leaving the traditional operational way and might not want to switch to the transformed scenario
PROJECT MANAGEMENT
(Conde et al. 2017). Proper training will be needed for the users to utilize the web portal in an
effective and efficient manner. Same concern was provided by Dingsoy et al. (2016) stating that
some of the individuals might not know how to use the portal and thus, it could affect the
effective implementation of the change. The privacy and security of the individuals should must
be provided the highest priority in manner to protect their privacy and security (Nazi et al. 2016).
Hosting the website at national and international level will have to make proper agreement with
the hosting company and the government. The new operational way should must comply with
the pre-existing policies of the company regarding the privacy and security of the individuals.
The Web Portal will be surely containing the personal and sensitive information of the
employees and customers and thus, it must comply with the privacy and security regulations of
the country.
Unauthorized access can be another issue that can be categorized in professional issues as
an unauthorized user might access the portal of another and utilize it for personal benefits
(Orenga and Chalmeta 2016). However, the individual might face the authorities for the deeds
that he is not known to. Proper firewall and protection should be implemented within the
business portal in manner to restrict the access and protecting the professional life of the
individuals.
Conclusion
The information provided in the above report can be helpful in managing the operations
and consideration of the aspects related to the implementation of cloud based web portal for the
Lizzie Leather belt Company and enhance the performance of the organization. This report
emphasizes on the mentioned activities involved in this implementation and accomplishing of
(Conde et al. 2017). Proper training will be needed for the users to utilize the web portal in an
effective and efficient manner. Same concern was provided by Dingsoy et al. (2016) stating that
some of the individuals might not know how to use the portal and thus, it could affect the
effective implementation of the change. The privacy and security of the individuals should must
be provided the highest priority in manner to protect their privacy and security (Nazi et al. 2016).
Hosting the website at national and international level will have to make proper agreement with
the hosting company and the government. The new operational way should must comply with
the pre-existing policies of the company regarding the privacy and security of the individuals.
The Web Portal will be surely containing the personal and sensitive information of the
employees and customers and thus, it must comply with the privacy and security regulations of
the country.
Unauthorized access can be another issue that can be categorized in professional issues as
an unauthorized user might access the portal of another and utilize it for personal benefits
(Orenga and Chalmeta 2016). However, the individual might face the authorities for the deeds
that he is not known to. Proper firewall and protection should be implemented within the
business portal in manner to restrict the access and protecting the professional life of the
individuals.
Conclusion
The information provided in the above report can be helpful in managing the operations
and consideration of the aspects related to the implementation of cloud based web portal for the
Lizzie Leather belt Company and enhance the performance of the organization. This report
emphasizes on the mentioned activities involved in this implementation and accomplishing of
PROJECT MANAGEMENT
these activities as a team. It also explains the benefits and disadvantages of the teamwork. The
statements and suggestions provided by the different authors explain the need of the effective
approaches as mentioned in the above report based on the above information, it can be concluded
that the teamwork is an essential and crucial element for the successful delivery of the project.
these activities as a team. It also explains the benefits and disadvantages of the teamwork. The
statements and suggestions provided by the different authors explain the need of the effective
approaches as mentioned in the above report based on the above information, it can be concluded
that the teamwork is an essential and crucial element for the successful delivery of the project.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT MANAGEMENT
References
Abrahamsson, P., Salo, O., Ronkainen, J. and Warsta, J., 2017. Agile software development
methods: Review and analysis. arXiv preprint arXiv:1709.08439.
Conde, M.A., Colomo-Palacios, R., García-Peñalvo, F.J. and Larrucea, X., 2017. Teamwork
assessment in the educational web of data: A learning analytics approach towards ISO
10018. Telematics and Informatics.
Dingsøyr, T., Fægri, T.E., Dybå, T., Haugset, B. and Lindsjørn, Y., 2016. Team performance in
software development: research results versus agile principles. IEEE Software, 33(4), pp.106-
110.
Finkelman, A., 2015. Leadership and management for nurses: Core competencies for quality
care. Pearson.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Laudon, K.C. and Laudon, J.P., 2016. Management information system. Pearson Education
India.
Layton, M.C. and Ostermiller, S.J., 2017. Agile project management for dummies. John Wiley &
Sons.
Niazi, M., Mahmood, S., Alshayeb, M., Qureshi, A.M., Faisal, K. and Cerpa, N., 2016. Toward
successful project management in global software development. International Journal of Project
Management, 34(8), pp.1553-1567.
References
Abrahamsson, P., Salo, O., Ronkainen, J. and Warsta, J., 2017. Agile software development
methods: Review and analysis. arXiv preprint arXiv:1709.08439.
Conde, M.A., Colomo-Palacios, R., García-Peñalvo, F.J. and Larrucea, X., 2017. Teamwork
assessment in the educational web of data: A learning analytics approach towards ISO
10018. Telematics and Informatics.
Dingsøyr, T., Fægri, T.E., Dybå, T., Haugset, B. and Lindsjørn, Y., 2016. Team performance in
software development: research results versus agile principles. IEEE Software, 33(4), pp.106-
110.
Finkelman, A., 2015. Leadership and management for nurses: Core competencies for quality
care. Pearson.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Laudon, K.C. and Laudon, J.P., 2016. Management information system. Pearson Education
India.
Layton, M.C. and Ostermiller, S.J., 2017. Agile project management for dummies. John Wiley &
Sons.
Niazi, M., Mahmood, S., Alshayeb, M., Qureshi, A.M., Faisal, K. and Cerpa, N., 2016. Toward
successful project management in global software development. International Journal of Project
Management, 34(8), pp.1553-1567.
PROJECT MANAGEMENT
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Taylor & Francis.
Orenga-Roglá, S. and Chalmeta, R., 2016. Social customer relationship management: taking
advantage of Web 2.0 and Big Data technologies. SpringerPlus, 5(1), p.1462.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Whetten, D. and Cameron, K., 2014. Developing Management Skills: Global Edition. Pearson
Higher Ed.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Taylor & Francis.
Orenga-Roglá, S. and Chalmeta, R., 2016. Social customer relationship management: taking
advantage of Web 2.0 and Big Data technologies. SpringerPlus, 5(1), p.1462.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Whetten, D. and Cameron, K., 2014. Developing Management Skills: Global Edition. Pearson
Higher Ed.
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.