This document provides a detailed project management plan for the implementation of an E-Toll system in Hyderabad Ring Road. It includes cost allocation and resource management plans, as well as a procurement management plan for outsourcing work. The document also includes a detailed project schedule and milestones.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Project: E-Toll system in India Hyderabad Ring Road
Name of the Student
Name of the University
Author’s Note
Project: E-Toll system in India Hyderabad Ring Road
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
PROJECT MANAGEMENT
Table of Contents
3. Project cost and resource management........................................................................................2
3.1 Cost allocation plan...............................................................................................................2
3.2 Resource allocation plan........................................................................................................3
3.3 Detailed resource and cost breakdown..................................................................................4
4. Project procurement management for the outsource work..........................................................9
4.1 Outsourcing needs of the project...........................................................................................9
4.2 Detailed project schedule.......................................................................................................9
4.3 Cost allocation plan.............................................................................................................13
4.4 Time allocation plan............................................................................................................14
4.5 Gantt chart and other planning details.................................................................................16
4.6 Milestones and deliverables.................................................................................................18
Bibliography..................................................................................................................................19
PROJECT MANAGEMENT
Table of Contents
3. Project cost and resource management........................................................................................2
3.1 Cost allocation plan...............................................................................................................2
3.2 Resource allocation plan........................................................................................................3
3.3 Detailed resource and cost breakdown..................................................................................4
4. Project procurement management for the outsource work..........................................................9
4.1 Outsourcing needs of the project...........................................................................................9
4.2 Detailed project schedule.......................................................................................................9
4.3 Cost allocation plan.............................................................................................................13
4.4 Time allocation plan............................................................................................................14
4.5 Gantt chart and other planning details.................................................................................16
4.6 Milestones and deliverables.................................................................................................18
Bibliography..................................................................................................................................19
2
PROJECT MANAGEMENT
3. Project cost and resource management
3.1 Cost allocation plan
The cost allocation plans as well as the direct cost rate proposals are generally
documented which is further utilized for the purpose of cost recovery that help the entities in
reflecting the allocated resources. The cost allocation plan that is mainly created for
implementing the E-toll system generally helps in reflecting on the activities in which proper
amount of costs are generally allocated in order to successfully complete the work of the project
quite effectively by getting review from 44 people [5]. The figure that is provided below
generally reflects on the allocation of project cost as per the phases of the project. The below
figure helps in reflecting that $18,720 is generally allocated in the initiation phase of the project
whereas $22,032 is allocated for completing the planning phase of the project. Furthermore, it is
identified that for completing the project execution, budget of around $138,968 is allocated.
$ 0.00
$ 20,000.00
$ 40,000.00
$ 60,000.00
$ 80,000.00
$ 100,000.00
$ 120,000.00
$ 140,000.00
$ 160,000.00
Actual Cost Remaining Cost Baseline Cost
Figure 3: Cost allocation overview
(Source: Created by Author)
PROJECT MANAGEMENT
3. Project cost and resource management
3.1 Cost allocation plan
The cost allocation plans as well as the direct cost rate proposals are generally
documented which is further utilized for the purpose of cost recovery that help the entities in
reflecting the allocated resources. The cost allocation plan that is mainly created for
implementing the E-toll system generally helps in reflecting on the activities in which proper
amount of costs are generally allocated in order to successfully complete the work of the project
quite effectively by getting review from 44 people [5]. The figure that is provided below
generally reflects on the allocation of project cost as per the phases of the project. The below
figure helps in reflecting that $18,720 is generally allocated in the initiation phase of the project
whereas $22,032 is allocated for completing the planning phase of the project. Furthermore, it is
identified that for completing the project execution, budget of around $138,968 is allocated.
$ 0.00
$ 20,000.00
$ 40,000.00
$ 60,000.00
$ 80,000.00
$ 100,000.00
$ 120,000.00
$ 140,000.00
$ 160,000.00
Actual Cost Remaining Cost Baseline Cost
Figure 3: Cost allocation overview
(Source: Created by Author)
3
PROJECT MANAGEMENT
3.2 Resource allocation plan
Resource allocation is one of the plan or a process that helps in managing the assets of
the project in order to support the strategic goal of the organization effectively. The allocation of
resource generally includes incorporating both tangible as well as intangible costs of the project.
It is found that the figure which is provided below reflects on the resources that are generally
allocated for completing the implementation of E-toll system within Hyderabad rail road [6].The
below chart showcases the project stakeholders and the time for which they are allocated within
the project in order to successfully complete the work of the project successfully. It is identified
that successfully allocation of project resources are very much important for effective execution
of the project activities as per the time ad budget of the project.
Project manager
Project planner
HR manager
Financial manager
Quality analyst
Contractor
Sub-contractor
Worker
Technical engineer
Designer
Database adminisrator
Tester
0 hrs
50 hrs
100 hrs
150 hrs
200 hrs
250 hrs
300 hrs
350 hrs
400 hrs
450 hrs
500 hrs
Actual Work Remaining Work Baseline Work
Figure 4: Resource allocation overview
(Source: Created by Author)
PROJECT MANAGEMENT
3.2 Resource allocation plan
Resource allocation is one of the plan or a process that helps in managing the assets of
the project in order to support the strategic goal of the organization effectively. The allocation of
resource generally includes incorporating both tangible as well as intangible costs of the project.
It is found that the figure which is provided below reflects on the resources that are generally
allocated for completing the implementation of E-toll system within Hyderabad rail road [6].The
below chart showcases the project stakeholders and the time for which they are allocated within
the project in order to successfully complete the work of the project successfully. It is identified
that successfully allocation of project resources are very much important for effective execution
of the project activities as per the time ad budget of the project.
Project manager
Project planner
HR manager
Financial manager
Quality analyst
Contractor
Sub-contractor
Worker
Technical engineer
Designer
Database adminisrator
Tester
0 hrs
50 hrs
100 hrs
150 hrs
200 hrs
250 hrs
300 hrs
350 hrs
400 hrs
450 hrs
500 hrs
Actual Work Remaining Work Baseline Work
Figure 4: Resource allocation overview
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4
PROJECT MANAGEMENT
3.3 Detailed resource and cost breakdown
The implementation of E-toll system on Hyderabad ring road is considered as one of the
important project that helps in reducing traffic congestion and further helps in saving the time of
the drivers. It is found that in order to develop the schedule of the project so that the project
activities can be executed properly, it is quite necessary to create detailed resources as well as
cost of the project. [10].The detailed table that is given below helps in showcasing each and
every resources of the project that are generally needed for successful execution of the project. In
addition to this, the below table helps in reflecting on the cost that is generally required for the
execution of each of the activities of the project successfully.
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0
Implementation of
e-toll system in
Hyderabad Ring
road
210 days
Fri
12-
04-19
Thu
30-01-
20
$ 200,000.00
1 Initiation phase 45 days
Fri
12-
04-19
Thu
13-06-
19
$ 18,720.00
1.1
Developing
business case
10 days
Fri
12-
04-19
Thu
25-04-
19
Project manager $ 4,000.00
1.2 Undertaking
feasibility study
12 days Fri
26-
Mon
13-05-
2 Financial $ 3,840.00
PROJECT MANAGEMENT
3.3 Detailed resource and cost breakdown
The implementation of E-toll system on Hyderabad ring road is considered as one of the
important project that helps in reducing traffic congestion and further helps in saving the time of
the drivers. It is found that in order to develop the schedule of the project so that the project
activities can be executed properly, it is quite necessary to create detailed resources as well as
cost of the project. [10].The detailed table that is given below helps in showcasing each and
every resources of the project that are generally needed for successful execution of the project. In
addition to this, the below table helps in reflecting on the cost that is generally required for the
execution of each of the activities of the project successfully.
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0
Implementation of
e-toll system in
Hyderabad Ring
road
210 days
Fri
12-
04-19
Thu
30-01-
20
$ 200,000.00
1 Initiation phase 45 days
Fri
12-
04-19
Thu
13-06-
19
$ 18,720.00
1.1
Developing
business case
10 days
Fri
12-
04-19
Thu
25-04-
19
Project manager $ 4,000.00
1.2 Undertaking
feasibility study
12 days Fri
26-
Mon
13-05-
2 Financial $ 3,840.00
5
PROJECT MANAGEMENT
04-19 19 manager
1.3
Establishing
charter
8 days
Tue
14-
05-19
Thu
23-05-
19
3
Project manager,
Project planner
$ 6,080.00
1.4
Appointing
team members
15 days
Fri
24-
05-19
Thu
13-06-
19
4 HR manager $ 4,800.00
1.5
Milestone 1:
Completion of
initiation phase
0 days
Thu
13-
06-19
Thu
13-06-
19
5 $ 0.00
2 Planning phase 37 days
Fri
14-
06-19
Mon
05-08-
19
$ 22,032.00
2.1
Development of
project plan
13 days
Fri
14-
06-19
Tue
02-07-
19
5 Project manager $ 5,200.00
2.2
Development of
resource plan
14 days
Fri
14-
06-19
Wed
03-07-
19
5 HR manager $ 4,480.00
2.3
Developing
financial plan
15 days
Fri
14-
06-19
Thu
04-07-
19
6
Financial
manager
$ 4,800.00
2.4 Developing 12 days Fri Mon 10 Quality analyst $ 3,552.00
PROJECT MANAGEMENT
04-19 19 manager
1.3
Establishing
charter
8 days
Tue
14-
05-19
Thu
23-05-
19
3
Project manager,
Project planner
$ 6,080.00
1.4
Appointing
team members
15 days
Fri
24-
05-19
Thu
13-06-
19
4 HR manager $ 4,800.00
1.5
Milestone 1:
Completion of
initiation phase
0 days
Thu
13-
06-19
Thu
13-06-
19
5 $ 0.00
2 Planning phase 37 days
Fri
14-
06-19
Mon
05-08-
19
$ 22,032.00
2.1
Development of
project plan
13 days
Fri
14-
06-19
Tue
02-07-
19
5 Project manager $ 5,200.00
2.2
Development of
resource plan
14 days
Fri
14-
06-19
Wed
03-07-
19
5 HR manager $ 4,480.00
2.3
Developing
financial plan
15 days
Fri
14-
06-19
Thu
04-07-
19
6
Financial
manager
$ 4,800.00
2.4 Developing 12 days Fri Mon 10 Quality analyst $ 3,552.00
6
PROJECT MANAGEMENT
quality plan
05-
07-19
22-07-
19
2.5
Developing
acceptance plan
10 days
Tue
23-
07-19
Mon
05-08-
19
11 Project manager $ 4,000.00
2.6
Milestone
2:Completion of
planning phase
0 days
Mon
05-
08-19
Mon
05-08-
19
12 $ 0.00
3 Designing phase 25 days
Tue
06-
08-19
Mon
09-09-
19
$ 8,720.00
3.1
Developing
design for the E-toll
system
20 days
Tue
06-
08-19
Mon
02-09-
19
12 Designer $ 5,600.00
3.2
Sending the
design for approval
2 days
Tue
03-
09-19
Wed
04-09-
19
15
Contractor,
Project planner,
Sub-contractor
$ 1,920.00
3.3
Getting
approval on the
project design
3 days
Thu
05-
09-19
Mon
09-09-
19
16 Project manager $ 1,200.00
3.4 Milestone
3:Completion of
designing phase of
0 days Mon
09-
Mon
09-09-
17 $ 0.00
PROJECT MANAGEMENT
quality plan
05-
07-19
22-07-
19
2.5
Developing
acceptance plan
10 days
Tue
23-
07-19
Mon
05-08-
19
11 Project manager $ 4,000.00
2.6
Milestone
2:Completion of
planning phase
0 days
Mon
05-
08-19
Mon
05-08-
19
12 $ 0.00
3 Designing phase 25 days
Tue
06-
08-19
Mon
09-09-
19
$ 8,720.00
3.1
Developing
design for the E-toll
system
20 days
Tue
06-
08-19
Mon
02-09-
19
12 Designer $ 5,600.00
3.2
Sending the
design for approval
2 days
Tue
03-
09-19
Wed
04-09-
19
15
Contractor,
Project planner,
Sub-contractor
$ 1,920.00
3.3
Getting
approval on the
project design
3 days
Thu
05-
09-19
Mon
09-09-
19
16 Project manager $ 1,200.00
3.4 Milestone
3:Completion of
designing phase of
0 days Mon
09-
Mon
09-09-
17 $ 0.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7
PROJECT MANAGEMENT
the project 09-19 19
4
Implementation
phase
76 days
Tue
10-
09-19
Tue
24-12-
19
$ 138,968.00
4.1
Connecting in-
road sensors
26 days
Tue
10-
09-19
Tue
15-10-
19
17
Database
administrator
$ 8,320.00
4.2
Putting
overhead cameras
25 days
Tue
10-
09-19
Mon
14-10-
19
17
Technical
engineer
$ 7,000.00
4.3
Connecting toll
checker
22 days
Tue
15-
10-19
Wed
13-11-
19
21
Contractor,
Hardware[1]
$ 43,040.00
4.4
Vehicle to
Roadside
Communication
20 days
Tue
15-
10-19
Mon
11-11-
19
21
Software[1],Sub-
contractor,
Technical
engineer
$ 45,688.00
4.5
Development of
e-toll system
22 days
Tue
12-
11-19
Wed
11-12-
19
23
Additional
cost[1],Database
administrator
$ 32,040.00
4.6 Testing of the
system
9 days Thu
12-
Tue
24-12-
24 Tester $ 2,880.00
PROJECT MANAGEMENT
the project 09-19 19
4
Implementation
phase
76 days
Tue
10-
09-19
Tue
24-12-
19
$ 138,968.00
4.1
Connecting in-
road sensors
26 days
Tue
10-
09-19
Tue
15-10-
19
17
Database
administrator
$ 8,320.00
4.2
Putting
overhead cameras
25 days
Tue
10-
09-19
Mon
14-10-
19
17
Technical
engineer
$ 7,000.00
4.3
Connecting toll
checker
22 days
Tue
15-
10-19
Wed
13-11-
19
21
Contractor,
Hardware[1]
$ 43,040.00
4.4
Vehicle to
Roadside
Communication
20 days
Tue
15-
10-19
Mon
11-11-
19
21
Software[1],Sub-
contractor,
Technical
engineer
$ 45,688.00
4.5
Development of
e-toll system
22 days
Tue
12-
11-19
Wed
11-12-
19
23
Additional
cost[1],Database
administrator
$ 32,040.00
4.6 Testing of the
system
9 days Thu
12-
Tue
24-12-
24 Tester $ 2,880.00
8
PROJECT MANAGEMENT
12-19 19
4.7
Milestone 4:
Completion of
implementation
phase
0 days
Tue
24-
12-19
Tue
24-12-
19
25 $ 0.00
5 Closure phase 27 days
Wed
25-
12-19
Thu
30-01-
20
$ 11,560.00
5.1
Post project
review
10 days
Wed
25-
12-19
Tue
07-01-
20
25 Project manager $ 4,000.00
5.2
Stakeholder
sign off
8 days
Wed
08-
01-20
Fri
17-01-
20
28 Project planner $ 2,880.00
5.3 Documentation 9 days
Mon
20-
01-20
Thu
30-01-
20
29
Sub-contractor,
Worker
$ 4,680.00
5.4
Milestone 5:
Completion of
execution phase
0 days
Thu
30-
01-20
Thu
30-01-
20
30 $ 0.00
PROJECT MANAGEMENT
12-19 19
4.7
Milestone 4:
Completion of
implementation
phase
0 days
Tue
24-
12-19
Tue
24-12-
19
25 $ 0.00
5 Closure phase 27 days
Wed
25-
12-19
Thu
30-01-
20
$ 11,560.00
5.1
Post project
review
10 days
Wed
25-
12-19
Tue
07-01-
20
25 Project manager $ 4,000.00
5.2
Stakeholder
sign off
8 days
Wed
08-
01-20
Fri
17-01-
20
28 Project planner $ 2,880.00
5.3 Documentation 9 days
Mon
20-
01-20
Thu
30-01-
20
29
Sub-contractor,
Worker
$ 4,680.00
5.4
Milestone 5:
Completion of
execution phase
0 days
Thu
30-
01-20
Thu
30-01-
20
30 $ 0.00
9
PROJECT MANAGEMENT
4. Project procurement management for the outsource work
4.1 Outsourcing needs of the project
The project is mainly outsourced due to its expense. It is identified that it is quite
necessary to outsource the requirements of project management and this is mainly due to the
taxes as well as benefits on the employees of the outsource organization [5]. The second reason
of outsourcing is efficiency. It is found that the employees who generally deal with the project
must be trained in some important perspectives of project management methodology in order to
complete the work of the project successfully. In addition to this, other reason due to which
outsourcing of the project can be done is the complexity of the project.
4.2 Detailed project schedule
The detailed schedule that is mainly developed for the implementation of electronic toll
system is generally provided in the table below. It is found that the table that is given below
reflects that the entire project will be completed within 210 days that is within 7 months. The
execution time for each of the project activities are generally reflected in the table below.
Furthermore, the paper also showcases initiation as well as closure date for each of the project
phase.
WBS Task Name Duration Start Finish Predecessors
0
Implementation of e-toll
system in Hyderabad Ring
road
210 days
Fri 12-04-
19
Thu 30-01-
20
1 Initiation phase 45 days
Fri 12-04-
19
Thu 13-06-
19
PROJECT MANAGEMENT
4. Project procurement management for the outsource work
4.1 Outsourcing needs of the project
The project is mainly outsourced due to its expense. It is identified that it is quite
necessary to outsource the requirements of project management and this is mainly due to the
taxes as well as benefits on the employees of the outsource organization [5]. The second reason
of outsourcing is efficiency. It is found that the employees who generally deal with the project
must be trained in some important perspectives of project management methodology in order to
complete the work of the project successfully. In addition to this, other reason due to which
outsourcing of the project can be done is the complexity of the project.
4.2 Detailed project schedule
The detailed schedule that is mainly developed for the implementation of electronic toll
system is generally provided in the table below. It is found that the table that is given below
reflects that the entire project will be completed within 210 days that is within 7 months. The
execution time for each of the project activities are generally reflected in the table below.
Furthermore, the paper also showcases initiation as well as closure date for each of the project
phase.
WBS Task Name Duration Start Finish Predecessors
0
Implementation of e-toll
system in Hyderabad Ring
road
210 days
Fri 12-04-
19
Thu 30-01-
20
1 Initiation phase 45 days
Fri 12-04-
19
Thu 13-06-
19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10
PROJECT MANAGEMENT
1.1
Developing business
case
10 days Fri 12-04-19
Thu 25-04-
19
1.2
Undertaking feasibility
study
12 days Fri 26-04-19
Mon 13-05-
19
2
1.3 Establishing charter 8 days
Tue 14-05-
19
Thu 23-05-
19
3
1.4
Appointing team
members
15 days Fri 24-05-19
Thu 13-06-
19
4
1.5
Milestone 1: Completion
of initiation phase
0 days
Thu 13-06-
19
Thu 13-06-
19
5
2 Planning phase 37 days
Fri 14-06-
19
Mon 05-08-
19
2.1
Development of project
plan
13 days Fri 14-06-19
Tue 02-07-
19
5
2.2
Development of
resource plan
14 days Fri 14-06-19
Wed 03-07-
19
5
2.3
Developing financial
plan
15 days Fri 14-06-19
Thu 04-07-
19
6
2.4 Developing quality plan 12 days Fri 05-07-19
Mon 22-07-
19
10
2.5
Developing acceptance
plan
10 days
Tue 23-07-
19
Mon 05-08-
19
11
2.6 Milestone 2:Completion 0 days Mon 05-08- Mon 05-08- 12
PROJECT MANAGEMENT
1.1
Developing business
case
10 days Fri 12-04-19
Thu 25-04-
19
1.2
Undertaking feasibility
study
12 days Fri 26-04-19
Mon 13-05-
19
2
1.3 Establishing charter 8 days
Tue 14-05-
19
Thu 23-05-
19
3
1.4
Appointing team
members
15 days Fri 24-05-19
Thu 13-06-
19
4
1.5
Milestone 1: Completion
of initiation phase
0 days
Thu 13-06-
19
Thu 13-06-
19
5
2 Planning phase 37 days
Fri 14-06-
19
Mon 05-08-
19
2.1
Development of project
plan
13 days Fri 14-06-19
Tue 02-07-
19
5
2.2
Development of
resource plan
14 days Fri 14-06-19
Wed 03-07-
19
5
2.3
Developing financial
plan
15 days Fri 14-06-19
Thu 04-07-
19
6
2.4 Developing quality plan 12 days Fri 05-07-19
Mon 22-07-
19
10
2.5
Developing acceptance
plan
10 days
Tue 23-07-
19
Mon 05-08-
19
11
2.6 Milestone 2:Completion 0 days Mon 05-08- Mon 05-08- 12
11
PROJECT MANAGEMENT
of planning phase 19 19
3 Designing phase 25 days
Tue 06-08-
19
Mon 09-09-
19
3.1
Developing design for
the E-toll system
20 days
Tue 06-08-
19
Mon 02-09-
19
12
3.2
Sending the design for
approval
2 days
Tue 03-09-
19
Wed 04-09-
19
15
3.3
Getting approval on the
project design
3 days
Thu 05-09-
19
Mon 09-09-
19
16
3.4
Milestone 3:Completion
of designing phase of the
project
0 days
Mon 09-09-
19
Mon 09-09-
19
17
4 Implementation phase 76 days
Tue 10-09-
19
Tue 24-12-
19
4.1
Connecting in-road
sensors
26 days
Tue 10-09-
19
Tue 15-10-
19
17
4.2
Putting overhead
cameras
25 days
Tue 10-09-
19
Mon 14-10-
19
17
4.3 Connecting toll checker 22 days
Tue 15-10-
19
Wed 13-11-
19
21
4.4
Vehicle to Roadside
Communication
20 days
Tue 15-10-
19
Mon 11-11-
19
21
PROJECT MANAGEMENT
of planning phase 19 19
3 Designing phase 25 days
Tue 06-08-
19
Mon 09-09-
19
3.1
Developing design for
the E-toll system
20 days
Tue 06-08-
19
Mon 02-09-
19
12
3.2
Sending the design for
approval
2 days
Tue 03-09-
19
Wed 04-09-
19
15
3.3
Getting approval on the
project design
3 days
Thu 05-09-
19
Mon 09-09-
19
16
3.4
Milestone 3:Completion
of designing phase of the
project
0 days
Mon 09-09-
19
Mon 09-09-
19
17
4 Implementation phase 76 days
Tue 10-09-
19
Tue 24-12-
19
4.1
Connecting in-road
sensors
26 days
Tue 10-09-
19
Tue 15-10-
19
17
4.2
Putting overhead
cameras
25 days
Tue 10-09-
19
Mon 14-10-
19
17
4.3 Connecting toll checker 22 days
Tue 15-10-
19
Wed 13-11-
19
21
4.4
Vehicle to Roadside
Communication
20 days
Tue 15-10-
19
Mon 11-11-
19
21
12
PROJECT MANAGEMENT
4.5
Development of e-toll
system
22 days
Tue 12-11-
19
Wed 11-12-
19
23
4.6 Testing of the system 9 days
Thu 12-12-
19
Tue 24-12-
19
24
4.7
Milestone 4: Completion
of implementation phase
0 days
Tue 24-12-
19
Tue 24-12-
19
25
5 Closure phase 27 days
Wed 25-12-
19
Thu 30-01-
20
5.1 Post project review 10 days
Wed 25-12-
19
Tue 07-01-
20
25
5.2 Stakeholder sign off 8 days
Wed 08-01-
20
Fri 17-01-20 28
5.3 Documentation 9 days
Mon 20-01-
20
Thu 30-01-
20
29
5.4
Milestone 5: Completion
of execution phase
0 days
Thu 30-01-
20
Thu 30-01-
20
30
4.3 Cost allocation plan
Cost allocation is considered as one of the procedure that helps in determining,
aggregating as well as assigning costs to each of the activities of the project. The cost allocation
plan that is generally developed for the electronic toll system in Hyderabad ring road is generally
reflected below. The figure which is mainly provided below reflects on the project cost
allocation as per the different phases of the project. From the above figure, it is helpful in
PROJECT MANAGEMENT
4.5
Development of e-toll
system
22 days
Tue 12-11-
19
Wed 11-12-
19
23
4.6 Testing of the system 9 days
Thu 12-12-
19
Tue 24-12-
19
24
4.7
Milestone 4: Completion
of implementation phase
0 days
Tue 24-12-
19
Tue 24-12-
19
25
5 Closure phase 27 days
Wed 25-12-
19
Thu 30-01-
20
5.1 Post project review 10 days
Wed 25-12-
19
Tue 07-01-
20
25
5.2 Stakeholder sign off 8 days
Wed 08-01-
20
Fri 17-01-20 28
5.3 Documentation 9 days
Mon 20-01-
20
Thu 30-01-
20
29
5.4
Milestone 5: Completion
of execution phase
0 days
Thu 30-01-
20
Thu 30-01-
20
30
4.3 Cost allocation plan
Cost allocation is considered as one of the procedure that helps in determining,
aggregating as well as assigning costs to each of the activities of the project. The cost allocation
plan that is generally developed for the electronic toll system in Hyderabad ring road is generally
reflected below. The figure which is mainly provided below reflects on the project cost
allocation as per the different phases of the project. From the above figure, it is helpful in
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13
PROJECT MANAGEMENT
reflecting that $18,720 is generally allocated in the initiation phase of the project whereas
completing the project execution, proper budget around $138,968 is allocated.
$ 0.00
$ 20,000.00
$ 40,000.00
$ 60,000.00
$ 80,000.00
$ 100,000.00
$ 120,000.00
$ 140,000.00
$ 160,000.00
Actual Cost Remaining Cost Baseline Cost
Figure 5: Cost allocation overview
(Source: Created by Author)
4.4 Time allocation plan
Time allocation rules helps in allowing in setting proper time for the project so that each
sages of the project can be able to get completed within the expected time and budget of the
project. Proper time allocation is generally needed for successful execution of the project that
further helps in providing idea that the entire project can get completed within the expected time
and budget that is assumed by the project manager. The figure that is provided below generally
reflects on the time that is allocated for the project. From the below table it is properly analyzed
that the work of the work will be completed in 210 days that is 7 months. The table showcases
PROJECT MANAGEMENT
reflecting that $18,720 is generally allocated in the initiation phase of the project whereas
completing the project execution, proper budget around $138,968 is allocated.
$ 0.00
$ 20,000.00
$ 40,000.00
$ 60,000.00
$ 80,000.00
$ 100,000.00
$ 120,000.00
$ 140,000.00
$ 160,000.00
Actual Cost Remaining Cost Baseline Cost
Figure 5: Cost allocation overview
(Source: Created by Author)
4.4 Time allocation plan
Time allocation rules helps in allowing in setting proper time for the project so that each
sages of the project can be able to get completed within the expected time and budget of the
project. Proper time allocation is generally needed for successful execution of the project that
further helps in providing idea that the entire project can get completed within the expected time
and budget that is assumed by the project manager. The figure that is provided below generally
reflects on the time that is allocated for the project. From the below table it is properly analyzed
that the work of the work will be completed in 210 days that is 7 months. The table showcases
14
PROJECT MANAGEMENT
time allocation for each of the project activities that are generally required for successfully
executing the activities of the project suecessfully.
WBS Task Name Duration
0
Implementation of e-toll system in Hyderabad
Ring road
210 days
1 Initiation phase 45 days
1.1 Developing business case 10 days
1.2 Undertaking feasibility study 12 days
1.3 Establishing charter 8 days
1.4 Appointing team members 15 days
1.5 Milestone 1: Completion of initiation phase 0 days
2 Planning phase 37 days
2.1 Development of project plan 13 days
2.2 Development of resource plan 14 days
2.3 Developing financial plan 15 days
2.4 Developing quality plan 12 days
2.5 Developing acceptance plan 10 days
2.6 Milestone 2:Completion of planning phase 0 days
3 Designing phase 25 days
3.1 Developing design for the E-toll system 20 days
3.2 Sending the design for approval 2 days
3.3 Getting approval on the project design 3 days
PROJECT MANAGEMENT
time allocation for each of the project activities that are generally required for successfully
executing the activities of the project suecessfully.
WBS Task Name Duration
0
Implementation of e-toll system in Hyderabad
Ring road
210 days
1 Initiation phase 45 days
1.1 Developing business case 10 days
1.2 Undertaking feasibility study 12 days
1.3 Establishing charter 8 days
1.4 Appointing team members 15 days
1.5 Milestone 1: Completion of initiation phase 0 days
2 Planning phase 37 days
2.1 Development of project plan 13 days
2.2 Development of resource plan 14 days
2.3 Developing financial plan 15 days
2.4 Developing quality plan 12 days
2.5 Developing acceptance plan 10 days
2.6 Milestone 2:Completion of planning phase 0 days
3 Designing phase 25 days
3.1 Developing design for the E-toll system 20 days
3.2 Sending the design for approval 2 days
3.3 Getting approval on the project design 3 days
15
PROJECT MANAGEMENT
3.4
Milestone 3:Completion of designing phase of the
project
0 days
4 Implementation phase 76 days
4.1 Connecting in-road sensors 26 days
4.2 Putting overhead cameras 25 days
4.3 Connecting toll checker 22 days
4.4 Vehicle to Roadside Communication 20 days
4.5 Development of e-toll system 22 days
4.6 Testing of the system 9 days
4.7 Milestone 4: Completion of implementation phase 0 days
5 Closure phase 27 days
5.1 Post project review 10 days
5.2 Stakeholder sign off 8 days
5.3 Documentation 9 days
5.4 Milestone 5: Completion of execution phase 0 days
In addition to this, it is found that figure that is provided below generally reflects on
%completion, cumulative cost as well as cumulative percent complete. All this information that
are mainly showcases in the report reflects that the work of the project will successfully get
completed as per the initial planning that is made by the project manager.
PROJECT MANAGEMENT
3.4
Milestone 3:Completion of designing phase of the
project
0 days
4 Implementation phase 76 days
4.1 Connecting in-road sensors 26 days
4.2 Putting overhead cameras 25 days
4.3 Connecting toll checker 22 days
4.4 Vehicle to Roadside Communication 20 days
4.5 Development of e-toll system 22 days
4.6 Testing of the system 9 days
4.7 Milestone 4: Completion of implementation phase 0 days
5 Closure phase 27 days
5.1 Post project review 10 days
5.2 Stakeholder sign off 8 days
5.3 Documentation 9 days
5.4 Milestone 5: Completion of execution phase 0 days
In addition to this, it is found that figure that is provided below generally reflects on
%completion, cumulative cost as well as cumulative percent complete. All this information that
are mainly showcases in the report reflects that the work of the project will successfully get
completed as per the initial planning that is made by the project manager.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16
PROJECT MANAGEMENT
08-04-19
06-05-19
03-06-19
01-07-19
29-07-19
26-08-19
23-09-19
21-10-19
18-11-19
16-12-19
13-01-20
$ 0.00
$ 50,000.00
$ 100,000.00
$ 150,000.00
$ 200,000.00
$ 250,000.00
Cumulative Cost
Cumulative Percent Complete
% Complete
Figure 6: Time allocation overview
(Source: Created by Author)
4.5 Gantt chart and other planning details
The Gantt chart that is created for the implementation of electronic toll system generally
reflects on the time that is needed for the execution of the project. In addition to this, the Gantt
chart that is given below generally includes proper information as well as details about the
duration that is required for executing each of the project activities as well as the starting and
completion date of each project activities. Furthermore, the dependencies that are reflected below
assists in planning a key role in managing the work of the project quite effectively.
PROJECT MANAGEMENT
08-04-19
06-05-19
03-06-19
01-07-19
29-07-19
26-08-19
23-09-19
21-10-19
18-11-19
16-12-19
13-01-20
$ 0.00
$ 50,000.00
$ 100,000.00
$ 150,000.00
$ 200,000.00
$ 250,000.00
Cumulative Cost
Cumulative Percent Complete
% Complete
Figure 6: Time allocation overview
(Source: Created by Author)
4.5 Gantt chart and other planning details
The Gantt chart that is created for the implementation of electronic toll system generally
reflects on the time that is needed for the execution of the project. In addition to this, the Gantt
chart that is given below generally includes proper information as well as details about the
duration that is required for executing each of the project activities as well as the starting and
completion date of each project activities. Furthermore, the dependencies that are reflected below
assists in planning a key role in managing the work of the project quite effectively.
17
PROJECT MANAGEMENT
Figure 7: Gantt chart
(Source: Created by Author)
PROJECT MANAGEMENT
Figure 7: Gantt chart
(Source: Created by Author)
18
PROJECT MANAGEMENT
4.6 Milestones and deliverables
Deliverables are generally referred as one of the important project management term that
assists in properly describing the quantifiable services as well as goods that are generally needed
for successful completion of the project [7]. The deliverables of the project that are required for
the proper implementation of electronic toll system are generally provided below:
Progress report
Site investigation report
Feasibility report
Tender document
Design report
Project milestone are mainly considered as the task of zero duration that generally showcases
the achievement of the project. It is found that the milestone for the implementation of E-toll
system within in the Hyderabad ring road is generally reflected in the table below:
Milestone Completion date
Milestone 1: Completion of initiation phase Thu 13-06-19
Milestone 2:Completion of planning phase Mon 05-08-19
Milestone 3:Completion of designing phase of the project Mon 09-09-19
Milestone 4: Completion of implementation phase Tue 24-12-19
Milestone 5: Completion of execution phase Thu 30-01-20
PROJECT MANAGEMENT
4.6 Milestones and deliverables
Deliverables are generally referred as one of the important project management term that
assists in properly describing the quantifiable services as well as goods that are generally needed
for successful completion of the project [7]. The deliverables of the project that are required for
the proper implementation of electronic toll system are generally provided below:
Progress report
Site investigation report
Feasibility report
Tender document
Design report
Project milestone are mainly considered as the task of zero duration that generally showcases
the achievement of the project. It is found that the milestone for the implementation of E-toll
system within in the Hyderabad ring road is generally reflected in the table below:
Milestone Completion date
Milestone 1: Completion of initiation phase Thu 13-06-19
Milestone 2:Completion of planning phase Mon 05-08-19
Milestone 3:Completion of designing phase of the project Mon 09-09-19
Milestone 4: Completion of implementation phase Tue 24-12-19
Milestone 5: Completion of execution phase Thu 30-01-20
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19
PROJECT MANAGEMENT
Bibliography
[1].H.A Hornstein.,The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
pp.291-298 2015.
[2].A. Badewi., The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778, 2016.
[3].P. Svejvig., and p. Andersen., Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290, 2015.
[4].Papke-Shields, E. Karen., and M. Kathleen Boyer-Wright. "Strategic planning
characteristics applied to project management." International Journal of Project
Management35, no. 2 (2017): 169-179 2015.
[5].M.G. Kaiser., F. El Arbi, and F. Ahlemann., Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), pp.126-139, 2015.
[6].M.M. De Carvalho., L.A Patah,. and D. de Souza Bido, Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), pp.1509-1522, 2015.
[7].J. Ramazani, and G. Jergeas., Project managers and the journey from good to great: The
benefits of investment in project management training and education. International
Journal of Project Management, 33(1), pp.41-52, 2015.
PROJECT MANAGEMENT
Bibliography
[1].H.A Hornstein.,The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
pp.291-298 2015.
[2].A. Badewi., The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778, 2016.
[3].P. Svejvig., and p. Andersen., Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290, 2015.
[4].Papke-Shields, E. Karen., and M. Kathleen Boyer-Wright. "Strategic planning
characteristics applied to project management." International Journal of Project
Management35, no. 2 (2017): 169-179 2015.
[5].M.G. Kaiser., F. El Arbi, and F. Ahlemann., Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), pp.126-139, 2015.
[6].M.M. De Carvalho., L.A Patah,. and D. de Souza Bido, Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), pp.1509-1522, 2015.
[7].J. Ramazani, and G. Jergeas., Project managers and the journey from good to great: The
benefits of investment in project management training and education. International
Journal of Project Management, 33(1), pp.41-52, 2015.
20
PROJECT MANAGEMENT
[8].A. Bucero, and R.L. Englund., October. Project sponsorship: Achieving management
commitment for project success. Project Management Institute, 2015
[9].H.L Bi., X. Jia., F.Q. Lu, and M. Huang., Schedule risk management of it outsourcing
project using negotiation mechanism. In Proceedings of the 23rd International
Conference on Industrial Engineering and Engineering Management 2016 (pp. 29-33).
Atlantis Press, Paris, 2017.
[10]. K. Samset, and G.H Volden., Front-end definition of projects: Ten paradoxes and
some reflections regarding project management and project governance. International
Journal of Project Management, 34(2), pp.297-313, 2016.
PROJECT MANAGEMENT
[8].A. Bucero, and R.L. Englund., October. Project sponsorship: Achieving management
commitment for project success. Project Management Institute, 2015
[9].H.L Bi., X. Jia., F.Q. Lu, and M. Huang., Schedule risk management of it outsourcing
project using negotiation mechanism. In Proceedings of the 23rd International
Conference on Industrial Engineering and Engineering Management 2016 (pp. 29-33).
Atlantis Press, Paris, 2017.
[10]. K. Samset, and G.H Volden., Front-end definition of projects: Ten paradoxes and
some reflections regarding project management and project governance. International
Journal of Project Management, 34(2), pp.297-313, 2016.
1 out of 21
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.