Project Management

   

Added on  2023-04-17

8 Pages770 Words343 Views
Running head: PROJECT MANAGEMENT
Project Management
Name of Student-
Name of University-
Author’s Note-

1PROJECT MANAGEMENT
A. START 0 -
B. Clear & Grub 12 A. START
C. Order & Delivery
Reinforcement
4 A. START
D. Order & Delivery PC
Slabs
5 A. START
E. Excavate Footings and
Utilities
7 B. Clean & Grub
F. Delivery Frames, Channel
etc.
9 B. Clean & Grub
G. RC Footings 9 C. Order & Delivery
Reinforcement
H. Form Footings 12 E. Excavate Footings and
Utilities (SS+2)
I. Masonry & Bearing Walls 9 D. Order & Delivery PC
Slabs
G. RC Footings (FF +3)
J. Erect Joists and Deck 7 I. Masonry & Bearing Walls
K. Foundation Block 12 F. Delivery Frames, Channel

2PROJECT MANAGEMENT
etc.
G. RC Footings (FS+4)
L. Backfill 9 H. Form Footings
K. Foundation Block
M. FINISH 0 J. Erect Joists and Deck
L. Backfill
1. AON Diagram
2.
Activities Early Start Early Finish Late Start Late Finish
A 0 0 0 0

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
BNV6047 Project Management Assignment
|6
|1309
|304

BNV6047 Project Management
|19
|3818
|40

Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start:
|115
|2991
|4

ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
|2
|670
|5

Project Management: Benefits Administration Software
|4
|811
|299

Using and managing data and information
|9
|465
|36