The main focus of the paper is to analyze the initial needs of the project by getting proper idea about the construction of the project. The fitness centre that will be constructed by the organization “Green apple gym” will provide proper facility of Gym to the workers and school student. The paper utilizes PRINCE2 methodology for developing the plan of the project which further reflects that the construction work will be completed in 154 days by using $400,000. In addition to this, the paper also analyzes the project and quality related issues.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Fitness centre Construction
Name of the Student
Name of the university
Author’s Note
Fitness centre Construction
Name of the Student
Name of the university
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
PROJECT MANAGEMENT
Executive Summary
The main focus of the paper is to analyze the initial needs of the project by getting proper
idea about the construction of the project. The fitness centre that will be constructed by the
organization “Green apple gym” will provide proper facility of Gym to the workers and
school student. The paper utilizes PRINCE2 methodology for developing the plan of the
project which further reflects that the construction work will be completed in 154 days by
using $400,000. In addition to this, the paper also analyzes the project and quality related
issues.
PROJECT MANAGEMENT
Executive Summary
The main focus of the paper is to analyze the initial needs of the project by getting proper
idea about the construction of the project. The fitness centre that will be constructed by the
organization “Green apple gym” will provide proper facility of Gym to the workers and
school student. The paper utilizes PRINCE2 methodology for developing the plan of the
project which further reflects that the construction work will be completed in 154 days by
using $400,000. In addition to this, the paper also analyzes the project and quality related
issues.
2
PROJECT MANAGEMENT
Table of Contents
1. Introduction............................................................................................................................3
2. Methodology..........................................................................................................................3
3. Analysis of the key findings using business example............................................................4
3.1 Project plan.......................................................................................................................4
3.2 Project budget...................................................................................................................6
3.3 Initial HR budget estimation............................................................................................7
3.4 Project risk and quality analysis.......................................................................................7
4. Conclusion..............................................................................................................................8
PROJECT MANAGEMENT
Table of Contents
1. Introduction............................................................................................................................3
2. Methodology..........................................................................................................................3
3. Analysis of the key findings using business example............................................................4
3.1 Project plan.......................................................................................................................4
3.2 Project budget...................................................................................................................6
3.3 Initial HR budget estimation............................................................................................7
3.4 Project risk and quality analysis.......................................................................................7
4. Conclusion..............................................................................................................................8
3
PROJECT MANAGEMENT
1. Introduction
The main focus of the paper is to construct a fitness and lifestyle centre for Green
apple gym for improving the health of the people of local communities. The company has
acquired a land that is located near the railway station in Sydney and it is also few minutes
away from the high school. It is identified that the construction of the Gym will be helpful in
giving a number of options for doing exercise on daily basis for the workers and the students.
The main important features that are provided by the Gym include indoor fitness group as
well as personal training services including cardio room. The floor size for the room will be
around 1240 sq. In addition to this, the fitness centre will generally provide the facility of
locker room for keeping personal belongings. In order to construct the fitness centre, the
“Green Apply Gym” generally wants to do the design works. It is found that for undertaking
the construction work, it is quite important to use PRINCE2 project methodology which is
considered as one of the procedure based method that is mainly used in order to manage the
work of the project quite effectively. In addition to this, the work of construction will get
completed within $400,000.
2. Methodology
The project utilizes PRINCE2 project methodology. It is found that the PRINCE2
methodology generally helps in diving the project into a number of stages and thus it makes
the schedule easier for proper management. Each stage of the project lifecycle are reviewed
effectively for making sure that the undertaken project is very much feasible and it generally
helps in delivering proper value to the entire organization (Mousaei and Javdani 2018).
Furthermore, the use of this specific methodology generally helps in analyzing all the
requirement of the project including client review, site inspection, flooring, paining, installing
equipment, creating blueprint and the activities that undertake the construction work.
PROJECT MANAGEMENT
1. Introduction
The main focus of the paper is to construct a fitness and lifestyle centre for Green
apple gym for improving the health of the people of local communities. The company has
acquired a land that is located near the railway station in Sydney and it is also few minutes
away from the high school. It is identified that the construction of the Gym will be helpful in
giving a number of options for doing exercise on daily basis for the workers and the students.
The main important features that are provided by the Gym include indoor fitness group as
well as personal training services including cardio room. The floor size for the room will be
around 1240 sq. In addition to this, the fitness centre will generally provide the facility of
locker room for keeping personal belongings. In order to construct the fitness centre, the
“Green Apply Gym” generally wants to do the design works. It is found that for undertaking
the construction work, it is quite important to use PRINCE2 project methodology which is
considered as one of the procedure based method that is mainly used in order to manage the
work of the project quite effectively. In addition to this, the work of construction will get
completed within $400,000.
2. Methodology
The project utilizes PRINCE2 project methodology. It is found that the PRINCE2
methodology generally helps in diving the project into a number of stages and thus it makes
the schedule easier for proper management. Each stage of the project lifecycle are reviewed
effectively for making sure that the undertaken project is very much feasible and it generally
helps in delivering proper value to the entire organization (Mousaei and Javdani 2018).
Furthermore, the use of this specific methodology generally helps in analyzing all the
requirement of the project including client review, site inspection, flooring, paining, installing
equipment, creating blueprint and the activities that undertake the construction work.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4
PROJECT MANAGEMENT
Moreover, the use of this specific methodology generally assists in improving communication
between the project team as with the external stakeholders and it further helps in providing
the stakeholder a chance when it generally comes to the procedure of decision making.
Furthermore, it is considered as one of the consistent approach that focuses on business
justification and helps in controlling the entire project schedule quite effectively.
3. Analysis of the key findings using business example
3.1 Project plan
The table which is given below reflects on the plan that is created for successful
execution of the project. It is showcased that the fitness centre will be constructed in 154 days
and moreover the below plan reflects on the initiation date, completion date as well as on the
duration that is needed for executing each activities.
WBS Task Name Duration Start Finish
0 Fitness centre construction 154 days Tue 30-04-19 Fri 29-11-19
1 Kick off phase 15 days Tue 30-04-19 Mon 20-05-19
1.1 Requirement analysis 5 days Tue 30-04-19 Mon 06-05-19
1.2 Feasibility analysis 3 days Tue 07-05-19 Thu 09-05-19
1.3 Project charter 4 days Fri 10-05-19 Wed 15-05-19
1.4
Team members
appointment
3 days Thu 16-05-19 Mon 20-05-19
2 Project planning phase 24 days Tue 21-05-19 Fri 21-06-19
2.1 Project plan 7 days Tue 21-05-19 Wed 29-05-19
2.2 Resource plan 4 days Thu 30-05-19 Tue 04-06-19
2.3 Financial plan 3 days Wed 05-06-19 Fri 07-06-19
PROJECT MANAGEMENT
Moreover, the use of this specific methodology generally assists in improving communication
between the project team as with the external stakeholders and it further helps in providing
the stakeholder a chance when it generally comes to the procedure of decision making.
Furthermore, it is considered as one of the consistent approach that focuses on business
justification and helps in controlling the entire project schedule quite effectively.
3. Analysis of the key findings using business example
3.1 Project plan
The table which is given below reflects on the plan that is created for successful
execution of the project. It is showcased that the fitness centre will be constructed in 154 days
and moreover the below plan reflects on the initiation date, completion date as well as on the
duration that is needed for executing each activities.
WBS Task Name Duration Start Finish
0 Fitness centre construction 154 days Tue 30-04-19 Fri 29-11-19
1 Kick off phase 15 days Tue 30-04-19 Mon 20-05-19
1.1 Requirement analysis 5 days Tue 30-04-19 Mon 06-05-19
1.2 Feasibility analysis 3 days Tue 07-05-19 Thu 09-05-19
1.3 Project charter 4 days Fri 10-05-19 Wed 15-05-19
1.4
Team members
appointment
3 days Thu 16-05-19 Mon 20-05-19
2 Project planning phase 24 days Tue 21-05-19 Fri 21-06-19
2.1 Project plan 7 days Tue 21-05-19 Wed 29-05-19
2.2 Resource plan 4 days Thu 30-05-19 Tue 04-06-19
2.3 Financial plan 3 days Wed 05-06-19 Fri 07-06-19
5
PROJECT MANAGEMENT
2.4 Quality plan 3 days Mon 10-06-19 Wed 12-06-19
2.5 Risk management plan 4 days Thu 13-06-19 Tue 18-06-19
2.6 Communication plan 3 days Wed 19-06-19 Fri 21-06-19
3 Project designing phase 24 days Mon 24-06-19 Thu 25-07-19
3.1 Creating blueprint 9 days Mon 24-06-19 Thu 04-07-19
3.2 Finishing design 7 days Fri 05-07-19 Mon 15-07-19
3.3
Cross-checking the
developed blueprint or design
6 days Tue 16-07-19 Tue 23-07-19
3.4 Design approval 2 days Wed 24-07-19 Thu 25-07-19
4 Project execution phase 81 days Fri 26-07-19 Fri 15-11-19
4.1
Flooring, floor caulking as
well as tile flooring
16 days Fri 26-07-19 Fri 16-08-19
4.2
Free standing dwelling
and construction of cardio
area
14 days Mon 19-08-19 Thu 05-09-19
4.3
Fitness group classes
development
13 days Fri 06-09-19 Tue 24-09-19
4.4
Construction of offices,
locker room as well as
reception area
12 days Wed 25-09-19 Thu 10-10-19
4.5
Construction of 2.7
ceilings
14 days Fri 11-10-19 Wed 30-10-19
4.6 Removing old cabinets 12 days Thu 31-10-19 Fri 15-11-19
5 Closure phase 10 days Mon 18-11-19 Fri 29-11-19
PROJECT MANAGEMENT
2.4 Quality plan 3 days Mon 10-06-19 Wed 12-06-19
2.5 Risk management plan 4 days Thu 13-06-19 Tue 18-06-19
2.6 Communication plan 3 days Wed 19-06-19 Fri 21-06-19
3 Project designing phase 24 days Mon 24-06-19 Thu 25-07-19
3.1 Creating blueprint 9 days Mon 24-06-19 Thu 04-07-19
3.2 Finishing design 7 days Fri 05-07-19 Mon 15-07-19
3.3
Cross-checking the
developed blueprint or design
6 days Tue 16-07-19 Tue 23-07-19
3.4 Design approval 2 days Wed 24-07-19 Thu 25-07-19
4 Project execution phase 81 days Fri 26-07-19 Fri 15-11-19
4.1
Flooring, floor caulking as
well as tile flooring
16 days Fri 26-07-19 Fri 16-08-19
4.2
Free standing dwelling
and construction of cardio
area
14 days Mon 19-08-19 Thu 05-09-19
4.3
Fitness group classes
development
13 days Fri 06-09-19 Tue 24-09-19
4.4
Construction of offices,
locker room as well as
reception area
12 days Wed 25-09-19 Thu 10-10-19
4.5
Construction of 2.7
ceilings
14 days Fri 11-10-19 Wed 30-10-19
4.6 Removing old cabinets 12 days Thu 31-10-19 Fri 15-11-19
5 Closure phase 10 days Mon 18-11-19 Fri 29-11-19
6
PROJECT MANAGEMENT
5.1 Project review 4 days Mon 18-11-19 Thu 21-11-19
5.2
Project stakeholders sign
off
3 days Fri 22-11-19 Tue 26-11-19
5.3 Documentation 3 days Wed 27-11-19 Fri 29-11-19
3.2 Project budget
The figure below reflects that around $400,000 is required for the construction of the
fitness centre.
Figure 1: Project budget
(Source: Created by Author)
PROJECT MANAGEMENT
5.1 Project review 4 days Mon 18-11-19 Thu 21-11-19
5.2
Project stakeholders sign
off
3 days Fri 22-11-19 Tue 26-11-19
5.3 Documentation 3 days Wed 27-11-19 Fri 29-11-19
3.2 Project budget
The figure below reflects that around $400,000 is required for the construction of the
fitness centre.
Figure 1: Project budget
(Source: Created by Author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7
PROJECT MANAGEMENT
3.3 Initial HR budget estimation
The HR budget estimation plan for the fitness Centre construction is generally
provided below:
Types of
Workers
Require
d
number
of
Worker
s
Hourly
Wage
Workin
g hours
Hiring
Date
Years of
Experien
ce
Total
Cost
Commen
ts
Labourer 10
$
10.00 704
10/04/201
9 3
$
70,400.00
Reasonab
le
Carpente
r 2
$
12.00 560
21/07/201
9 5
$
13,440.00
Reasonab
le
Contract
or 1
$
55.00 776 5/07/2019 6
$
42,680.00
Reasonab
le
Plumber 2
$
12.00 176
25/07/201
9 3
$
4,224.00
Reasonab
le
Welder 2
$
15.00 48
15/07/201
9 2
$
1,440.00
Reasonab
le
Electricia
n 2
$
18.00 152
30/08/201
9 3
$
5,472.00
Reasonab
le
Project
Manager 1
$
60.00 216
25/04/201
9 5
$
12,960.00
Reasonab
le
Planner 1
$
55.00 192 7/05/2019 2
$
10,560.00
Reasonab
le
Consulta
nt 1
$
50.00 656 5/07/2019 2
$
32,800.00
Reasonab
le
Total Cost
$
193,976.0
0
Average Cost
$
110,973.3
3
Maximum Cost
$
208,800.0
0
Minimum Cost
$
152,474.6
7
PROJECT MANAGEMENT
3.3 Initial HR budget estimation
The HR budget estimation plan for the fitness Centre construction is generally
provided below:
Types of
Workers
Require
d
number
of
Worker
s
Hourly
Wage
Workin
g hours
Hiring
Date
Years of
Experien
ce
Total
Cost
Commen
ts
Labourer 10
$
10.00 704
10/04/201
9 3
$
70,400.00
Reasonab
le
Carpente
r 2
$
12.00 560
21/07/201
9 5
$
13,440.00
Reasonab
le
Contract
or 1
$
55.00 776 5/07/2019 6
$
42,680.00
Reasonab
le
Plumber 2
$
12.00 176
25/07/201
9 3
$
4,224.00
Reasonab
le
Welder 2
$
15.00 48
15/07/201
9 2
$
1,440.00
Reasonab
le
Electricia
n 2
$
18.00 152
30/08/201
9 3
$
5,472.00
Reasonab
le
Project
Manager 1
$
60.00 216
25/04/201
9 5
$
12,960.00
Reasonab
le
Planner 1
$
55.00 192 7/05/2019 2
$
10,560.00
Reasonab
le
Consulta
nt 1
$
50.00 656 5/07/2019 2
$
32,800.00
Reasonab
le
Total Cost
$
193,976.0
0
Average Cost
$
110,973.3
3
Maximum Cost
$
208,800.0
0
Minimum Cost
$
152,474.6
7
8
PROJECT MANAGEMENT
Labourer Carpenter Contractor Plumber Welder Electrician Project
Manager
Planner Consultant
0%
5%
10%
15%
20%
25%
30%
35%
40% 36%
7%
22%
2% 1% 3%
7% 5%
17%
Percentage of total cost
Resource
Percent
Figure 2: HR budget estimation
(Source: Created by Author)
3.4 Project risk and quality analysis
After analyzing, it is found that there is a chance of occurring the following risks that
are listed in the table below:
Risk Impact Probability Mitigation
Shortage of budget
due to inappropriate
management can
further creates a
number of financial
issues and challenges
in the project
High High Proper
management of
project
management is
helpful in
avoiding
financial issues
and challenges.
PROJECT MANAGEMENT
Labourer Carpenter Contractor Plumber Welder Electrician Project
Manager
Planner Consultant
0%
5%
10%
15%
20%
25%
30%
35%
40% 36%
7%
22%
2% 1% 3%
7% 5%
17%
Percentage of total cost
Resource
Percent
Figure 2: HR budget estimation
(Source: Created by Author)
3.4 Project risk and quality analysis
After analyzing, it is found that there is a chance of occurring the following risks that
are listed in the table below:
Risk Impact Probability Mitigation
Shortage of budget
due to inappropriate
management can
further creates a
number of financial
issues and challenges
in the project
High High Proper
management of
project
management is
helpful in
avoiding
financial issues
and challenges.
9
PROJECT MANAGEMENT
Slippage of project
schedule further
creates delay in the
project completion
date. It also helps in
increasing the budget
of the project
High High Tracking the
schedule on
regular basis is
needed for
avoiding slippage
of the project.
Utilization of
improper quality of
materials that are used
in the project creates
quality related
problems as well as
issues within the
project
Medium High The material
quality must be
checked before
utilizing it in the
project.
Inappropriate
inspection of project
site further creates a
number of issues
including improper
knowledge about the
project requirement
High Medium Proper
inspection of the
site is important
for avoiding
problems and
issues related
with construction
It is found that the quality issues that occur within the project needs to be properly
managed by following proper quality standards according to which it is quite important to use
proper quality of materials so that the quality issues related with the project can be avoided.
PROJECT MANAGEMENT
Slippage of project
schedule further
creates delay in the
project completion
date. It also helps in
increasing the budget
of the project
High High Tracking the
schedule on
regular basis is
needed for
avoiding slippage
of the project.
Utilization of
improper quality of
materials that are used
in the project creates
quality related
problems as well as
issues within the
project
Medium High The material
quality must be
checked before
utilizing it in the
project.
Inappropriate
inspection of project
site further creates a
number of issues
including improper
knowledge about the
project requirement
High Medium Proper
inspection of the
site is important
for avoiding
problems and
issues related
with construction
It is found that the quality issues that occur within the project needs to be properly
managed by following proper quality standards according to which it is quite important to use
proper quality of materials so that the quality issues related with the project can be avoided.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10
PROJECT MANAGEMENT
The materials that are used within the project needs to be checked before using it for maintain
quality. In addition to this, experienced project team members needs to be hired so that
proper quality of the project can be managed.
4. Conclusion
It can be concluded from the entire paper that the fitness centre construction will be
advantageous as it will generally helpful in providing the opportunity of exercising with the
help of a number of tools. The paper creates a project plan as per which the construction will
be completed within 154 days within the budget that is around $400,000. Moreover, the paper
also provides HR estimation and further analyzes project quality and risk analysis.
PROJECT MANAGEMENT
The materials that are used within the project needs to be checked before using it for maintain
quality. In addition to this, experienced project team members needs to be hired so that
proper quality of the project can be managed.
4. Conclusion
It can be concluded from the entire paper that the fitness centre construction will be
advantageous as it will generally helpful in providing the opportunity of exercising with the
help of a number of tools. The paper creates a project plan as per which the construction will
be completed within 154 days within the budget that is around $400,000. Moreover, the paper
also provides HR estimation and further analyzes project quality and risk analysis.
11
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Kaiser, M.G., El Arbi, F. and Ahlemann, F., 2015. Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), pp.126-139.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Mousaei, M. and Javdani, T., 2018. A New Project Risk Management Model Based on Scrum
Framework and Prince2 Methodology. International Journal of Advanced Computer Science
and Applications, 9.
Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics
applied to project management. International Journal of Project Management, 35(2), pp.169-
179.
Sánchez, M.A., 2015. Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, pp.319-330.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Kaiser, M.G., El Arbi, F. and Ahlemann, F., 2015. Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), pp.126-139.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Mousaei, M. and Javdani, T., 2018. A New Project Risk Management Model Based on Scrum
Framework and Prince2 Methodology. International Journal of Advanced Computer Science
and Applications, 9.
Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics
applied to project management. International Journal of Project Management, 35(2), pp.169-
179.
Sánchez, M.A., 2015. Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, pp.319-330.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.