Project
Management
CONSTRUCTION PROJECT: ESSENDON & BUCKLEY STREET
LEVEL CROSSING REMOVAL
Management
CONSTRUCTION PROJECT: ESSENDON & BUCKLEY STREET
LEVEL CROSSING REMOVAL
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Introduction
Project Management can be considered
as the application of the methods,
processes, skills and knowledge which
is aimed at achieving the objectives of
the project
Project management usually consist of
following points:
•Time
•Cost
•Scope
•Quality
Project Management can be considered
as the application of the methods,
processes, skills and knowledge which
is aimed at achieving the objectives of
the project
Project management usually consist of
following points:
•Time
•Cost
•Scope
•Quality
About the Project
Essendon & Buckley Street level
crossing removal
Problem Encountered
The main problem which is faced is
that the Boom gate of Buckley Street
is down for almost 78 minutes.
Creates Frustration and congestion
for the vehicles.
Essendon & Buckley Street level
crossing removal
Problem Encountered
The main problem which is faced is
that the Boom gate of Buckley Street
is down for almost 78 minutes.
Creates Frustration and congestion
for the vehicles.
About the Project (Cont.)
The main focus of the project was to
reduce the overall congestion which
was is very much hectic for the point of
view of the travellers. The main focus
was the reduction of the traffic which is
created in the point.
Victorian government took an important
step of removing the traffic congestion
by means of removing the level
crossing.
The main focus of the project was to
reduce the overall congestion which
was is very much hectic for the point of
view of the travellers. The main focus
was the reduction of the traffic which is
created in the point.
Victorian government took an important
step of removing the traffic congestion
by means of removing the level
crossing.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Implementation Overview
The main aim of the implementation
is to remove the level crossing at
Buckley Street.
The main Focus point of the removal
would be helping to remove
congestion and improve the safety.
The main aim of the implementation
is to remove the level crossing at
Buckley Street.
The main Focus point of the removal
would be helping to remove
congestion and improve the safety.
Requirement of the Project
The requirement of the project mainly
involve the following points:
Ability to enter the information of the
project.
Tracking of the project.
Reporting the project as defined by the
level crossing authority.
The requirement of the project mainly
involve the following points:
Ability to enter the information of the
project.
Tracking of the project.
Reporting the project as defined by the
level crossing authority.
Project Objective
The main objective of the project are
the following:
Removal of the level crossing at
Buckley Street, Essendon
Reduction of traffic at boom Gate
By means of minimizing
disruption improvement of the
traffic flow.
The main objective of the project are
the following:
Removal of the level crossing at
Buckley Street, Essendon
Reduction of traffic at boom Gate
By means of minimizing
disruption improvement of the
traffic flow.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project Objective (Cond)
Main advantage Achievement
Reduce transport time
Reduction of human
intervention
Improvement of facility.
Main advantage Achievement
Reduce transport time
Reduction of human
intervention
Improvement of facility.
Scope of the Project
Definition
The scope of the project mainly consist of the documentation and
the determining a list of project deliverables, goals, task, features,
deadline and most majorly the cost of the project.
In simple words it can be stated as the things which has to be done
in a project to order to reach the factor of success.
Definition
The scope of the project mainly consist of the documentation and
the determining a list of project deliverables, goals, task, features,
deadline and most majorly the cost of the project.
In simple words it can be stated as the things which has to be done
in a project to order to reach the factor of success.
Scope of the Project (Cont.)
In scope of the Project includes:
Building a road underpass which would be helping to remove the
level crossing.
Boom gate removal in order to reduce the overall congestion.
To complete the entire project within the budget and time.
In scope of the Project includes:
Building a road underpass which would be helping to remove the
level crossing.
Boom gate removal in order to reduce the overall congestion.
To complete the entire project within the budget and time.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Scope of the Project (Cont.)
The out scope project mainly consist:
The type of congestion removal after the underpass is created is
not taken into consideration.
No information in detail is provided for the up gradation of the
exiting underpass is provided.
The out scope project mainly consist:
The type of congestion removal after the underpass is created is
not taken into consideration.
No information in detail is provided for the up gradation of the
exiting underpass is provided.
Work breakdown Structure
Stakeholders
Definition
According to the Project Management Institute (PMI) the term
project stakeholders mainly explains a organisation, group of people
who are directly affect or are affected by the outcome of a project.
Definition
According to the Project Management Institute (PMI) the term
project stakeholders mainly explains a organisation, group of people
who are directly affect or are affected by the outcome of a project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Internal Stakeholders
The internal Stakeholders of the Project are:
Project Planner
Project manager
Construction engineer.
Architect
Construction technician
The internal Stakeholders of the Project are:
Project Planner
Project manager
Construction engineer.
Architect
Construction technician
External Stakeholders
The External Stakeholders of the Project are:
Contractor
Sub contractor
Creditor
Supplier
The External Stakeholders of the Project are:
Contractor
Sub contractor
Creditor
Supplier
Risk Management
There can be different risks which can be associated with the
planning and the final approval of the project. Different risk factors
which are taken into consideration are stated below:
Risk related to government approval
Risk of budget
Risk of approval
Risk of resources violation
Risk of planning and achieving the goal
There can be different risks which can be associated with the
planning and the final approval of the project. Different risk factors
which are taken into consideration are stated below:
Risk related to government approval
Risk of budget
Risk of approval
Risk of resources violation
Risk of planning and achieving the goal
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Risk Management (Cont.)
Design issue
Technical risk
Integration
communication
Design issue
Technical risk
Integration
communication
Risk Management (Cont.)
Project Team
The team which is involved in the project are:
Project manager
Financial manager
Contractor
Site supervisor
The team which is involved in the project are:
Project manager
Financial manager
Contractor
Site supervisor
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project Approval
It is very much important to get the approval from the ministry for the
implementation of the planning. On the other hand the occupiers
should also be taken into consideration about the affect they would be
having in the planning and the construction phase.
It is very much important to get the approval from the ministry for the
implementation of the planning. On the other hand the occupiers
should also be taken into consideration about the affect they would be
having in the planning and the construction phase.
Conclusion
The Buckley Street,
Essondon level crossing
removal will be very
much advantageous for
the normal citizen
which would be directly
decreasing the travel
time.
The Buckley Street,
Essondon level crossing
removal will be very
much advantageous for
the normal citizen
which would be directly
decreasing the travel
time.
Bibliography
Kerzner, H. and Kerzner, H.R., 2017. Project management: a
systems approach to planning, scheduling, and controlling. John
Wiley & Sons.
Schwalbe, K., 2015. Information technology project management.
Cengage Learning.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value
project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a
structured approach. Routledge.
Harrison, F. and Lock, D., 2017. Advanced project management: a
structured approach. Routledge.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a
systems approach to planning, scheduling, and controlling. John
Wiley & Sons.
Schwalbe, K., 2015. Information technology project management.
Cengage Learning.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value
project management. Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a
structured approach. Routledge.
Harrison, F. and Lock, D., 2017. Advanced project management: a
structured approach. Routledge.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Bibliography
Heagney, J., 2016. Fundamentals of project management. AMACOM
Div American Mgmt Assn.
Verzuh, E., 2015. The fast forward MBA in project management.
John Wiley & Sons.
Binder, J., 2016. Global project management: communication,
collaboration and management across borders. Routledge.
Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in
higher education: Learning from and with each other. Routledge.
Heagney, J., 2016. Fundamentals of project management. AMACOM
Div American Mgmt Assn.
Verzuh, E., 2015. The fast forward MBA in project management.
John Wiley & Sons.
Binder, J., 2016. Global project management: communication,
collaboration and management across borders. Routledge.
Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in
higher education: Learning from and with each other. Routledge.
1 out of 23
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.