PROJECT
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents INTRODUCTION...........................................................................................................................3 PROJECT PLAN.............................................................................................................................3 PROJECT SCOPE...........................................................................................................................4 REFERENCES................................................................................................................................1
INTRODUCTION The project plan refers to a series of activities that are related with the development of project. Under project plan a series of activities are steps are determined that would lead to the development of product or outcome (BUI, TSAI and SCHNIEDERS, 2020). This report will discuss about the project plan along with its various aspect including the concerned risk and mitigation strategies. Project success factors would also be a part of this report. PROJECT PLAN Gantt chart refers to a chart that depict the series of activities which are being adopted and carried out during the process of development (Trojanowska and Dostatni, 2017). The project for the app development is as follows: Task ModeTask NameDurationStartFinishPredecessors Auto ScheduledMain activities1 dayMon 11/1/21Mon 11/1/21 Auto ScheduledProject idea drafting1 dayTue 11/2/21Tue 11/2/211 Auto ScheduledDrafting of concept4 daysWed 11/3/21Mon 11/8/212 Auto Scheduled Defining functions and features of idea6 daysTue 11/9/21Tue 11/16/213 Auto Scheduled Formation of computer programming language15 daysWed 11/17/21Tue 12/7/214 Auto Scheduled Formulating success measures4 daysWed 12/8/21Mon 12/13/215 Auto ScheduledResearch of market5 daysTue 12/14/21Mon 12/20/216 Auto ScheduledSetting up of target group2 daysTue 12/21/21Wed 12/22/216,7 Auto ScheduledCrafting possible cost2 daysThu 12/23/21Fri 12/24/218 Auto ScheduledCrafting budget6 daysMon 12/27/21Mon 1/3/229 Auto Scheduled Determining pricing strategy4 daysTue 1/4/22Fri 1/7/229,10 Auto ScheduledHiring a graphic designer8 daysMon 1/10/22Wed 1/19/2211 Auto Scheduled Building, testing and launching landing page11 daysThu 1/20/22Thu 2/3/2212
Auto Scheduled Front and back end development6 daysFri 2/4/22Fri 2/11/2213 Auto ScheduledDevelopment14 daysMon 2/14/22Thu 3/3/2214 Auto ScheduledTesting4 daysFri 3/4/22Wed 3/9/2215 Auto ScheduledLaunching3 daysThu 3/10/22Mon 3/14/2216 PROJECT SCOPE App design: The design of the app is very important for the project. this is because if the app design would be complicated then it will not be acceptable by the customers and the result would be the affection towards the company’s sales and profit. The app would be designed in such a manner that its main features would be presentable at its front page which would be user friendly. In the
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
same way with the customer friendly user interface the app would be able to serve the need of the customers. The launch cost of the app would tried to be minimum so that the company would get the maximum profit. The app would be developed within a period of 3 months so the average cost that would be incurred would be around£9000 for the installation of the app.In the same way the cost would be made as per the expenses and benefits that would be derived from the app so that the company along with the user will get better experience.
REFERENCES Books and journals BUI, T.T., TSAI, Y.T. and SCHNIEDERS, D.D., 2020. PROJECT PLAN. Trojanowska, J. and Dostatni, E., 2017. Application of the theory of constraints for project management.Management and production engineering review.8. 1