Renovation of Head Office of Superior Implements (SIM Co.)
Verified
Added on  2023/04/20
|12
|1935
|162
AI Summary
This project plan outlines the renovation of the head office of Superior Implements (SIM Co.). It includes project details, objectives, deliverables, time management, cost management, human resource management, communication management plan, change management process, records management, and risk management plan.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Project Plan forRenovation of head office of Superior Implements (SIM Co.) Prepared by:__________________________________ Date: _________________________
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents PROJECT SCOPE.............................................................................................................2 Project Details.................................................................................................................2 Project Deliverables........................................................................................................2 Assumptions...................................................................................................................2 Constraints......................................................................................................................2 Exclusions.......................................................................................................................2 Inclusions........................................................................................................................2 TIME MANAGEMENT........................................................................................................3 Work Breakdown Structure.............................................................................................3 Gantt Chart.....................................................................................................................3 COST MANAGEMENT.......................................................................................................4 HUMAN RESOURCE MANAGEMENT...............................................................................5 COMMUNICATION MANAGEMENT PLAN........................................................................7 CHANGE MANAGEMENT PROCESS............................................................................7 RECORDS MANAGEMENT...........................................................................................7 RISK MANAGEMENT PLAN..............................................................................................8 Risk Assessment Matrix..................................................................................................9 APPENDICES..................................................................................................................10 CHANGE REQUEST FORM............................................................................................10 CHANGE SUMMARY REPORT.......................................................................................11 STATUS REPORT...........................................................................................................12 Deliverables and Milestones.............................................................................................12 Budget Status...................................................................................................................12 Work Completed During Last Period................................................................................12 Work Planned For Next Period.........................................................................................13 Open Issues/Risks............................................................................................................13 PROJECT FINAL REPORT (CLOSING).......................................................................14 BSBPMG522_AT2_Task2.2_ProjectPlan1|P a g e
PROJECT SCOPE PROJECT DETAILS Project NameRenovation of head office of Superior Implements (SIM Co.) PurposeThe main purpose of the project is completing the renovation works for the head office of Superior Implements (SIM Co.) by finishing all the expected works in the assigned time and budget. Project Objectives To renovate the head office of Superior Implements (SIM Co.) by using the effective project management tools and functions Relationshipto Organisational Objectives Renovation would help in getting rid of the damping and flaws in the infrastructure It would allow the replacing of the old facilities of kitchen and bathroom These benefits would be measured by the final approval of PROJECT DELIVERABLES SMART Objectives of the Project Specific:The project is developed for the renovation of the head office of Superior Implements (SIM Co.) and it would involve the usage of less than 6 months for the completionoftherenovationworks.Thecompanywantstheirheadofficetobe renovated and developed into a new office by working on the flooring, replacing kitchen and bathroom facilities, and refurbishing them for the organization. Measurable:The measurable quantity of the project includes the renovation works and the formation of the successive implication of the innovative work development. The quality, cost, and time can be measured for the attenuation of the works. Attainable:The work completion would be attained by the utilization of the specific and successive alignment of the work. The attainable work alignment would be formed with the continuation of the improved analysis and management. Realistic:The renovation works would be in tangible form aligning to the implication of the successful work completion at the head office. Timely:The renovation of the head office has been estimated to be completed within 6 mons and the actual time taken for the completion of the project would be measured for calculating the efficiency. ASSUMPTIONS ï‚·Acquiring of the resources in time ï‚·Formation of the team BSBPMG522_AT2_Task2.2_ProjectPlan2|P a g e
ï‚·Completion of the works ï‚·Meeting the quality and WHS standards CONSTRAINTS ï‚·Estimated Time ï‚·Calculated Budget ï‚·Required Quality Factor EXCLUSIONS ï‚·Transportation Requirement ï‚·Communication Management INCLUSIONS ï‚·Working on the flooring ï‚·Replacing kitchen and bathroom facilities ï‚·Refurbishing them for the organization TIME MANAGEMENT WORK BREAKDOWN STRUCTURE Renovation of head office of Superior Implements (SIM Co.) Initialization PhasePlanning PhaseRenovation PhaseClosure Analysis of the requirements Finalizing the works required in the Head Office Letter to sponsor for approval Project kick off Selection of Plan methodology Schedule development and Cost estimation Developing plan for the project Approval of the plan Clearing of the Kitchen and Bathroom Fixing of the flooring Washing the house Bathroom Fixation Installing wash basin Painting the Head Office Installing new equipment Furniture fixation Change of drapes and curtains Completion of the renovation Evaluation of the implementation Integration Management Closed WBSTask Name 0Renovation of head office of Superior Implements (SIM Co.) 1Initialization Phase 1.1Analysis of the requirements 1.2Finalizing the works required in the Head Office BSBPMG522_AT2_Task2.2_ProjectPlan3|P a g e
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
1.3Letter to sponsor for approval 1.4Project kick off 2Planning Phase 2.1Selection of Plan methodology 2.2Schedule development and Cost estimation 2.3Developing plan for the project 2.4Approval of the plan 3Renovation Phase 3.1Clearing of the Kitchen and Bathroom 3.2Fixing of the flooring 3.3Washing the house 3.4Bathroom Fixation 3.5Installing wash basin 3.6Painting the Head Office 3.7Installing new equipment 3.8Furniture fixation 3.9Change of drapes and curtains 3.10Completion of the renovation 4Closure 4.1Evaluation of the implementation 4.2Integration Management 4.3Closed GANTT CHART IDTask Mode WBSTask NameDurationStart 00Renovation of head office of Superior Implements (SIM Co.) 5 monsTue 1/1/19 11Initialization Phase1.15 monsTue 1/1/19 21.1Analysis of the requirements4 daysTue 1/1/19 31.2Finalizing the works required in the Head Office 5 daysMon 1/7/19 41.3Letter to sponsor for approval3 daysMon 1/28/19 51.4Project kick off0 daysThu 1/31/19 62Planning Phase0.9 monsMon 1/7/19 72.1Selection of Plan methodology3 daysMon 1/7/19 82.2Schedule development and Cost estimation 5 daysThu 1/10/19 92.3Developing plan for the project7 daysThu 1/17/19 102.4Approval of the plan0 daysWed 1/30/19 113Renovation Phase2.55 monsFri 2/1/19 123.1Clearing of the Kitchen and Bathroom 5 daysFri 2/1/19 133.2Fixing of the flooring7 daysFri 2/8/19 143.3Washing the house4 daysTue 2/19/19 153.4Bathroom Fixation6 daysMon 2/25/19 163.5Installing wash basin4 daysTue 3/5/19 173.6Painting the Head Office10 daysMon 3/11/19 183.7Installing new equipment7 daysMon 3/25/19 193.8Furniture fixation6 daysWed 4/3/19 203.9Change of drapes and curtains2 daysThu 4/11/19 213.10Completion of the renovation0 daysFri 4/12/19 224Closure1.3 monsMon 4/15/19 234.1Evaluation of the implementation20 daysMon 4/15/19 244.2Integration Management6 daysMon 5/13/19 254.3Closed0 daysMon 5/20/19 Renovator Renovator Project Manager 1/31 Planner Planner Planner 1/30 Worker,Cleaning Tools[1] Worker,Flooring[1] Worker,Cleaning Tools[1] Plumber,Taps[1],Pipes[1],Showers[1],Basin[1] Wash Basin[1],Tapes[1],Boards[1],Switches[1],Regulators[1],Plumber Painters,Paint[1] Worker,Equipments[1] Carpenter,Wood[1],Bolts[1],Door handle[1],Glasses[1] Worker,Drapes[1],Curtains[1] 4/12 5/20 FSTTSMWFSTTSMWFST Dec 16, '18Jan 6, '19Jan 27, '19Feb 17, '19Mar 10, '19Mar 31, '19Apr 21, '19May 12, '19 BSBPMG522_AT2_Task2.2_ProjectPlan4|P a g e
COST MANAGEMENT BUDGET DIRECT COSTS Wages/SalariesHourly Rate# HoursTotal Cost Renovator$7072$5,040.00 Project Manager$10024$2,400.00 Planner$60120$7,200.00 Worker$50200$10,000.00 Plumber$6580$5,200.00 Painter$7080$5,600.00 Carpenter$7548$3,600.00 Other Direct Costs Cleaning Tools$1,600.00 Flooring$250.00 Taps$500.00 Pipes$500.00 Showers$600.00 Basin$1,000.00 Wash Basin$1,250.00 Tapes$110.00 Boards$400.00 Switches$200.00 Regulators$600.00 Paint$1,500.00 Equipment$10,000.00 Wood$800.00 Bolts$300.00 Door handle$200.00 Glasses$400.00 Drapes$250.00 Curtains$500.00 Total Direct Costs: $39,040.00 Total Indirect Costs: $20,960.00 TOTAL BUDGET: $60,000.00 BSBPMG522_AT2_Task2.2_ProjectPlan5|P a g e
HUMAN RESOURCE MANAGEMENT HUMAN RESOURCE REQUIREMENTS Role to play on projectQualification required to do this role Number requiredResponsibilitySpecialist Skills Required RenovatorNA1Managing renovation worksExperience in renovation works Project ManagerManagement1Managing project works and resources Experience in managing projects PlannerNA1Developing plan for projectExperience in project planning WorkerNA1Executing the construction worksExperience in construction works PlumberNA1Executing the plumbing worksExperience in plumbing works PainterNA1Executing the painting worksExperience in painting buildings CarpenterNA1Executing the carpenting worksExperience in carpenter works
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT STAKEHOLDERS StakeholderRole on projectLevel of InterestLevel of Influence How best to manage stakeholder Project SponsorSponsors the project by funding the project and verifying all the deliverablesHighHighManage closely ClientApproving the projectHighLowManage closely Project ManagerManaging the project workLowHighManage closely End UserUsing the end product after project completionLowLowManage closely BSBPMG522_AT2_Task2.2_ProjectPlan7|P a g e
COMMUNICATION MANAGEMENT PLAN What are you to Communicate How is this to be CommunicatedFrequency FormatOwnerRecipient/ Attendees Status ReportE-mail and face- to-faceFortnightlyShort report Project Manager ProjectSponsorand Senior Management Project ProgressReportsWeeklyLong report Project teamProject owner ProjectWork RequirementDocumentationOnceLong ReportClientProject Client Information ListingFace to faceOnceTalkQuality AnalystTeam CHANGE MANAGEMENT PROCESS The change management process would be developed with the help of the implying the effective management of the project works. The change management would be helpful for the execution of the innovative work alignment and completion. The change management includes, Identification of the change required Developing strategy for the change implication Evaluation of the changes Completion of the change implication RECORDS MANAGEMENT Records are to be managed with the help of effective storing and managing the records with the help of development. The record management would be helpful for the formation of the effective storage and implication of the innovative work alignment. .
RISK MANAGEMENT PLAN Risk Description Probability Impact Risk Level CategoryCurrent Controls to Mitigate the Risk Effectiveness of these Current ControlsRisk Priority Over budget33HHighProvisional budgetHighHigh Delay42MMediumTime Management PlanLowMedium Transportation Issues34HHighHiring TransportationMediumHigh Alignment Issues24MMediumIssue managementMediumMedium 9|P a g e
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
RISK ASSESSMENT MATRIX IMPACT / CONSEQUENCE Extreme Possible project failure or increased cost to the project. High Considerable impact delaying the delivery or increasing the costs to the project. Medium Some notable impact on the project resulting in delays or increased costs. Low Minimalimpactontheproject, managed via the risk mitigation strategy. Insignificant Almost no impact on the projectmanagedwithout delays or increased costs. PROBABILITY / LIKELYHOODExtreme (Almost Certain) Over budgetAlignment Issues High (Probable)Transportation IssuesDelay Medium (50 / 50) Low (more likely the event will not occur) Insignificant (Doubtful) 10|P a g e
PROJECT APPROVALS AND DELEGATIONS Approval or delegationPerson’s NamePosition <<name of the student>><<name of the student>>Project Manager 11|P a g e