Running Head: PROJECT PLANNING AND BUDGETING St. Dismas Assisted Living Facility Project Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT PLANNING AND BUDGETING Project Goals and Objectives St. Dismas is a medical facility where the patients and injured people can get treatment after admission. In spite of providing satisfactory services, there have been some problems as the institution started losing the number of patients for some time. After conducting a survey, the authority has found that the main problem that patients are facing is that there is no residential system. Many of the patients, including the elderly people, often coming through long distances for treatment need a nearby residential centre so that they can rest and also visit the hospital in case of further need or second phase of treatment. The authority has thus decided to build an assisted living facilitywhere the patients can stay and rest for some time as required. As per the initial plan, there will be 100 units of rooms constructed in the facility where the patients will be able to stay. In addition, the patients will be assisted by specially trained nurses who will be recruited and trained after the facility is ready for use. The main goal of the project is to provide the patients of the hospital with the benefit of assisted living in a facility that will be constructed on the hospital premises. Accordingly, the objectives of the project are determined as follows. To construct an assisted living facility for the patients of the hospital To provide the assisted living facility for the critically injured and elderly patients To create opportunity for growth of the medical centre as increased number of the patients will increase the revenue of the hospital As per the primary objective of the project, the assisted living facility will be developed for the patients who will need to rest under assistance. The facility will be divided into two
2PROJECT PLANNING AND BUDGETING different departments – light assistance and heavy assistance. The light assistance rooms will be provided to the patients who will not require much assistance whereas the heavy assistance rooms will be provided for the patients who will require significant amount of assistance. For the assistance purpose, new nurses will be recruited and specially trained before allocating them with assistance duties in the living facility. In addition, special marketing will also be conducted in order to attract more patients to come to the medical centre for treatment so that the revenue of the institution increases and the medical centre can grow over the course of the next few years. Project Scope Statement The primary scope of this project is the construction of the assisted living facility for providing the facility of assisted living to the patients of the hospital. The overall scope of the project include the following. Operational Implementation– This part of the project includes the development of a suitable operational plan for the assisted living facility. As per the initial plan, several staff and assistance nurses will be recruited and allocated to the facility. Moreover, food service will also be provided to the patients and the food will be cooked in the kitchen of the facility. Legal and Licensing– Before construction and setting up of the assisted living facility, it is important to procure the license and fulfil all legal requirements and formalities associated with the project. Marketing– Marketing is another important aspect of this project. For marketing purposes, volunteers will be hired and specific marketing techniques will be used including
3PROJECT PLANNING AND BUDGETING development of community forums, establishment of inquiry log, ground breaking ceremony and others. Construction and Furnishing– This is the main part of the project in which the assisted living facility will be constructed and furnished as per the overall plan. Work Breakdown Structure (WBS) The work breakdown structure for the construction of the St. Dismas Assisted Living Facility is shown in the following table. WBSTask NameDurationStartFinishPredecessors Construction of Assisted Living Facility for St. Dismas 4Construction and Furnishing417 daysTue 06-08-19Wed 10-03-21 4.1Phase 1 - Foundation and Excavation (Basement/1st Floor Slab)95 daysTue 06-08-19Mon 16-12-19 4.2Phase 2 - Structure (Steel/Framing)113 daysFri 24-01-20Tue 30-06-202FS+28 days 4.3Phase 3 - Enclosure (Masonry/Windows/Roof)134 daysWed 01-07-20Mon 04-01-213 4.4Phase 4 - Interiors (Drywall/Ceiling/Flooring/Case Goods)234 daysFri 31-01-20Wed 23-12-203SS+1 wk 4.5First 45 (Light Assisted) Units Readiness to Prepare for Occupancy10 daysThu 31-12-20Wed 13-01-215FS+1 wk 4.6First 45 Units Ready for Residents8 wksThu 14-01-21Wed 10-03-216 4.7Remaining 57 Units (Light and Heavy) Readiness to Prepare for Occupancy10 daysThu 24-12-20Wed 06-01-215 4.8Construction Complete0 daysWed 06-01-21Wed 06-01-218 4.9Building Ready for Residents8 wksThu 07-01-21Wed 03-03-219 Project Schedule The project schedule is shown in the form of a Gantt Chart as follows.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT PLANNING AND BUDGETING Figure 1: Gantt Chart (Schedule) of the Project (Source: Created by Author) The network diagram using critical path method (CPM) (excluding non-critical tasks) is shown in the following diagram. Figure 2: Network Diagram (CPM Method) of the Project (Source: Created by Author)
5PROJECT PLANNING AND BUDGETING Bibliography Alothaimeen, I., & Arditi, D. (2019). Overview of Multi-Objective Optimization Approaches in Construction Project Management. InMulti-criteria Optimization-Pareto-optimal and Related Principles. IntechOpen. Nicholas, J. M., & Steyn, H. (2017).Project management forengineering, business and technology. Routledge. Raj,M.,&Wadsamudrakar,N.K.(2018).Riskmanagementinconstruction project.International Journal of Engineering and Management Research (IJEMR),8(3), 162-167.