PROJECT PLANNING REPORT
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents PART 1............................................................................................................................................1 Introduction.................................................................................................................................1 Business Case..............................................................................................................................1 Risk Analysis and benefit of trade show.....................................................................................1 Potential ROI (Return on Investment)........................................................................................2 Project Milestone........................................................................................................................3 Gantt Chart..................................................................................................................................3 Project Objective.........................................................................................................................3 Type of investment......................................................................................................................4 Stakeholder..................................................................................................................................4 Work break Down structure........................................................................................................4 Conclusion...................................................................................................................................4 PART 2............................................................................................................................................5 Reflection....................................................................................................................................5 REFERENCES................................................................................................................................8
PART 1 Introduction Project management is the different activity which is performed to initiate, Plan, execute, control and closing up of project to achieve the different goal very efficiently in the specified time.This report is will be consideringLondon Technology and AI Trade Showas a case scenario.This report will develop the project development plan for Softwirewho used to offer variety of IT services to the consumer. Participation of trade show which will be constructed in the last week of August will help the consumer in getting more enhanced facility of logistic and warehouse to their organizational product. Also, this report will explain the benefit of trade show and different analysis of potential stakeholder of an organization. Business Case Softwireis used to offer different supportive operation to different third party business in the UK region. Now organization is looking to organize a trade show at a platform which can help the company in promoting the different offering in the market to encourage business in the market. In current scenario organization used to offer variety of different It supportive services to third party, but now Softwire is looking to bring good amount of automation in warehouse and logistic operation of an business. Reason behind the same is to improve the customer value and customer base of company in market(Schultz, McEwen and Griffiths, 2016). Organizing a trade show will provide Softwire a platform to promote different facility of automotive warehouse and logistic to different consumer in the market so that they are aware about different offering of the company. They will also look to have different feedback of participation. Proper feedback and comment of different participation in trade show, …..Softwire will able to get a good sort of support in implement change in the service before offering it to the consumer in the market. Softwire is known for providing high quality of services to different consumer in the market, this help the company in building a good sort of relationship with the customer in the market. Also on floor and after sales service of …....Softwirewill also play a crucial role in expanding their business. Risk Analysis and benefit of trade show Risk 1
There are many risk associated with organization of this project, one of the biggest risk for the project manager is financial risk as any shortage of finance at any point in the procedure of the conducting project, may impact the efficiency of the business. Project sponsor are the one who are responsible for this type of risk in project. Another risk which is associated with conduction of the project is the scheduling of the event(Duanand et.al., 2016). This risk may take place when all the employee in the organization are not clear about the different activity which they need to perform in the organization. This will impact the processing of the project. Project manager are the responsible authority for the same. Unproper allocation of resources in project is another risk associated with the project. As it may lead to wastage of different resources and increase cost of the company. Resource allocator are the one responsible for this type of risk. Benefit for organization There are many different benefit which we be also brought by the trade show to the organization. Organizing trade show will help company in expanding the network of the business in market. As trade show will help the company in building good sort of customer base of company by enhancing the brand awareness about the product in the market. Also trade show will help company in maintaining a good sort of relationship with different client in the market. As trade show will open up a professional opportunity for Softwire to manage relationship with new client and manage different relationship with them in market. This trade show not only will help the company in getting external benefit it will also help the company in getting internal benefit as well(Syahdan, Munawaroh, and Akbar, 2018). As trade show will help the company in understanding the different perception of the customer in the market, on the basis of the same organization can plan different employee training activity, which can help the company in building good and efficient human resource in organization. Potential ROI (Return on Investment) Return on Investment will help company in finding out the efficiency of different investment cost. Estimated sale: 9500 Total investment for three days: 9000 Net profit: 5500 2
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ROI = Net Profit/ Total investment * 100 ROI = 5500/9000 * 100 = 61.1 % Expected rate of investment by participating in the trade show for SoftwireSoftwire is 61.1%. This means that there is very high rate of return on investment which is will be very beneficial for the organization in long run. Project Plan Project Milestone Project milestone plan of the company shows that project will start by developing a project and allocating project manager for the project. After that different planning will be done in the organization regarding procurement of different resources for the purpose of carrying out project in organization(Heagney, 2016). Also planning will including planning regarding budget which will be require to carry out the project in the organization. Project manager is the authority in the organization, whom will be dividing different funds to different department in the project. After that event went into the implication stages, in which organization will make sure about execute the event after evaluating the primary situation of the event and bring any sort of changes if any require. Also project manager will also look for different monitoring and controlling system in the organization. Manager will also make sure to protect the business from variety of different risk prevailing. Milestone plan of the project has also make sure that there are many different type of strategy are also developed in the project to maintain good quality of communication and public relation in the project. Gantt Chart Gantt chart and network diagram for Softwire shows that organization can complete the whole project by participating in the same for days. This is because critical path of the project shows the same(van Niekerk and Getz, 2019). 3
4
Project Objective To enhance product awareness by 10 % by the end of 1 year. To increase the customer base by 15% by the end of six month. To increase the brand image in local and international market 5
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Type of investment Softwire has to make variety of the investment related to conduction of trade show for the organization. Organization will be taking different insurance regarding the event and product to promote good sort of security in the market. Also organization will invest toward any alternative solution or the service, if this service is fail to create that sort of impact on the consumer of service. Stakeholder Project manager: Project manager is the main stakeholder of the project, as he is the one who will be responsible to carry out the different outcome of the project(Rasnacis and 6
Berzisa,2017). Project manager will be planning and implementing different strategies in the organization. Project owner: Project owner is the one in the organization who will be the one who will be finalizing and approving and coordinating different activity in the project. Supplier: Supplier are the one who will be providing different raw material to complete the project in the organization. Work break Down structure 7
8
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Conclusion After going through the report it has been concluded that Softwire is looking to organize a event to build a good brand awareness about the product , which company is planning to introduce in the organization. After that the report concludes that this project is good for company as high on thethe rate of investment prospect as well. As ROI of project is 61.1 percent in the market.The report has analyzed the key benefits and risk in participating into trade show PART 2 Reflection TakingpartinprojectplanningregardingorganizationofTradeshowforthe organization, has helped me in getting good sort of learning and knowledge from the same. As it was something new for me. In the starting stage I was feeling some sort of the pressure to carry out different operation of the project in the market. In the initial stage itself it was understood by me that there are many skill which is possess by me which will prove crucial to carry out different operation of the business for the organization. Some of such type of the skills are learning skill, leadership skill and coordinating skill. At same time there are many different type of skill which are also not possess by me to carry out different operation of the project. This will eventually impact my performance in term of carrying out the outcome of the project. This will eventually impact mine performance of in carrying out the project task, some of the such skills are communication, numeracy, ICT, working with other in team and problem solving skill. 9
I have developed an effective communication skills while carrying out the project (Meredith, Mantel Jr, and Shafer, 2017). It has helped me enhance my both written and verbal communication skills. This way it helped me communicate the idea and take effective decision which in turn leads to long term sustainable growth and productivity for carrying out the specific project within the stipulated time frame. This skill has developed me the key quality to communicate with other individuals. I have also developed effective information communication technology skills. I know how to use various platforms associated with the ICT to reach and attain high degree of innovative ways in order to interact with the various people or individuals. I have also developed skills to effectively use various Microsoft office programs as it helps in carrying out various set of computer based tasks. This way it helps me in attaining high degree of operational efficiency and productivity. It has helped me transmit the data on a real time basis.I have also developed numeracy skill of mine in the project. Reason doing same in the organization was to get better viability of the different outcome which has been carried out by me in the project. I have done this bytaking part in different seminar and conference in the market. This has helped me in understanding the different aspect of different numerical issue which was faced by me in the project in past. Another skill which was developed by me was the problem solving skill. Reason behind doing the same in the organization is that it was difficult for me to find out the solution of the different issue which is faced by the employee or me in carryout project task. This skill was developed by me by evaluating the listing skill of mine. This has eventually has also helped me in building a good sort of team building skill, as well as I was able to work with different colleague very effectiveness. Developing of written communication skills has helped me write letters, circulars and making of an effective communication plan. This way it helps in effectively managing various team members to carry out the specific set of project. Verbal communication is useful for me to communicate with the large audiences. It is useful for me to build confidence to communicate the idea with the various group of people. It is useful for me to note down various set of important information and has also helped me to verbally communicate the idea which helps in taking feedback from the tutor and clear various set of doubts. In order to work on improving my communication skills I have clearly and concisely transmitted the message to the team members. Effective communication skills has helped enhance the way I give presentation. It has also helped me to cater attraction of the audience and keep them engaged. Development of the 10
communication skills has has helped me in writing a report in a precise and clear format. ICT Skill in turn eventually helps me in carrying various set of project operations with higher accuracy and efficiency. I know how to useMicrosoft Excel,Microsoft office,Microsoft word,Microsoft Outlook, etc. This way it has helped me protect and save various set of data which in turn is very prominent in attainment of project goals and objectives. It was very interesting for me because it has developed various professional skills and knowledge which is going to be very beneficial for me in the long run. It has made it easier for me to mange my work with high degree of accuracy within the set time frame. This has also helped me gain wide set of knowledge which in turn helped me in attaining various set of skills within the set time frame. I have also developed skills to develop an attractive power point presentation which helps me in arranging data in a systematic manner. This helps in effectively communicating the relevant set of data. Developing a numeracy skill of mine has helped me in building good sort of knowledge about the different technique through which I cam solve different numeracy problem in the project, this has eventually helped me in improving the level of the performance of mine in the organization. Building a listening skill of mine has helped me in getting better pool of the idea through which I can solve the different issue which is faced by me in the project. As I am able to understand the variety of different aspect of the issue and on the basis of that I used to make more efficient decision in the organization. Not only that developing a listening skill has also helped me in building good team building skill. As with the help of the same I was able to present good image of mine in front of other colleague in the project task. Learning this sort of skill has helped me in building good sort of confidence to performs variety of the different activity in the project. This skill will eventually help me in carrying out variety of different project in the future as well. Looking at the overall experience of the project management it can be said that it was one of the pleasant experience. As it has helped me in gaining variety of different skill and knowledge about different prospect of project management. 11
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
REFERENCES Books and Journals Schultz, K., McEwen, L. and Griffiths, J., 2016. Applying Kolb’s learning cycle to competency- based residency education.Academic Medicine.91(2). p.284. Duan, Y., and et.al., 2016, June. Benchmarking deep reinforcement learning for continuous control. InInternational Conference on Machine Learning(pp. 1329-1338). Tan, Y., Zhang, Y. and Khodaverdi, R., 2017. Service performance evaluation using data envelopment analysis and balance scorecard approach: an application to automotive industry.Annals of Operations Research.248(1-2). pp.449-470. Syahdan, S. A., Munawaroh, R. S. and Akbar, H. M., 2018. Balance Scorecard Implementation in PublicSector Organization,A Problem?.InternationalJournal of Accounting, Finance, and Economics.1(1). pp.1-6. Kerzner, H., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Meredith, J. R., Mantel Jr, S .J. and Shafer, S. M., 2017.Project management: a managerial approach. John Wiley & Sons. Heagney, J., 2016.Fundamentals of project management. Amacom. Rasnacis, A. and Berzisa, S., 2017. Method for adaptation and implementation of agile project management methodology.Procedia Computer Science.104.pp.43-50. Joslin, R., 2019. Project Management Methodologies, Project Success, Project Governance, Contingency Theory, Agency Theory, and Stewardship Theory. InProject Management Methodologies, Governance and Success(pp. 17-30). Auerbach Publications. van Niekerk, M. and Getz, D., 2019. Generic Stakeholder Management Strategies. 12
APPENDIX 1 13
Task ModeTask NameDurationStartFinishPredecessors Manually Schedule d Initiation11 daysThu 3/19/20Thu 4/2/20 Auto Schedule d Determinethekey requirement3 daysThu 3/19/20Mon 3/23/20 Auto Schedule d Assign project manager3 daysTue 3/24/20Thu 3/26/202 Auto Schedule d Meet with stakeholder2 daysFri 3/27/20Mon 3/30/202,3 Auto Schedule d Sponsor Approval3 daysTue 3/31/20Thu 4/2/204 Manually Schedule d Planning stage14 daysThu 3/19/20Tue 4/7/20 Auto Schedule d Performprimary planning3 daysTue 3/31/20Thu 4/2/204 Auto Schedule d communicatewith other stakeholder1 dayFri 4/3/20Fri 4/3/204,7 Auto Schedule d bookingand transportation2 daysFri 3/27/20Mon 3/30/202,3 Auto Schedule d Makingresource planning2 daysMon 4/6/20Tue 4/7/208 Auto Schedule d Budget3 daysThu 3/19/20Mon 3/23/20 Auto Schedule d Estimating the cost1 dayWed 4/8/20Wed 4/8/2010 Auto Schedule d Allocation of financial resource2 daysThu 4/9/20Fri 4/10/2012 Manually Schedule Implementation12 daysThu 3/19/20Fri 4/3/20 14
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
d Auto Schedule d Manage communications2 daysWed 4/8/20Thu 4/9/2010 Auto Schedule d Manage procurement2 daysMon 4/6/20Tue 4/7/208 Auto Schedule d Monitoring4 daysFri 4/10/20Wed 4/15/2015,16 Auto Schedule d Risk management2 daysMon 4/13/20Tue 4/14/2012,13 Auto Schedule d Makechangesafter mitigating risk strategy2 daysWed 4/15/20Thu 4/16/2018 Manually Schedule d Closing2 daysThu 3/19/20Fri 3/20/20 Auto Schedule d Proper documentation1 dayFri 4/17/20Fri 4/17/2019 Auto Schedule d Project closure1 dayMon 4/20/20Mon 4/20/2019,21 15