ENG8208: Project Management Plan for Airport Construction Project

Verified

Added on  2022/08/23

|27
|6120
|20
Project
AI Summary
This project management assignment focuses on the construction of an open span structure at Sydney International Airport by ADCO construction. The project aims to improve passenger check-in experience by replacing existing columns and roof with a new open structure, including skylights and a diagrid roof. The assignment includes the preparation of a business case, a revised project charter, and a detailed project management plan covering integration, scope, schedule, cost, quality, resource, communication, and procurement management. The plan includes a Gantt chart, cost estimations, and a Work Breakdown Structure (WBS). The report also addresses steps taken to deliver the project within the original timeframe, the reasons behind those steps, and any additional costs incurred. This report is a comprehensive analysis of the project's planning, execution, and control phases, providing valuable insights into the complexities of large-scale construction projects. The assignment covers the key elements of project management, including scope management, schedule management, cost management, and risk assessment, and provides a practical application of project management principles.
Document Page
Running head: PROJECT MANAGEMENT
Project management
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1. Defining the organization and project.........................................................................................2
2. Preparation of business case and revised project charter.............................................................2
2.1 Business case.........................................................................................................................2
2.2 Project charter........................................................................................................................3
3. Preparation of project management plan.....................................................................................5
3.1Project integration management.............................................................................................5
3.2 Project scope management....................................................................................................6
3.3 Project schedule management................................................................................................8
3.4 Project cost management.....................................................................................................10
3.5 Project quality management................................................................................................13
3.6 Project resource management..............................................................................................14
3.7 Project communication management...................................................................................15
3.8 Project procurement management.......................................................................................16
Question 2b) Report to the project sponsor...................................................................................17
1. Steps that are taken for delivering the project within original timeframe with explanation. 17
2. Reasons of taking such step to completing project on time...................................................19
2. Ways in which project is enabled to complete within original timeframe............................20
3. Additional costs which will be incurred for achieving the target..........................................21
Bibliography..................................................................................................................................23
Document Page
2
PROJECT MANAGEMENT
1. Defining the organization and project
The paper mainly reflects on proper construction of open span structure in Sydney
International airport for passenger check-in by ADCO construction which is the oldest as well as
most established construction company of Australia. The company helps in offering a number of
services including refurbishment, renovation, construction management, as well as other types of
advisory solutions to warehouses and buildings. The project that was undertaken by the company
mainly aims to improve the design of the existing roof as well as columns that are generally
being removed as well as replaced with new open structure including high level ceiling as well as
skylights. This is mainly done in order to effectively streamline the experience of the passengers
for properly creating proper path with the help of various processes from check-in to boarding. In
addition to this, the project work generally involves proper construction of a new diagrid roof
that is mainly suspended for 28 meters above the tarmac level. Moreover, the new roof also
includes 78m of clear span trusses as well as very much new 10m of high-class façade spanning
which is of 45 meters.
2. Preparation of business case as well as revised project charter
2.1 Business case
The paper generally reflects on the construction of open span structure in Sydney
International airport for passenger check-in by ADCO construction company. It is found that due
to the presence of existing design of the airport that includes roof as well as columns, the
passengers face space issue while check-in within the airport. In order to resolve such issues and
for providing streamlined experience to the customers by developing clear path, the ADCO
construction company need to make changes within the design. The construction company takes
Document Page
3
PROJECT MANAGEMENT
the responsibility of removing the columns as well as roof which will be further replaced by an
open span structure that includes skylights as well as high level of ceiling. Additionally, it is
identified that the work of the project will get executed within the time span of 3 years.
Moreover, the project generally includes proper construction of a new diagrid roof that is mainly
suspended for around 28 meters as well as the development of new 78m clear span trusses.
2.2 Project charter
Project description
The main focus of the paper is to develop the Sydney international airport for the check
in of the passengers. In this project, the existing roofs as well as columns will be removed with
open span structure including high level ceiling as well as skylights. This mainly done in order to
streamline the experience of the passengers with clear path so that they do not face any issues
while check-in.
Project scope
The project scope mainly includes:
Project charter development
Development of proper project management plan
Proper arrangement of the equipment as well as materials
Hiring stakeholders
Developing blueprint of the design
Removal of roofs and columns
Replacement of new open space structure
Developing skylights and high-level ceiling
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
PROJECT MANAGEMENT
Construction of diagrid roof that is suspended for around 28m above the tarmac level
New roof includes 78, clear span trusses as well as 10m high class façade spanning
Project constraints
Cost: Improper expenditure on project resources as well as due to lack of project
management which can cause different types of economic challenges for the project.
Time: If the manager is unable to track the schedule properly then the manager will
generally face a lot of issues in finishing the development of Sydney International airport
within the assumed time and therefore the project completion time generally enhances.
Scope: If the work of the project gets successfully delayed then the managers are unable
to progress as per the scope which can further increase the project budget.
Deliverables
The deliverables of the project generally include:
Business case report
Project charter
Project management plan
Cost benefit analysis report
Financial report
Blueprint report for the project
Project documentation
Time required for the project
Document Page
5
PROJECT MANAGEMENT
It is found that the development of Sydney international airport for check-in of the
passengers will generally get completed within 3years of time.
3. Preparation of project management plan
3.1Project integration management
Project integration will be done successfully while developing Sydney international
airport for check in, if the different elements of the project are effectively coordinated. This
further includes proper coordination of project tasks, resources, stakeholders as well as other
type of project elements for managing conflicts between various aspect of the project
(Demirkesen and Ozorhon 2017). The project managers must take the responsibility of assessing
different situations in order to make proper decision foe successful integration management in
the entire project. The project integration can be effectively done by undertaking process that are
elaborated below:
Development of charter: Project charter is created for providing high level of
information to the project managers about the development of the project and it further helps in
authorizing the project within the enterprise that generally begins in the next process.
Development of project plan: It is considered as the second step for proper project
integration. This particular process generally includes proper planning of the project as well as
generating different plans including scope management, time management as well as proper
management of project cost (Pheng 2018).
Management of project work: This is considered as the third step and in this particular
process, the tasks are mainly carried out successfully within the entire project management plan
such that the changes are generally done as per the project requirements
Document Page
6
PROJECT MANAGEMENT
Monitoring project work: In this step, the project manager gathered different types of
user requirements (Waheed et al. 2019). In addition to this, variations related with different
planned things are generally measured for properly monitoring as well as controlling the project
work.
3.2 Project scope management
The scope management procedure that is mainly created for developing the Sydney
international airport for improving the entire procedure of check-in for the passengers helps in
ensuring that the entire project generally includes all the work that is found to be appropriate for
achieving the objectives. It further helps in enabling the managers as well as supervisors for
allocating the amount of work which is mainly needed for positively completing the work of the
project (Corvello, Javernick-Will and Ratta 2017). The entire scope which is developed for the
entire project gets managed effectively by using six steps that are elaborated below:
Planning scope: In this particular step, the project manager generally gathers different
types of input that is needed for the stakeholders in order to develop the international airport of
Sydney for passengers check in facility. They also added information for handling different types
of unforeseen circumstances that will generally occur within the project.
Collecting requirements: In this step, proper idea about the stakeholders must be
gathered for successfully managing the different expectations of the project. The manager will
generally document what is generally needed in the project (Corvello, Javernick-Will and Ratta
2017). Furthermore, the requirement management plan that is developed is generally helpful in
avoiding various types of frustrating hurdles within the project.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
Defining scope: The project scope should be defined clearly so that the project scope will
generally serve as an important guides within the project. The project team members generally
refer to it and completes the work so that the project objectives can be met quite successfully.
Creating WBS: As per the scope of the project as well as documents which are created
during the requirement collection, a work breakdown structure is mainly created. The WBS
which is provided below assists in reflecting how construction works are generally carried out in
different phases such that the manager can be able to manage the work of the project quite
successfully (Raza 2019). The provided WBS helps in reflecting that the work of the project will
get completed within initiation, planning, construction as well as closure phases.
Creating open span
structure in Sydney
International airport for
passenger check-in by
ADCO construction
company
Initiation phase
Identyfying the issue
Determining
solution
Creating business
case
Undertaking cost
benefit analysis
Milestone 1:
Completion of
initiation phase
Planning phase
Development of
project charter
Development of
project management
plan
Arranging
equipments and
materials
Hiring stakeholders
Arranaging the
funding for the
project
Milestone 2:
Completion of
planning phase
Execution phase
Creating the
blueprint for the
construction
Getting approval for
the blueprint
Allocating work to
the team members
Removal of roof and
colums
Replacement of new
open span structure
Adding skylights and
high level ceiling
Creation of clear
paths
Construction of a
new diagrid roof
Suspension of
diagrid roof above
tarmac level
78M clear span
trusses
Adding 10m high
class façade
Milestone 3:
Completion of
execution phase
Close out phase
Undertaking quality
assurance
Stakeholder sign off
Documentation
Milestone 4:
Releasing the
involved resources
Figure 1: WBS
Document Page
8
PROJECT MANAGEMENT
(Source: Created by Author)
Validating scope: In this step, the manager takes the responsibility of reviewing the
deliverables. It is necessary to create proper plan so that the deliverables of the project get
accepted as complete. In the last phase, one can be able to accept deliverables, change requests
as well as can be able to update project documents.
Controlling scope: The status report should be monitored by the manager starting from
the kick off phase till the close out phase so that each of the activities of the project gets executed
on time (Lampa et al. 2017). For successfully controlling the scope, the managers generally
compare the initial report with the performance report.
3.3 Project schedule management
It is identified that schedule management generally plays an important role in developing,
maintaining as well as communicating the time as well as resources which are assigned in each
of the project activity for successful completion of the project. The schedule that is created helps
in giving a starting and closure date for each of the activity so that the project manager can
complete that work within that time-period (Kerzner 2017).The Gantt chart that is developed
helps in providing proper graphical reflection of the schedule which is further beneficial in
properly communicating the project timeline in a very much simple as well as quick manner. The
schedule that is used by ADCO company for undertaking the project is reflected below:
Document Page
9
PROJECT MANAGEMENT
Figure 2: Gantt chart
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
PROJECT MANAGEMENT
3.4 Project cost management
It is found that in order to undertake the work of construction, proper financial support
will be delivered by the Australian government. In addition to this, it is necessary to ensure that
the cost estimation must be done accurately so that the budget of the project does not increase in
any circumstances. The budget that is estimated for undertaking each of the steps is reflected in
the figure below.
WBS Task Name Duration Resource Names Cost
0
Creating open span structure in
Sydney International airport for
passenger check-in by ADCO
construction company
36 mons $ 5,000,000.00
1 Initiation phase 1 mon $ 10,560.00
1.1 Identifying the issue 6 days Project manager $ 2,640.00
1.2 Determining solution 4 days Project planner $ 1,600.00
1.3 Creating business case 6 days
Project manager,
Project planner
$ 5,040.00
1.4 Undertaking cost benefit analysis 4 days Financial manager $ 1,280.00
1.5
Milestone 1: Completion of
initiation phase
0 days $ 0.00
2 Planning phase 2 mons $ 14,960.00
2.1 Development of project charter 6 days Project manager $ 2,640.00
2.2 Development of project 10 days Project planner $ 4,000.00
Document Page
11
PROJECT MANAGEMENT
management plan
2.3
Arranging equipment’s and
materials
6 days HR manager $ 2,160.00
2.4 Hiring stakeholders 10 days HR manager $ 3,600.00
2.5
Arranging the funding for the
project
8 days Financial manager $ 2,560.00
2.6
Milestone 2: Completion of
planning phase
0 days $ 0.00
3 Execution phase 32 mons $ 4,967,040.00
3.1
Creating the blueprint for the
construction
3 mons Designer/architect $ 21,600.00
3.2 Getting approval for the blueprint 1 mon Project manager $ 8,800.00
3.3
Allocating work to the team
members
2 mons HR manager $ 14,400.00
3.4 Removal of roof and columns 3 mons
Civil engineer,
Construction
manager, Equipment
cost [1]
$ 1,546,080.00
3.5
Replacement of new open span
structure
5 mons
Construction
manager, Contractor,
Materials [1]
$ 2,072,800.00
3.6 Adding skylights and high-level 3 mons Civil engineer, $ 45,600.00