Project Risk Management: ERP Project Failure
VerifiedAdded on 2023/06/14
|34
|6715
|231
AI Summary
This report reflects the importance of developing proper risk management plan for a nominated environment that is “ERP implementation failure in a multinational company”. It is the responsibilities of the project manager to develop allot resources for each of the project activities. FMEA technique for managing risks is adopted in this report for developing the risk management plan. In addition to this, the ToR and the risk acceptance criteria for the situation is also developed in this report.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT RISK MANAGEMENT
Project Risk Management: ERP Project Failure
Bam of the student:
Name of the university:
Project Risk Management: ERP Project Failure
Bam of the student:
Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT RISK MANAGEMENT
Executive summary
This report reflects the importance of developing proper risk management plan for a nominated
environment that is “ERP implementation failure in a multinational company”. It is the
responsibilities of the project manager to develop allot resources for each of the project
activities. FMEA technique for managing risks is adopted in this report for developing the risk
management plan. In addition to this, the ToR and the risk acceptance criteria for the situation is
also developed in this report.
Executive summary
This report reflects the importance of developing proper risk management plan for a nominated
environment that is “ERP implementation failure in a multinational company”. It is the
responsibilities of the project manager to develop allot resources for each of the project
activities. FMEA technique for managing risks is adopted in this report for developing the risk
management plan. In addition to this, the ToR and the risk acceptance criteria for the situation is
also developed in this report.
2PROJECT RISK MANAGEMENT
Table of Contents
Overview..........................................................................................................................................4
1. Literature review..........................................................................................................................4
2. Content of Risk management plan.............................................................................................10
2.1 Identification of project stakeholders..................................................................................14
2.2 Defining system boundaries................................................................................................15
3. Defining project context............................................................................................................15
4. Discussing the social benefits of risk exposure.........................................................................15
5. Usage of FMEA technique to identify, quantify and mitigate the source of risk......................16
6. Different risk assessment methods............................................................................................16
7. Presenting risk tolerability criteria.............................................................................................16
8. Quantified Tolerability of Risk (ToR) discussion and relevant measures on ToR table...........17
9. Discussion on the findings.........................................................................................................19
References......................................................................................................................................20
Appendices....................................................................................................................................24
Appendix 1: Risk Identification Checklist................................................................................24
Appendix 2: Risk Register.........................................................................................................24
Appendix 3: FMEA Analysis....................................................................................................16
Appendix 4: Example................................................................................................................16
Appendix 5: Risk treatment table..............................................................................................16
Table of Contents
Overview..........................................................................................................................................4
1. Literature review..........................................................................................................................4
2. Content of Risk management plan.............................................................................................10
2.1 Identification of project stakeholders..................................................................................14
2.2 Defining system boundaries................................................................................................15
3. Defining project context............................................................................................................15
4. Discussing the social benefits of risk exposure.........................................................................15
5. Usage of FMEA technique to identify, quantify and mitigate the source of risk......................16
6. Different risk assessment methods............................................................................................16
7. Presenting risk tolerability criteria.............................................................................................16
8. Quantified Tolerability of Risk (ToR) discussion and relevant measures on ToR table...........17
9. Discussion on the findings.........................................................................................................19
References......................................................................................................................................20
Appendices....................................................................................................................................24
Appendix 1: Risk Identification Checklist................................................................................24
Appendix 2: Risk Register.........................................................................................................24
Appendix 3: FMEA Analysis....................................................................................................16
Appendix 4: Example................................................................................................................16
Appendix 5: Risk treatment table..............................................................................................16
3PROJECT RISK MANAGEMENT
Overview
The uncertainty in economic times in the past decades is increasing eventually in
different business organizations those are needed to be mitigated by developing proper risk
mitigation planning. In order to evaluate any project in the engineering environment proper
operational and functional activities are needed to be implemented by the project managers. For
this particular project, the Nominated engineering environment is about the implementation of an
Enterprise Resource planning (ERP), system in a Multinational Business organization. However,
due to lack of proper risk management planning the ERPS system failed to give the project
objectives to the consumers and the employee who are working for the company.
This paper is focused on the development of an accurate risk management plan for a
situation which has interrupting the measurable success of a project in an engineering
organization. In order to prepare the project risk management plan both the oral and written
medium are selected. For this particular situation the risk management plan that has been
developed is consists of risk identification, risk analysis, evaluation, treatment, communication
and risk consultant. In addition to this, proper risk monitoring and risk review are the other
important components considered for this project.
1. Literature review
This literature depicts the importance of developing accurate risk management plan for
different engineering environment. According to [17] for any business environment, the main
reason of uncertainty is risk. Thus, most the companies are focusing on the identification of risks
and management of risks even before it affect the business success negatively. There are many
Overview
The uncertainty in economic times in the past decades is increasing eventually in
different business organizations those are needed to be mitigated by developing proper risk
mitigation planning. In order to evaluate any project in the engineering environment proper
operational and functional activities are needed to be implemented by the project managers. For
this particular project, the Nominated engineering environment is about the implementation of an
Enterprise Resource planning (ERP), system in a Multinational Business organization. However,
due to lack of proper risk management planning the ERPS system failed to give the project
objectives to the consumers and the employee who are working for the company.
This paper is focused on the development of an accurate risk management plan for a
situation which has interrupting the measurable success of a project in an engineering
organization. In order to prepare the project risk management plan both the oral and written
medium are selected. For this particular situation the risk management plan that has been
developed is consists of risk identification, risk analysis, evaluation, treatment, communication
and risk consultant. In addition to this, proper risk monitoring and risk review are the other
important components considered for this project.
1. Literature review
This literature depicts the importance of developing accurate risk management plan for
different engineering environment. According to [17] for any business environment, the main
reason of uncertainty is risk. Thus, most the companies are focusing on the identification of risks
and management of risks even before it affect the business success negatively. There are many
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT RISK MANAGEMENT
companies who used to operate their business much smoothly and also with the help of the
business forecast and projection. Due to these reasons the companies have adopted renewed to
manage the risks [30]. In order to make future decisions for the businesses much confidently risk
management approaches help the companies a lot. Business organizations face both the internal
and external factors that influence the uncertain weather of the business organization. Proper risk
management plan will help the business organizations to reach its objectives within the estimated
time period. The business environments will be impacted positively with an accurate risk
management plan. [17] Stated that, risks may be generated from both internal and external
sources. The external risks such as political risk, exchange risk, interest risk etc are those which
cannot be directly controlled by the management team. [24] argued that, based on the
background of the projects, proper risk management plan should be developed by the project
manager rater project executives. There are many business organizations that have incorporated
risk management as a department in their business organization. Besides internal and external
risks there are another risk named as critical risk which have adverse influence in the business in
the business organization [10]. In the year of 2005, the international organization and standard
had developed a working group and also implemented the first international risk management
standard considering the AS/NZS 4360:2004 as the first draft that was advised to be followed by
all the business organization of Australia and New Zealand. The standard development process
contains both the public consultation of Australia and New Zealand. The public consultation
results in the ISO 31000:2009 publication. The AS/NZS ISO 31000:2009 does not differ much
from the AS/NZS ISO 31000:2004 [14]. Minor modifications are done on the standard of 2004
and the modified version was officially promoted and published in the year of 2009. This
standard shows the relation among the risk management principles, framework and process
companies who used to operate their business much smoothly and also with the help of the
business forecast and projection. Due to these reasons the companies have adopted renewed to
manage the risks [30]. In order to make future decisions for the businesses much confidently risk
management approaches help the companies a lot. Business organizations face both the internal
and external factors that influence the uncertain weather of the business organization. Proper risk
management plan will help the business organizations to reach its objectives within the estimated
time period. The business environments will be impacted positively with an accurate risk
management plan. [17] Stated that, risks may be generated from both internal and external
sources. The external risks such as political risk, exchange risk, interest risk etc are those which
cannot be directly controlled by the management team. [24] argued that, based on the
background of the projects, proper risk management plan should be developed by the project
manager rater project executives. There are many business organizations that have incorporated
risk management as a department in their business organization. Besides internal and external
risks there are another risk named as critical risk which have adverse influence in the business in
the business organization [10]. In the year of 2005, the international organization and standard
had developed a working group and also implemented the first international risk management
standard considering the AS/NZS 4360:2004 as the first draft that was advised to be followed by
all the business organization of Australia and New Zealand. The standard development process
contains both the public consultation of Australia and New Zealand. The public consultation
results in the ISO 31000:2009 publication. The AS/NZS ISO 31000:2009 does not differ much
from the AS/NZS ISO 31000:2004 [14]. Minor modifications are done on the standard of 2004
and the modified version was officially promoted and published in the year of 2009. This
standard shows the relation among the risk management principles, framework and process
5PROJECT RISK MANAGEMENT
individually. Most of finance departments of the large to medium organizations follow the
standard to avoid economic complications. However, after the development of AS/NZS ISO
31000:2009, the risk management standard developed in AS/NZS ISO 31000:2004 was
completely replaced [18]. During the development of the risk management program or
framework for any business organization, the fund member agencies provide AS/NZS ISO: 3100
principles and guidelines.
In this current technology era, the organizations who are failing to adopt proper technical
operations, will lag to meet their objectives easily and also will fail to give competition to other
companies [29] It is the responsibility of the project managers and other managerial executives,
to adopt the most suitable risk management plan to avoid all commercial, social, legal and
environmental risks collectively. Under the AS/NZS ISO 31000:2009 the definition of risk has
been changed and became the “effect of uncertainty over the objectives” [12]. Thus, before
developing any risk management plan the below mentioned steps are needed to be considered by
the risk management plan developers:
Clear understanding about the purpose or event which is facing major risk
Identification of all presentable activities and attractions
Creation of the environment to be presented in the nominated event
Identification of the audience who are expected to be attracted just after the risk
will be resolved
In order to develop a risk management plan the developers maintain a consistent
sequence rather systematic approach to analyze and realize the impact of the risks. In general
there are common phases those are considered for the development of the risks management plan
individually. Most of finance departments of the large to medium organizations follow the
standard to avoid economic complications. However, after the development of AS/NZS ISO
31000:2009, the risk management standard developed in AS/NZS ISO 31000:2004 was
completely replaced [18]. During the development of the risk management program or
framework for any business organization, the fund member agencies provide AS/NZS ISO: 3100
principles and guidelines.
In this current technology era, the organizations who are failing to adopt proper technical
operations, will lag to meet their objectives easily and also will fail to give competition to other
companies [29] It is the responsibility of the project managers and other managerial executives,
to adopt the most suitable risk management plan to avoid all commercial, social, legal and
environmental risks collectively. Under the AS/NZS ISO 31000:2009 the definition of risk has
been changed and became the “effect of uncertainty over the objectives” [12]. Thus, before
developing any risk management plan the below mentioned steps are needed to be considered by
the risk management plan developers:
Clear understanding about the purpose or event which is facing major risk
Identification of all presentable activities and attractions
Creation of the environment to be presented in the nominated event
Identification of the audience who are expected to be attracted just after the risk
will be resolved
In order to develop a risk management plan the developers maintain a consistent
sequence rather systematic approach to analyze and realize the impact of the risks. In general
there are common phases those are considered for the development of the risks management plan
6PROJECT RISK MANAGEMENT
including risk identification, risk analysis, prioritize and control. According to [6] in this risk
management plan the input of any phase should have to be the output of the previous phase. Mis-
link between any two phases will lead the risk management plan towards failure. Development
of a risk management plan and its assessment prior to the identified risky event the potential risks
can even be identified and prioritize accordingly in terms of likelihood, consequence etc [28]. In
order to reduce and mitigate all potential risks, risk control and mitigation approaches are needed
to be undertaken. The below are the content of the risk assessment process and plan to be
delivered:
Identification of risk: Risk is referred to as an event that prevents any project to meet its
objectives as the progress was previously planned. [21] stated that, different resources are needed
to complete any project and risks can occur from any of the resources. Some of the risks may be
quite general and are identified prior to project kickoff. Even the project developer fails to
identify those risks at the initial phase then during the project lifecycle phase those can be easily
identified [15]. Collectively it can be said that for successfully assist any project, risk
management plan development is a very important part. Some of the risks can be inherent
whereas some of the risks are occurred due to external influence [3]. Internal risks are still easy
to control whereas the external risks control is difficult. Not only this external risk control but
also external risk identification is also a difficult part of project development lifecycle. It is the
responsibility of the project manager to control the project risks. According to [5] for reporting to
the project manager in every project there are specific areas where the project team members are
allotted. Throughout the project development lifecycle, the intent of the project manager is to
develop a project team who will assign only for the risk awareness, identification,
communication and documentation. Risk awareness is the practice that assures that all the project
including risk identification, risk analysis, prioritize and control. According to [6] in this risk
management plan the input of any phase should have to be the output of the previous phase. Mis-
link between any two phases will lead the risk management plan towards failure. Development
of a risk management plan and its assessment prior to the identified risky event the potential risks
can even be identified and prioritize accordingly in terms of likelihood, consequence etc [28]. In
order to reduce and mitigate all potential risks, risk control and mitigation approaches are needed
to be undertaken. The below are the content of the risk assessment process and plan to be
delivered:
Identification of risk: Risk is referred to as an event that prevents any project to meet its
objectives as the progress was previously planned. [21] stated that, different resources are needed
to complete any project and risks can occur from any of the resources. Some of the risks may be
quite general and are identified prior to project kickoff. Even the project developer fails to
identify those risks at the initial phase then during the project lifecycle phase those can be easily
identified [15]. Collectively it can be said that for successfully assist any project, risk
management plan development is a very important part. Some of the risks can be inherent
whereas some of the risks are occurred due to external influence [3]. Internal risks are still easy
to control whereas the external risks control is difficult. Not only this external risk control but
also external risk identification is also a difficult part of project development lifecycle. It is the
responsibility of the project manager to control the project risks. According to [5] for reporting to
the project manager in every project there are specific areas where the project team members are
allotted. Throughout the project development lifecycle, the intent of the project manager is to
develop a project team who will assign only for the risk awareness, identification,
communication and documentation. Risk awareness is the practice that assures that all the project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT RISK MANAGEMENT
team members are aware of the risks it outcome and all other side-effects. On the other hand, risk
identification identifies those risks for which the project outcome may be impacted negatively.
Risk communication is all about serious discussion about the project risks. It means that through
risks communication the risks those may affect the project success are come under the attention
or focus of the project managers and other project heads. In order to control the risks the project
developers should develop a risk register eventually. The risk register must contain notification
on the arrival of any new risk. According to [20], a section should be added to the risk register to
describe the risk in details. Again [25] stated that, besides risk description there must be a part to
identify the probability of the risks. Some of the risks occur frequently whereas; some of the
risks are rare but have high negative impact in the projects outcomes. The other sections to be
managed in the project risk identification phase include, impact of risk schedule, quality
management, cost impact etc. It is the responsibility of the project manager to develop and share
the risks among the members associated to the project [22]. The following is the mentioned table
to be usually followed by the project managers to control all the identified risks:
Activity Responsibility
Risk identification Project stakeholders
Risk registry Project manager and other project executives
Risk assessment All the stakeholders associated to the project
Risk response Stakeholders
Approval to the responded risks Project manager along with the executives
Contingency management Project managers
Managing risk response Project managers
Reporting of the risks Project managers
team members are aware of the risks it outcome and all other side-effects. On the other hand, risk
identification identifies those risks for which the project outcome may be impacted negatively.
Risk communication is all about serious discussion about the project risks. It means that through
risks communication the risks those may affect the project success are come under the attention
or focus of the project managers and other project heads. In order to control the risks the project
developers should develop a risk register eventually. The risk register must contain notification
on the arrival of any new risk. According to [20], a section should be added to the risk register to
describe the risk in details. Again [25] stated that, besides risk description there must be a part to
identify the probability of the risks. Some of the risks occur frequently whereas; some of the
risks are rare but have high negative impact in the projects outcomes. The other sections to be
managed in the project risk identification phase include, impact of risk schedule, quality
management, cost impact etc. It is the responsibility of the project manager to develop and share
the risks among the members associated to the project [22]. The following is the mentioned table
to be usually followed by the project managers to control all the identified risks:
Activity Responsibility
Risk identification Project stakeholders
Risk registry Project manager and other project executives
Risk assessment All the stakeholders associated to the project
Risk response Stakeholders
Approval to the responded risks Project manager along with the executives
Contingency management Project managers
Managing risk response Project managers
Reporting of the risks Project managers
8PROJECT RISK MANAGEMENT
Risk assessment: Risk assessment is referred to as an act that helps to determine the
probability of risk, whose occurrence negatively impacts the project objectives [19]. Risk
assessment can be also defined as a cause and effect analysis. Cause is the event that may occur
during the project development phase and effect is the potential impact of the risk that may
interrupt the success of any project. Risk assessment is divided into two different factors such as
probability that measures the event and estimation on the impact of the risks [16]. Cost
estimation, potential delay duration, scope and reduction changes are the qualities those are very
important factors to be considered for assessing the risks. In order to avoid the risks there are
certain project management tools to be considered including project plan, budget planning, work
statement etc.
Risks response or risk prioritization: For each individual risk, the way of response
should be different. In order to identify the risk response for each of the risk the project managers
are responsible [14]. For selecting the correct response for each risk, the project team members
should select the best possible risk assessment way. Based on the type and background of the
risks the risks should be priorities or scored out of 10. In order to evaluate risk mitigation
strategies for multiple risk proper cost is needed to be developed [10]. There are different risk
response options available those are necessary to be developed by the project managers in terms
of avoidance, transference, mitigation, and acceptance and deferred. Risk avoidance is referred to
as the way in which projects should be changed in terms of change scope and objectives etc. Risk
mitigation is the development of strategies for individual risks. This step helps to reduce the
identified and assessed risk from the projects [12]. Instead of eliminating risk, risks should be
shifted to the third parties. Risk acceptance is the way to simply accept the risks and not to avoid
Risk assessment: Risk assessment is referred to as an act that helps to determine the
probability of risk, whose occurrence negatively impacts the project objectives [19]. Risk
assessment can be also defined as a cause and effect analysis. Cause is the event that may occur
during the project development phase and effect is the potential impact of the risk that may
interrupt the success of any project. Risk assessment is divided into two different factors such as
probability that measures the event and estimation on the impact of the risks [16]. Cost
estimation, potential delay duration, scope and reduction changes are the qualities those are very
important factors to be considered for assessing the risks. In order to avoid the risks there are
certain project management tools to be considered including project plan, budget planning, work
statement etc.
Risks response or risk prioritization: For each individual risk, the way of response
should be different. In order to identify the risk response for each of the risk the project managers
are responsible [14]. For selecting the correct response for each risk, the project team members
should select the best possible risk assessment way. Based on the type and background of the
risks the risks should be priorities or scored out of 10. In order to evaluate risk mitigation
strategies for multiple risk proper cost is needed to be developed [10]. There are different risk
response options available those are necessary to be developed by the project managers in terms
of avoidance, transference, mitigation, and acceptance and deferred. Risk avoidance is referred to
as the way in which projects should be changed in terms of change scope and objectives etc. Risk
mitigation is the development of strategies for individual risks. This step helps to reduce the
identified and assessed risk from the projects [12]. Instead of eliminating risk, risks should be
shifted to the third parties. Risk acceptance is the way to simply accept the risks and not to avoid
9PROJECT RISK MANAGEMENT
it. If the risks are accepted then respective changes should be included in project schedule, scope,
cost, quality etc.
Risk control: The phase called risk mitigation or control are again divided into two
different parts according to AS/NZS ISO 31000:2009 [20]. At the initial phase of risk mitigation,
all the different activities rather steps should be identified. After identification of the risks a
contingency plan has to be developed by the project managers to deal with the tasks. For each
and individual phase accurate risk mitigation plan or control plan should be developed. With the
help of risk assessment matrix, the priority and its ranking can be eventually identified. Risk can
be catastrophic, critical, moderate, minor and negligible and from the priority matrix
implementation of risk mitigation plan will become much easier.
2. Content of Risk management plan
In the year of 2004, a multinational company announced about their failure in Enterprise
Resource Planning (ERP) which affected their commercial failure. The net revenue of the
company faced about more than 56% of failure in this ERP failure [21]. During the development
of a centralize ERP system in their company, they failed to develop proper risk management plan
and as a result they lost their revenue a lot that is more than 5 times of their quarterly profit. The
complete financial impacts of the ERP failure include backlogs, revenue lost. The products of
the company are well known for their excellent products quality and reasonable price. There is a
decentralized organizational structure and this is the responsibility of each of the business units
to design market and manufacture their own software products. The engineering company faced
high level risk due to the improper risk management planning [26]. From the resellers and direct
consumers the multinational company witnessed excessive benefit from their quality product and
it. If the risks are accepted then respective changes should be included in project schedule, scope,
cost, quality etc.
Risk control: The phase called risk mitigation or control are again divided into two
different parts according to AS/NZS ISO 31000:2009 [20]. At the initial phase of risk mitigation,
all the different activities rather steps should be identified. After identification of the risks a
contingency plan has to be developed by the project managers to deal with the tasks. For each
and individual phase accurate risk mitigation plan or control plan should be developed. With the
help of risk assessment matrix, the priority and its ranking can be eventually identified. Risk can
be catastrophic, critical, moderate, minor and negligible and from the priority matrix
implementation of risk mitigation plan will become much easier.
2. Content of Risk management plan
In the year of 2004, a multinational company announced about their failure in Enterprise
Resource Planning (ERP) which affected their commercial failure. The net revenue of the
company faced about more than 56% of failure in this ERP failure [21]. During the development
of a centralize ERP system in their company, they failed to develop proper risk management plan
and as a result they lost their revenue a lot that is more than 5 times of their quarterly profit. The
complete financial impacts of the ERP failure include backlogs, revenue lost. The products of
the company are well known for their excellent products quality and reasonable price. There is a
decentralized organizational structure and this is the responsibility of each of the business units
to design market and manufacture their own software products. The engineering company faced
high level risk due to the improper risk management planning [26]. From the resellers and direct
consumers the multinational company witnessed excessive benefit from their quality product and
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT RISK MANAGEMENT
services. Under the light of the increasing demand for different products the company had
planned to reorganize their business process for managing the complex situations. It is expected
that the newly arranged business process will help the company to operate its functionalities.
The aim of the company is to design a business plan to venture into a high volume of low priced
electronic market. The company also planned to phase the legacy system as a standard ERP
solution [23]. In order to implement a SAP R/3 ERP securely a risk management plan is needed
to be developed by the project manager. Basically the major failure was faced by the company
during the ERP migration. It is expected that, if proper risk management plan is developed for
the company then all the issues will be resolved appropriately. The risk management plan
developed for the company is mentioned below:
Risk management plan
Like the other project, in case of ERP implementation also a risk management plan
should be developed [32]. The risk management plan for the company should be consists of
three phases in terms of planning, implementation and post implementation phases. During ERP
planning risk analysis is a phase that is closely associated to the selection of ERP system. The
risk management plan developed for the nominated environment is mentioned below:
Task Name Duration Start Finish Predecessors Resource
Names
Risk management
planning 143 days Mon 4/9/18 Wed 10/24/18
Risk identification 30 days Mon 4/9/18 Fri 5/18/18
Understanding
project scope 6 days Mon 4/9/18 Mon 4/16/18 Project
manager
Analyzing project
activities
5 days Tue 4/17/18 Mon 4/23/18 2 Project
manager ,Proje
services. Under the light of the increasing demand for different products the company had
planned to reorganize their business process for managing the complex situations. It is expected
that the newly arranged business process will help the company to operate its functionalities.
The aim of the company is to design a business plan to venture into a high volume of low priced
electronic market. The company also planned to phase the legacy system as a standard ERP
solution [23]. In order to implement a SAP R/3 ERP securely a risk management plan is needed
to be developed by the project manager. Basically the major failure was faced by the company
during the ERP migration. It is expected that, if proper risk management plan is developed for
the company then all the issues will be resolved appropriately. The risk management plan
developed for the company is mentioned below:
Risk management plan
Like the other project, in case of ERP implementation also a risk management plan
should be developed [32]. The risk management plan for the company should be consists of
three phases in terms of planning, implementation and post implementation phases. During ERP
planning risk analysis is a phase that is closely associated to the selection of ERP system. The
risk management plan developed for the nominated environment is mentioned below:
Task Name Duration Start Finish Predecessors Resource
Names
Risk management
planning 143 days Mon 4/9/18 Wed 10/24/18
Risk identification 30 days Mon 4/9/18 Fri 5/18/18
Understanding
project scope 6 days Mon 4/9/18 Mon 4/16/18 Project
manager
Analyzing project
activities
5 days Tue 4/17/18 Mon 4/23/18 2 Project
manager ,Proje
11PROJECT RISK MANAGEMENT
ct sponsor
Defining risks 8 days Tue 4/24/18 Thu 5/3/18 3 Project sponsor
Considering
possible risks
associated to ERP
6 days Fri 5/4/18 Fri 5/11/18 4 HR manager
Developing
analytical process
models
4 days Fri 5/4/18 Wed 5/9/18 4
system analyst,
system
developer
Considering
amount of risks 5 days Mon 5/14/18 Fri 5/18/18 5
Project
manager ,syste
m developer
Developing
business strategies 6 days Thu 5/10/18 Thu 5/17/18 6 finance
manager
Risk analysis 37 days Mon 5/21/18 Tue 7/10/18
Risks of ERP are
to be analyzed 4 days Mon 5/21/18 Thu 5/24/18 7 system
developer
Proper software
configuration 8 days Fri 5/25/18 Tue 6/5/18 8,10
Project
sponsor, system
developer
Contract and
developing Service
Level Agreement
5 days Wed 6/6/18 Tue 6/12/18 11 Project sponsor
Considering
Delphi technique 6 days Wed 6/13/18 Wed 6/20/18 12 Project sponsor
Hierarchical
process improvement 6 days Thu 6/21/18 Thu 6/28/18 13
system analyst,
system
developer
Considering ISO
31000:2009 standards 5 days Fri 6/29/18 Thu 7/5/18 14 Project
manager
Risk
communication 3 days Fri 7/6/18 Tue 7/10/18 15 HR manager
Risk prioritize 44 days Wed 7/11/18 Mon 9/10/18
Analyzing each of 5 days Wed 7/11/18 Tue 7/17/18 16 finance
ct sponsor
Defining risks 8 days Tue 4/24/18 Thu 5/3/18 3 Project sponsor
Considering
possible risks
associated to ERP
6 days Fri 5/4/18 Fri 5/11/18 4 HR manager
Developing
analytical process
models
4 days Fri 5/4/18 Wed 5/9/18 4
system analyst,
system
developer
Considering
amount of risks 5 days Mon 5/14/18 Fri 5/18/18 5
Project
manager ,syste
m developer
Developing
business strategies 6 days Thu 5/10/18 Thu 5/17/18 6 finance
manager
Risk analysis 37 days Mon 5/21/18 Tue 7/10/18
Risks of ERP are
to be analyzed 4 days Mon 5/21/18 Thu 5/24/18 7 system
developer
Proper software
configuration 8 days Fri 5/25/18 Tue 6/5/18 8,10
Project
sponsor, system
developer
Contract and
developing Service
Level Agreement
5 days Wed 6/6/18 Tue 6/12/18 11 Project sponsor
Considering
Delphi technique 6 days Wed 6/13/18 Wed 6/20/18 12 Project sponsor
Hierarchical
process improvement 6 days Thu 6/21/18 Thu 6/28/18 13
system analyst,
system
developer
Considering ISO
31000:2009 standards 5 days Fri 6/29/18 Thu 7/5/18 14 Project
manager
Risk
communication 3 days Fri 7/6/18 Tue 7/10/18 15 HR manager
Risk prioritize 44 days Wed 7/11/18 Mon 9/10/18
Analyzing each of 5 days Wed 7/11/18 Tue 7/17/18 16 finance
12PROJECT RISK MANAGEMENT
the risks individually manager ,Proje
ct sponsor
Measuring the
level of tolerance for
each risk
4 days Wed 7/18/18 Mon 7/23/18 18 system analyst
Risk ranking 6 days Tue 7/24/18 Tue 7/31/18 19 finance
manager
Contingency
planning 2 days Wed 8/1/18 Thu 8/2/18 20
Project
manager ,Proje
ct sponsor
Setting risk
priority 3 days Fri 8/3/18 Tue 8/7/18 21 system analyst
Addition of
notification for each
new task
4 days Wed 8/8/18 Mon 8/13/18 22 system
developer
Description of risk
factor 6 days Tue 8/14/18 Tue 8/21/18 23 system analyst
Analyzing scope
impact 5 days Wed 8/22/18 Tue 8/28/18 23,24 system
developer
Analyzing
schedule impact 3 days Wed 8/29/18 Fri 8/31/18 25 HR manager
Analyzing
quantity impact 6 days Mon 9/3/18 Mon 9/10/18 26 system analyst
Risk mitigation
planning 23 days Tue 9/11/18 Thu 10/11/18
Allotting
responsible person for
each risk
2 days Tue 9/11/18 Wed 9/12/18 27 system analyst
Developing risk
register 4 days Thu 9/13/18 Tue 9/18/18 29 Project
manager
Regulatory and
compliance issue
identification
3 days Wed 9/19/18 Fri 9/21/18 30 system analyst
Feasibility study 6 days Mon 9/24/18 Mon 10/1/18 31 finance
the risks individually manager ,Proje
ct sponsor
Measuring the
level of tolerance for
each risk
4 days Wed 7/18/18 Mon 7/23/18 18 system analyst
Risk ranking 6 days Tue 7/24/18 Tue 7/31/18 19 finance
manager
Contingency
planning 2 days Wed 8/1/18 Thu 8/2/18 20
Project
manager ,Proje
ct sponsor
Setting risk
priority 3 days Fri 8/3/18 Tue 8/7/18 21 system analyst
Addition of
notification for each
new task
4 days Wed 8/8/18 Mon 8/13/18 22 system
developer
Description of risk
factor 6 days Tue 8/14/18 Tue 8/21/18 23 system analyst
Analyzing scope
impact 5 days Wed 8/22/18 Tue 8/28/18 23,24 system
developer
Analyzing
schedule impact 3 days Wed 8/29/18 Fri 8/31/18 25 HR manager
Analyzing
quantity impact 6 days Mon 9/3/18 Mon 9/10/18 26 system analyst
Risk mitigation
planning 23 days Tue 9/11/18 Thu 10/11/18
Allotting
responsible person for
each risk
2 days Tue 9/11/18 Wed 9/12/18 27 system analyst
Developing risk
register 4 days Thu 9/13/18 Tue 9/18/18 29 Project
manager
Regulatory and
compliance issue
identification
3 days Wed 9/19/18 Fri 9/21/18 30 system analyst
Feasibility study 6 days Mon 9/24/18 Mon 10/1/18 31 finance
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13PROJECT RISK MANAGEMENT
manager
Resource planning 5 days Tue 10/2/18 Mon 10/8/18 32 Project
manager
Security breach
mitigation 3 days Tue 10/9/18 Thu 10/11/18 33 Project sponsor
Risk management
plan closure 9 days Fri 10/12/18 Wed 10/24/18
Final risk
management plan 2 days Fri 10/12/18 Mon 10/15/18 34 HR manager
Action planning 3 days Tue 10/16/18 Thu 10/18/18 36 system analyst
Post ERP
maintenance plan 4 days Fri 10/19/18 Wed 10/24/18 37 system
developer
2.1 Identification of project stakeholders
In order to develop the risk management for ERP failure occurred in a Multinational
company the stakeholders of the projects are also allotted [2]. In order to reduce the work
pressure from the project team members, stakeholders are also allotted for each of the activity
and for this particular risk management plan the associated stakeholders and their responsibilities
are illustrated below:
Resource
Name Type Material
Label Initials Group Max.
Units
Std.
Rate
Ovt.
Rate Cost/Use Accrue
At
Base
Calendar
Project
manager Work P 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
finance
manager Work f 100% $14.00/hr $0.00/hr $0.00 Prorated Standard
HR
manager Work H 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
system
developer Work s 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
manager
Resource planning 5 days Tue 10/2/18 Mon 10/8/18 32 Project
manager
Security breach
mitigation 3 days Tue 10/9/18 Thu 10/11/18 33 Project sponsor
Risk management
plan closure 9 days Fri 10/12/18 Wed 10/24/18
Final risk
management plan 2 days Fri 10/12/18 Mon 10/15/18 34 HR manager
Action planning 3 days Tue 10/16/18 Thu 10/18/18 36 system analyst
Post ERP
maintenance plan 4 days Fri 10/19/18 Wed 10/24/18 37 system
developer
2.1 Identification of project stakeholders
In order to develop the risk management for ERP failure occurred in a Multinational
company the stakeholders of the projects are also allotted [2]. In order to reduce the work
pressure from the project team members, stakeholders are also allotted for each of the activity
and for this particular risk management plan the associated stakeholders and their responsibilities
are illustrated below:
Resource
Name Type Material
Label Initials Group Max.
Units
Std.
Rate
Ovt.
Rate Cost/Use Accrue
At
Base
Calendar
Project
manager Work P 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
finance
manager Work f 100% $14.00/hr $0.00/hr $0.00 Prorated Standard
HR
manager Work H 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
system
developer Work s 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
14PROJECT RISK MANAGEMENT
system
analyst Work s 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
Project
sponsor Work P 100% $20.00/hr $0.00/hr $0.00 Prorated Standard
.
2.2 Defining system boundaries
Lack of license for the software needed to run the application
Improper SLA
Lack of training and development for the new technology application
Improper budgeting and resource allocation
3. Defining project context
The project is based upon an ERP system implementation failure in a multinational
company.
4. Discussing the social benefits of risk exposure
Worker’s protection from accidents
Maintenance of organizational reputation
Protecting business against the unforeseeable
Reduced rate of worker absence
system
analyst Work s 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
Project
sponsor Work P 100% $20.00/hr $0.00/hr $0.00 Prorated Standard
.
2.2 Defining system boundaries
Lack of license for the software needed to run the application
Improper SLA
Lack of training and development for the new technology application
Improper budgeting and resource allocation
3. Defining project context
The project is based upon an ERP system implementation failure in a multinational
company.
4. Discussing the social benefits of risk exposure
Worker’s protection from accidents
Maintenance of organizational reputation
Protecting business against the unforeseeable
Reduced rate of worker absence
15PROJECT RISK MANAGEMENT
5. Usage of FMEA technique to identify, quantify and mitigate the source of
risk
Failure Mode Effects Analysis (FMEA) is referred to as a technique that is widely used
by the business organizations for developing risk management plan. It is expected that wt the
help of this risk management plan all the risks can be easily identified, analyzed and mitigated.
In order to improve any current product, service, layout or even process the most widely used
tool in FMEA. Regardless of the occupation and status that has to determine, FMEA tool can be
used for measuring risks [8]. Besides this approach many other approaches are also available in
terms of design review by failure mode, failure mode, effects and critical analysis. FMEA is a
structured approach that helps to evaluate a process or product for identifying where and how the
approach may fail to meet its objectives. FMEA approach should be applied by the project
manager for developing the risk management plan. It also helps to identify the impact of the risks
and based on that priority matrix is also developed by the project manager. The risk priority
numbers are ranges from 1 to 1000 and the priority measure results are obtained by making
multiplication along with severity, occurrence, detection etc. on the other hand the detection
scale ranges from 1 to 10 [5]. Based on the priority the risks are ranked by the project managers.
Besides the FMEA approach there are certain optional approaches available in the market those
are widely used by the project managers for implementing a secure project risk management
plan. A typical FMEA technique has the ability to create linkage between Control plan, process
map, C-E m=Matrix, SIPOC etc. The rating scale of a Typical FMEA approach is stated in the
below table:
Probability of failure Possible failure rates
Extremely high >=1 and 2
5. Usage of FMEA technique to identify, quantify and mitigate the source of
risk
Failure Mode Effects Analysis (FMEA) is referred to as a technique that is widely used
by the business organizations for developing risk management plan. It is expected that wt the
help of this risk management plan all the risks can be easily identified, analyzed and mitigated.
In order to improve any current product, service, layout or even process the most widely used
tool in FMEA. Regardless of the occupation and status that has to determine, FMEA tool can be
used for measuring risks [8]. Besides this approach many other approaches are also available in
terms of design review by failure mode, failure mode, effects and critical analysis. FMEA is a
structured approach that helps to evaluate a process or product for identifying where and how the
approach may fail to meet its objectives. FMEA approach should be applied by the project
manager for developing the risk management plan. It also helps to identify the impact of the risks
and based on that priority matrix is also developed by the project manager. The risk priority
numbers are ranges from 1 to 1000 and the priority measure results are obtained by making
multiplication along with severity, occurrence, detection etc. on the other hand the detection
scale ranges from 1 to 10 [5]. Based on the priority the risks are ranked by the project managers.
Besides the FMEA approach there are certain optional approaches available in the market those
are widely used by the project managers for implementing a secure project risk management
plan. A typical FMEA technique has the ability to create linkage between Control plan, process
map, C-E m=Matrix, SIPOC etc. The rating scale of a Typical FMEA approach is stated in the
below table:
Probability of failure Possible failure rates
Extremely high >=1 and 2
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16PROJECT RISK MANAGEMENT
Very high 1- 3
Repeated failures 1-8
High 1-20
Moderately high 1-80
Moderate 1-400
Quite low 1-2000
Low 1-15000
Remote 1-150000
Almost impossible <=1-1,500,000
Very high 1- 3
Repeated failures 1-8
High 1-20
Moderately high 1-80
Moderate 1-400
Quite low 1-2000
Low 1-15000
Remote 1-150000
Almost impossible <=1-1,500,000
PROJECT RISK MANAGEMENT 15
With the help of the FMEA technique the ERP failure project based risk management plan can be developed and in the below section the plan has been shown:
Process
Function
Potential
Failure
Mode
Potential
Effect(s) of
Failure
Sev Cla
ss
Potential
Cause(s)/
Mechanism(s)
of Failure
Oc
cur
Current
Process
Controls
Det
ec RPN Recommended
Action(s)
Responsibility
and Target
Completion
Date
Action Results
Actions
Taken
(date)
Sev Oc
c Det RP
N
Risk
identificatio
n
Incorrect
budget
estimation
Revenue
interrupted 2 Wrong
feasibility testing 4
The finance
manager of the
company has
developed a
project
feasibility
study
considering all
the project
resources both
human and
physical to
make
understand
that whether
the project is
successful or
not
4 45 Feasibility test Finance manager
23/4/2018 10/4/2018 7 5 3 0
Risk
Assessment
Improper
resource
managemen
t
Budget and
time
overload
3
Loss in
commercial
revenue
2
Before the
initiation of
the project an
accurate
timeline,
budget plan
and cost for
individual
resource are
allotted.
4 114
Resource
identification and
estimation
Project manager
23/4/2018 14/4/2018 7 4 3 0
Risk
Control
Lack of
training
among the
project team
members
Fail to
consider all
necessary
risk
management
aspects
4
The company
fails to arrange
timely training
and development
program for the
employees who
are working for
the company
4
After hiring
the employees
for the project
team
members,
proper training
and
development
program
should be
arranged.
3 221
Training and
development
program
(Project
manager ) 23/4/2018 5 5 3 20
With the help of the FMEA technique the ERP failure project based risk management plan can be developed and in the below section the plan has been shown:
Process
Function
Potential
Failure
Mode
Potential
Effect(s) of
Failure
Sev Cla
ss
Potential
Cause(s)/
Mechanism(s)
of Failure
Oc
cur
Current
Process
Controls
Det
ec RPN Recommended
Action(s)
Responsibility
and Target
Completion
Date
Action Results
Actions
Taken
(date)
Sev Oc
c Det RP
N
Risk
identificatio
n
Incorrect
budget
estimation
Revenue
interrupted 2 Wrong
feasibility testing 4
The finance
manager of the
company has
developed a
project
feasibility
study
considering all
the project
resources both
human and
physical to
make
understand
that whether
the project is
successful or
not
4 45 Feasibility test Finance manager
23/4/2018 10/4/2018 7 5 3 0
Risk
Assessment
Improper
resource
managemen
t
Budget and
time
overload
3
Loss in
commercial
revenue
2
Before the
initiation of
the project an
accurate
timeline,
budget plan
and cost for
individual
resource are
allotted.
4 114
Resource
identification and
estimation
Project manager
23/4/2018 14/4/2018 7 4 3 0
Risk
Control
Lack of
training
among the
project team
members
Fail to
consider all
necessary
risk
management
aspects
4
The company
fails to arrange
timely training
and development
program for the
employees who
are working for
the company
4
After hiring
the employees
for the project
team
members,
proper training
and
development
program
should be
arranged.
3 221
Training and
development
program
(Project
manager ) 23/4/2018 5 5 3 20
PROJECT RISK MANAGEMENT 16
6. Different risk assessment methods
Besides FMEA technique there are many other techniques that can be used by the project
managers to detect, analyze and mitigate the identified risks. The techniques are as follows:
What –if analysis
Qualitative risk analysis
Development of project checklist
Hazard and operability study (HAZOP)
Decision making tree
7. Presenting risk tolerability criteria
The risk tolerability criteria are similar as to the risk acceptance criteria and the risk
acceptance criteria for this project are as follows:
Profits can be obtained from the risks
Degree of control for the risk
Times until effects are experience
Times in realization of the risks (occurrence of accidents)
6. Different risk assessment methods
Besides FMEA technique there are many other techniques that can be used by the project
managers to detect, analyze and mitigate the identified risks. The techniques are as follows:
What –if analysis
Qualitative risk analysis
Development of project checklist
Hazard and operability study (HAZOP)
Decision making tree
7. Presenting risk tolerability criteria
The risk tolerability criteria are similar as to the risk acceptance criteria and the risk
acceptance criteria for this project are as follows:
Profits can be obtained from the risks
Degree of control for the risk
Times until effects are experience
Times in realization of the risks (occurrence of accidents)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PROJECT RISK MANAGEMENT 17
8. Quantified Tolerability of Risk (ToR) discussion and relevant measures on
ToR table
Figure 1: ToR for framework
(Source: 8)
Risk name Responsible
person
Frequency Impact Mitigation
strategy
Incorrect resource
allocation
Project manager High High At the project
initiation phase the
project manager
should identify the
necessary
8. Quantified Tolerability of Risk (ToR) discussion and relevant measures on
ToR table
Figure 1: ToR for framework
(Source: 8)
Risk name Responsible
person
Frequency Impact Mitigation
strategy
Incorrect resource
allocation
Project manager High High At the project
initiation phase the
project manager
should identify the
necessary
PROJECT RISK MANAGEMENT 18
resources and allot
them in the
necessary phases.
Lack of experts HR manager High Medium Professional
training and
development
program should be
developed to make
the employees
aware of their
responsibilities
and job roles
Budget overload Finance manager Very High High Project budget
should be prepared
at the project
initiation phase
Time overload Sponsor and
project manager
High High For each activity
time should be
estimated by the
project manager
9. Discussion on the findings
From the overall discussion it can be concluded that, the nominated ERP failure project
can be mitigated if proper risk management plan is developed by the responsible project team
resources and allot
them in the
necessary phases.
Lack of experts HR manager High Medium Professional
training and
development
program should be
developed to make
the employees
aware of their
responsibilities
and job roles
Budget overload Finance manager Very High High Project budget
should be prepared
at the project
initiation phase
Time overload Sponsor and
project manager
High High For each activity
time should be
estimated by the
project manager
9. Discussion on the findings
From the overall discussion it can be concluded that, the nominated ERP failure project
can be mitigated if proper risk management plan is developed by the responsible project team
PROJECT RISK MANAGEMENT 19
members. Among different risk management techniques the most suitable technique for
mitigating the ERP implementation project failure risk is FMEA technique, which is illustrated
here. Moreover, it has been determined that in order to resolve any kind of business risks it is
necessary for the executives to develop a risk management pan at the very project initiation
phase. The common phases those are to be followed accordingly include risk identification,
assessment, prioritize and mitigation or control. If all of these phases are followed properly then
the chance of risks are expected to be minimized automatically. However the risk management
plan should be developed based upon the IS0 31000:2009, which is the modified version of
ISO:31000:2004.
members. Among different risk management techniques the most suitable technique for
mitigating the ERP implementation project failure risk is FMEA technique, which is illustrated
here. Moreover, it has been determined that in order to resolve any kind of business risks it is
necessary for the executives to develop a risk management pan at the very project initiation
phase. The common phases those are to be followed accordingly include risk identification,
assessment, prioritize and mitigation or control. If all of these phases are followed properly then
the chance of risks are expected to be minimized automatically. However the risk management
plan should be developed based upon the IS0 31000:2009, which is the modified version of
ISO:31000:2004.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT RISK MANAGEMENT 20
References
[1]. McNeil, A.J., Frey, R. and Embrechts, P.,. Quantitative risk management: Concepts,
techniques and tools. Princeton university press., 2015
[2]. Cagliano, A.C., Grimaldi, S. and Rafele, C.,. Choosing project risk management
techniques. A theoretical framework. Journal of Risk Research, 18(2), pp.232-248., 2015
[3]. Neves, A.A.S., Pinardi, N., Martins, F., Janeiro, J., Samaras, A., Zodiatis, G. and De
Dominicis, M.,. Towards a common oil spill risk assessment framework–adapting ISO 31000
and addressing uncertainties. Journal of environmental management, 159, pp.158-168., 2015
[4]. Marin, J.C., January. Risk Management for Road Safety Based on the ISO 31000.
In ASSE Professional Development Conference and Exposition. American Society of Safety
Engineers., 2017
[5]. Hoffer, E., Shaw, G.B., Senge, P.M. and Drucker, P.F.. Creating a new system model of
managing change based on quality management principles and risk management principles
2. Journal of central banking theory and practice, 4(3), p.94. 2015.
[6]. Dias, A.A.D.S.P.. A more effective audit after COSO ERM 2017 or after ISO 31000:
2009?. Revista Perspectiva Empresarial ISSN: 2389-8194 (En línea), 4(2), pp.73-82., 2017
[7]. Mikes, A. and Kaplan, R.S.,. When one size doesn't fit all: Evolving directions in the
research and practice of enterprise risk management. Journal of Applied Corporate
Finance, 27(1), pp.37-40., 2015
[8]. Horner, C.A. and Wilmshurst, T.D.,. STAKEHOLDER ENGAGEMENT AND THE
GRI: IMPLICATIONS FOR EFFECTIVE RISK MANAGEMENT. CORPORATE
OWNERSHIP & CONTROL, p.210. 2016
References
[1]. McNeil, A.J., Frey, R. and Embrechts, P.,. Quantitative risk management: Concepts,
techniques and tools. Princeton university press., 2015
[2]. Cagliano, A.C., Grimaldi, S. and Rafele, C.,. Choosing project risk management
techniques. A theoretical framework. Journal of Risk Research, 18(2), pp.232-248., 2015
[3]. Neves, A.A.S., Pinardi, N., Martins, F., Janeiro, J., Samaras, A., Zodiatis, G. and De
Dominicis, M.,. Towards a common oil spill risk assessment framework–adapting ISO 31000
and addressing uncertainties. Journal of environmental management, 159, pp.158-168., 2015
[4]. Marin, J.C., January. Risk Management for Road Safety Based on the ISO 31000.
In ASSE Professional Development Conference and Exposition. American Society of Safety
Engineers., 2017
[5]. Hoffer, E., Shaw, G.B., Senge, P.M. and Drucker, P.F.. Creating a new system model of
managing change based on quality management principles and risk management principles
2. Journal of central banking theory and practice, 4(3), p.94. 2015.
[6]. Dias, A.A.D.S.P.. A more effective audit after COSO ERM 2017 or after ISO 31000:
2009?. Revista Perspectiva Empresarial ISSN: 2389-8194 (En línea), 4(2), pp.73-82., 2017
[7]. Mikes, A. and Kaplan, R.S.,. When one size doesn't fit all: Evolving directions in the
research and practice of enterprise risk management. Journal of Applied Corporate
Finance, 27(1), pp.37-40., 2015
[8]. Horner, C.A. and Wilmshurst, T.D.,. STAKEHOLDER ENGAGEMENT AND THE
GRI: IMPLICATIONS FOR EFFECTIVE RISK MANAGEMENT. CORPORATE
OWNERSHIP & CONTROL, p.210. 2016
PROJECT RISK MANAGEMENT 21
[9]. Gaudenzi, B., Confente, I. and Manuj, I., , September. HOW MANAGERS PERCEIVE
AND ASSESS SUPPLY CHAIN RISKS? EMPIRICAL RESULTS FROM A SAMPLE OF
EUROPEAN ORGANIZATIONS. In 8th Annual Conference of the EuroMed Academy of
Business.,2015
[10]. Wessels, J.S. and Sadler, E.,. Risk management in higher education: An open distance
learning perspective. Southern African Business Review, 19(2), pp.74-98., 2015
[11]. Shad, M.K. and Lai, F.W.,. A conceptual framework for enterprise risk management
performance measure through economic value added. Global Business and Management
Research, 7(2), p.1., 2015
[12]. Griraa, J., Bedard, Y., Roche, S. and Devillersb, R.,. Towards a Collaborative Knowledge
Discovery System for Enriching Semantic Information about Risks of Geospatial Data
misuse. Uncertainty Modelling and Quality Control for Spatial Data, p.233., 2015
[13]. Mayer, N. and De Smet, D.,. Systematic Literature Review and ISO Standards analysis to
Integrate IT Governance and Security Risk Management. International Journal for Infonomics
(IJI), 10(1), pp.1255-1263.,2017
[14]. Bromiley, P., McShane, M., Nair, A. and Rustambekov, E. Enterprise risk management:
Review, critique, and research directions. Long range planning, 48(4), pp.265-276., 2015
[15]. Ho, W., Zheng, T., Yildiz, H. and Talluri, S. Supply chain risk management: a literature
review. International Journal of Production Research, 53(16), pp.5031-5069.,2015
[16]. Pritchard, C.L. and PMP, P.R.,. Risk management: concepts and guidance. CRC Press.
2014
[17]. Hopkinson, M.,. The project risk maturity model: Measuring and improving risk
management capability. Routledge. 2017
[9]. Gaudenzi, B., Confente, I. and Manuj, I., , September. HOW MANAGERS PERCEIVE
AND ASSESS SUPPLY CHAIN RISKS? EMPIRICAL RESULTS FROM A SAMPLE OF
EUROPEAN ORGANIZATIONS. In 8th Annual Conference of the EuroMed Academy of
Business.,2015
[10]. Wessels, J.S. and Sadler, E.,. Risk management in higher education: An open distance
learning perspective. Southern African Business Review, 19(2), pp.74-98., 2015
[11]. Shad, M.K. and Lai, F.W.,. A conceptual framework for enterprise risk management
performance measure through economic value added. Global Business and Management
Research, 7(2), p.1., 2015
[12]. Griraa, J., Bedard, Y., Roche, S. and Devillersb, R.,. Towards a Collaborative Knowledge
Discovery System for Enriching Semantic Information about Risks of Geospatial Data
misuse. Uncertainty Modelling and Quality Control for Spatial Data, p.233., 2015
[13]. Mayer, N. and De Smet, D.,. Systematic Literature Review and ISO Standards analysis to
Integrate IT Governance and Security Risk Management. International Journal for Infonomics
(IJI), 10(1), pp.1255-1263.,2017
[14]. Bromiley, P., McShane, M., Nair, A. and Rustambekov, E. Enterprise risk management:
Review, critique, and research directions. Long range planning, 48(4), pp.265-276., 2015
[15]. Ho, W., Zheng, T., Yildiz, H. and Talluri, S. Supply chain risk management: a literature
review. International Journal of Production Research, 53(16), pp.5031-5069.,2015
[16]. Pritchard, C.L. and PMP, P.R.,. Risk management: concepts and guidance. CRC Press.
2014
[17]. Hopkinson, M.,. The project risk maturity model: Measuring and improving risk
management capability. Routledge. 2017
PROJECT RISK MANAGEMENT 22
[18]. Glendon, A.I., Clarke, S. and McKenna, E. Human safety and risk management. Crc
Press. 2016
[19]. Lam, J. Enterprise risk management: from incentives to controls. John Wiley & Sons.,
2014
[20]. Burtonshaw-Gunn, S.A. Risk and financial management in construction. Routledge.,
2017
[21]. Falkner, E.M. and Hiebl, M.R. Risk management in SMEs: a systematic review of
available evidence. The Journal of Risk Finance, 16(2), pp.122-144. 2015
[22]. Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P.,. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340., 2014
[23]. Hoffmann, R., Kiedrowicz, M. and Stanik, J. Risk management system as the basic
paradigm of the information security management system in an organization. In MATEC Web of
Conferences (Vol. 76, p. 04010). EDP Sciences., 2016
[24]. Ibáñez, A.J.P., Bernal, J.M.M., de Diego, M.J.C. and Sánchez, F.J.A. Expert system for
predicting buildings service life under ISO 31000 standard. Application in architectural
heritage. Journal of Cultural Heritage, 18, pp.209-218., 2016
[25]. Dias, A.A.D.S.P. A more effective audit after COSO ERM 2017 or after ISO 31000:
2009?. Revista Perspectiva Empresarial ISSN: 2389-8194 (En línea), 4(2), pp.73-82.,2017
[26]. de Oliveira, U.R., Marins, F.A.S., Rocha, H.M. and Salomon, V.A.P. The ISO 31000
standard in supply chain risk management. Journal of Cleaner Production, 151, pp.616-
633.,2017
[18]. Glendon, A.I., Clarke, S. and McKenna, E. Human safety and risk management. Crc
Press. 2016
[19]. Lam, J. Enterprise risk management: from incentives to controls. John Wiley & Sons.,
2014
[20]. Burtonshaw-Gunn, S.A. Risk and financial management in construction. Routledge.,
2017
[21]. Falkner, E.M. and Hiebl, M.R. Risk management in SMEs: a systematic review of
available evidence. The Journal of Risk Finance, 16(2), pp.122-144. 2015
[22]. Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P.,. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340., 2014
[23]. Hoffmann, R., Kiedrowicz, M. and Stanik, J. Risk management system as the basic
paradigm of the information security management system in an organization. In MATEC Web of
Conferences (Vol. 76, p. 04010). EDP Sciences., 2016
[24]. Ibáñez, A.J.P., Bernal, J.M.M., de Diego, M.J.C. and Sánchez, F.J.A. Expert system for
predicting buildings service life under ISO 31000 standard. Application in architectural
heritage. Journal of Cultural Heritage, 18, pp.209-218., 2016
[25]. Dias, A.A.D.S.P. A more effective audit after COSO ERM 2017 or after ISO 31000:
2009?. Revista Perspectiva Empresarial ISSN: 2389-8194 (En línea), 4(2), pp.73-82.,2017
[26]. de Oliveira, U.R., Marins, F.A.S., Rocha, H.M. and Salomon, V.A.P. The ISO 31000
standard in supply chain risk management. Journal of Cleaner Production, 151, pp.616-
633.,2017
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PROJECT RISK MANAGEMENT 23
[27]. Chemweno, P., Pintelon, L., Van Horenbeek, A. and Muchiri, P. Development of a risk
assessment selection methodology for asset maintenance Griraa, J., Bedard, Y., Roche, S. and
Devillersb, R., 2015. Towards a Collaborative Knowledge Discovery System for Enriching
Semantic Information about Risks of Geospatial Data misuse. Uncertainty Modelling and
Quality Control for Spatial Data, p.233. Journal of Production Economics, 170, pp.663-676.
2015.
[28]. Griraa, J., Bedard, Y., Roche, S. and Devillersb, R. Towards a Collaborative Knowledge
Discovery System for Enriching Semantic Information about Risks of Geospatial Data
misuse. Uncertainty Modelling and Quality Control for Spatial Data, p.233., 2015
[29]. Horner, C.A. and Wilmshurst, T.D. STAKEHOLDER ENGAGEMENT AND THE GRI:
IMPLICATIONS FOR EFFECTIVE RISK MANAGEMENT. CORPORATE OWNERSHIP &
CONTROL, p.210, 2016.
[30]. Shad, M.K. and Lai, F.W. A conceptual framework for enterprise risk management
performance measure through economic value added. Global Business and Management
Research, 7(2), p.1., 2015
[31]. Gaudenzi, B., Confente, I. and Manuj, I., , September. HOW MANAGERS PERCEIVE
AND ASSESS SUPPLY CHAIN RISKS? EMPIRICAL RESULTS FROM A SAMPLE OF
EUROPEAN ORGANIZATIONS. In 8th Annual Conference of the EuroMed Academy of
Business., 2015.
[32]. Mayer, N. and De Smet, D. Systematic Literature Review and ISO Standards analysis to
Integrate IT Governance and Security Risk Management. International Journal for Infonomics
(IJI), 10(1), pp.1255-1263., 2017
[27]. Chemweno, P., Pintelon, L., Van Horenbeek, A. and Muchiri, P. Development of a risk
assessment selection methodology for asset maintenance Griraa, J., Bedard, Y., Roche, S. and
Devillersb, R., 2015. Towards a Collaborative Knowledge Discovery System for Enriching
Semantic Information about Risks of Geospatial Data misuse. Uncertainty Modelling and
Quality Control for Spatial Data, p.233. Journal of Production Economics, 170, pp.663-676.
2015.
[28]. Griraa, J., Bedard, Y., Roche, S. and Devillersb, R. Towards a Collaborative Knowledge
Discovery System for Enriching Semantic Information about Risks of Geospatial Data
misuse. Uncertainty Modelling and Quality Control for Spatial Data, p.233., 2015
[29]. Horner, C.A. and Wilmshurst, T.D. STAKEHOLDER ENGAGEMENT AND THE GRI:
IMPLICATIONS FOR EFFECTIVE RISK MANAGEMENT. CORPORATE OWNERSHIP &
CONTROL, p.210, 2016.
[30]. Shad, M.K. and Lai, F.W. A conceptual framework for enterprise risk management
performance measure through economic value added. Global Business and Management
Research, 7(2), p.1., 2015
[31]. Gaudenzi, B., Confente, I. and Manuj, I., , September. HOW MANAGERS PERCEIVE
AND ASSESS SUPPLY CHAIN RISKS? EMPIRICAL RESULTS FROM A SAMPLE OF
EUROPEAN ORGANIZATIONS. In 8th Annual Conference of the EuroMed Academy of
Business., 2015.
[32]. Mayer, N. and De Smet, D. Systematic Literature Review and ISO Standards analysis to
Integrate IT Governance and Security Risk Management. International Journal for Infonomics
(IJI), 10(1), pp.1255-1263., 2017
PROJECT RISK MANAGEMENT 24
Appendices
Appendix 1: Risk Identification Checklist
Checklist
Project name:
Location:
Date:
No CHECKLIST YES/NO
1 Are the project boundaries and other components are
correctly identified?
2 Did the FMEA technique used to determine the risk rate is
appropriate?
3 Did the rest of the mentioned risk management methods
can be used for this particular scenario?
4 Did the security and privacy approaches undertook to
recommend ERP failures are appreciable?
Appendix 2: Risk Register
Risk
name
Respons
ible
person
Frequency Impact Mitigation
strategy
Likeli
hood
conseq
uence
Risk
level
Incorrect
resource
allocation
Project
manager
High High At the project
initiation phase the
project manager
5 1 M
Appendices
Appendix 1: Risk Identification Checklist
Checklist
Project name:
Location:
Date:
No CHECKLIST YES/NO
1 Are the project boundaries and other components are
correctly identified?
2 Did the FMEA technique used to determine the risk rate is
appropriate?
3 Did the rest of the mentioned risk management methods
can be used for this particular scenario?
4 Did the security and privacy approaches undertook to
recommend ERP failures are appreciable?
Appendix 2: Risk Register
Risk
name
Respons
ible
person
Frequency Impact Mitigation
strategy
Likeli
hood
conseq
uence
Risk
level
Incorrect
resource
allocation
Project
manager
High High At the project
initiation phase the
project manager
5 1 M
PROJECT RISK MANAGEMENT 25
should identify the
necessary
resources and allot
them in the
necessary phases.
Lack of
experts
HR
manager
High Medium Professional
training and
development
program should be
developed to make
the employees
aware of their
responsibilities
and job roles
3 5 E
Budget
overload
Finance
manager
Very High High Project budget
should be prepared
at the project
initiation phase
3 3 M
Time
overload
Sponsor
and
project
manager
High High For each activity
time should be
estimated by the
project manager
2 1 L
should identify the
necessary
resources and allot
them in the
necessary phases.
Lack of
experts
HR
manager
High Medium Professional
training and
development
program should be
developed to make
the employees
aware of their
responsibilities
and job roles
3 5 E
Budget
overload
Finance
manager
Very High High Project budget
should be prepared
at the project
initiation phase
3 3 M
Time
overload
Sponsor
and
project
manager
High High For each activity
time should be
estimated by the
project manager
2 1 L
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16PROJECT RISK MANAGEMENT
Appendix 3: FMEA Analysis
Process
Function
Potential
Failure
Mode
Potential
Effect(s) of
Failure
Sev Cla
ss
Potential
Cause(s)/
Mechanism(s) of
Failure
Oc
cur
Current
Process
Controls
Det
ec RPN Recommended
Action(s)
Responsibility
and Target
Completion Date
Action Results
Actions
Taken
(date)
Sev Oc
c Det RP
N
Risk
identificatio
n
Incorrect
budget
estimation
Revenue
interrupted 2 Wrong
feasibility testing 4
The finance
manager of the
company has
developed a
project
feasibility
study
considering all
the project
resources both
human and
physical to
make
understand that
whether the
project is
successful or
not
4 45 Feasibility test Finance manager
23/4/2018 10/4/2018 7 5 3 0
Risk
Assessment
Improper
resource
managemen
t
Budget and
time overload 3
Loss in
commercial
revenue
2
Before the
initiation of the
project an
accurate
timeline,
budget plan
and cost for
individual
resource are
allotted.
4 114
Resource
identification and
estimation
Project manager
23/4/2018 14/4/2018 7 4 3 0
Risk
Control
Lack of
training
among the
project team
members
Fail to
consider all
necessary risk
management
aspects
4
The company
fails to arrange
timely training
and development
program for the
employees who
are working for
the company
4
After hiring the
employees for
the project
team members,
proper training
and
development
program should
be arranged.
3 221
Training and
development
program
(Project manager
) 23/4/2018 5 5 3 20
Appendix 3: FMEA Analysis
Process
Function
Potential
Failure
Mode
Potential
Effect(s) of
Failure
Sev Cla
ss
Potential
Cause(s)/
Mechanism(s) of
Failure
Oc
cur
Current
Process
Controls
Det
ec RPN Recommended
Action(s)
Responsibility
and Target
Completion Date
Action Results
Actions
Taken
(date)
Sev Oc
c Det RP
N
Risk
identificatio
n
Incorrect
budget
estimation
Revenue
interrupted 2 Wrong
feasibility testing 4
The finance
manager of the
company has
developed a
project
feasibility
study
considering all
the project
resources both
human and
physical to
make
understand that
whether the
project is
successful or
not
4 45 Feasibility test Finance manager
23/4/2018 10/4/2018 7 5 3 0
Risk
Assessment
Improper
resource
managemen
t
Budget and
time overload 3
Loss in
commercial
revenue
2
Before the
initiation of the
project an
accurate
timeline,
budget plan
and cost for
individual
resource are
allotted.
4 114
Resource
identification and
estimation
Project manager
23/4/2018 14/4/2018 7 4 3 0
Risk
Control
Lack of
training
among the
project team
members
Fail to
consider all
necessary risk
management
aspects
4
The company
fails to arrange
timely training
and development
program for the
employees who
are working for
the company
4
After hiring the
employees for
the project
team members,
proper training
and
development
program should
be arranged.
3 221
Training and
development
program
(Project manager
) 23/4/2018 5 5 3 20
17PROJECT RISK MANAGEMENT
16PROJECT RISK MANAGEMENT
Appendix 4: Example
Appendix 4: Example
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16PROJECT RISK MANAGEMENT
Appendix 5: Risk treatment table
Risk name Frequency Impact Treatment option Likelihood consequence Preferred
option
Cost
benefit
analysis
Likelihood
after
treatment
Responsible
person
Incorrect
resource
allocation
High High At the project initiation
phase the project
manager should
identify the
necessary resources
and allot them in the
necessary phases.
During project
progress resource
update
5 1 All Accept Project
manager
Lack of
experts
High Medium Professional
training and
3 5 All Accept HR manager
Appendix 5: Risk treatment table
Risk name Frequency Impact Treatment option Likelihood consequence Preferred
option
Cost
benefit
analysis
Likelihood
after
treatment
Responsible
person
Incorrect
resource
allocation
High High At the project initiation
phase the project
manager should
identify the
necessary resources
and allot them in the
necessary phases.
During project
progress resource
update
5 1 All Accept Project
manager
Lack of
experts
High Medium Professional
training and
3 5 All Accept HR manager
17PROJECT RISK MANAGEMENT
development
program should be
developed to make
the employees
aware of their
responsibilities and
job roles
Incentives and
rewards
Budget
overload
Very High High Project budget
should be prepared
at the project
initiation phase
Addition sponsors
and third party
partnership during
3 3 All Accept Finance
manager
development
program should be
developed to make
the employees
aware of their
responsibilities and
job roles
Incentives and
rewards
Budget
overload
Very High High Project budget
should be prepared
at the project
initiation phase
Addition sponsors
and third party
partnership during
3 3 All Accept Finance
manager
18PROJECT RISK MANAGEMENT
progress period
Time overload High High For each activity
time should be
estimated by the
project manager
Hiring more
employees to
divide workload
for minimizing
time
2 1 All Accept Sponsor and
project
manager
progress period
Time overload High High For each activity
time should be
estimated by the
project manager
Hiring more
employees to
divide workload
for minimizing
time
2 1 All Accept Sponsor and
project
manager
1 out of 34
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.