[COMPANY NAME][Company address] PROJECT SCHEDULING AND CONRTOL
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Contents Introduction.........................................................................................................................................1 Approaches to project scheduling and control..................................................................................2 Work Break Down Structure for ‘Personal Trainer’ business....................................................2 Project network diagram................................................................................................................5 Gantt chart.......................................................................................................................................6 Project budgeting.............................................................................................................................6 Critical path.....................................................................................................................................7 Critical chain....................................................................................................................................8 Earned value Analysis.....................................................................................................................8 Agile methodology...........................................................................................................................9 Lean Project Management..............................................................................................................9 Project crashing.............................................................................................................................10 List of Project Deliverables...........................................................................................................10 Recommendations to achieve project success..................................................................................11 Conclusion..........................................................................................................................................11 References..........................................................................................................................................12 Introduction The demand for personal trainers has been increasing at a rapid rate with the increase in health consciousness in Australia. Nowadays, Australian of all shapes, sizes, and ages hire personal coach in order to exercise correctly to keep themselves trim, healthy and fit. The main motive of Personal Trainer business is to spread the word about the physical fitness expertise at health spas, biking, swimming, and running clubs and other athletic outlets. The personal trainer will help Australians to achieve their selected fitness goals by designing an individualized exercise program. The main objective of this report is to design a project schedule for the new selected business named as Personal Trainer. Approaches to project scheduling and control
The project team members have been utilized different project scheduling and control approaches for identifying and sequencing project activities including project duration and cost estimation as shown below: Work Break Down Structure for ‘Personal Trainer’ business WorkBreakdownStructure(WBS)referstothedivisionofcomplexprojectsinto manageable and simpler activities/tasks(Kukhnavets, 2017). It provides a strong base for all project management work including work project scheduling, resource allocation, planning, effort, and cost estimation. Figure-1 Work Breakdown Structure of the Personal training project Description of work break down the structure The WBS dictionary is used for describing each element or activity of work break down structure: Persona l Trainer Equipm ent First aid kit Defibrill ators Training equipm ent Adverti sing materia l Pamphl ets Talk to custom ers Facebo ok Ads Training Progra ms Area to train Parks Space at the park SIS4021 5 Certific ate IV Workin g with Childre n Check First Aid Certific ate
WBS level WBS IDWBS NameWBS descriptionPWS/SOW mapping 11Certificatein fitness In order to work as a personal trainer in Australia, it is necessary to get a SIS40215 certificate IV in fitness. The personal trainers need to spend 1 year on complete this course("Become A Personal Trainer - Cert IV in Fitness", 2019). 22EquipmentIn this phase, the project team will buy equipment’s that will be required to start a new business. 32.1First aid kitThe first aid kit should include Analgesic, antibiotic ointment, decongestant, instant cold packs, latex gloves, thermometer, antiseptic, etc. that will help the personal trainer to manage an emergency or critical situations. 32.2DefibrillatorsA defibrillatorshould be purchased as it will help people to beat the heartbreak from cardiac arrest. 32.3Training equipment’s Personal trainers will require quality music systems, stop watches, form rollers, suspension trainer, weighted belts,clothes,towels,waterdispensersandother equipment’s. 23Advertising material In this phase, different types of advertising strategies andthematerialwillbeusedbybusiness partners/owners to raise awareness among citizens in Australia about the unique fitness services that they will offer to them. 33.1PamphletsIn this phase, brochures and pamphlet will be designed1
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
and distributed in the consumer segment. 33.2Talkto customers Personaltrainerswoulddirectlycommunicatewith customerstospreadawarenessregardingfitness services. 1 33.3Facebook adsFacebook ads will be designed for promoting the new business at a global level. 1 24Training program The training team should be designed based on the key requirements of business stakeholders. 2 25Area to trainIn this phase, the project team will identify a suitable area where training can be provided to customers. 1 35.1ParksTheprojectteamshouldidentifyparkswhichare suitable to provide personal training services. 1 35.2Spaceatthe park The project team will identify the appropriate space at the selected park during this phase. 1 26FirstAid Certificate Personal trainers must get first aid certificate before starts working as a personal trainer. 27Working with children check For personal trainers, “working with children check” is a key requirement as they will be volunteering child- related work during training sessions. Table:1 WBS dictionary Project network diagram The pictorial representation of the project schedule has been represented by Project Network Diagram. The project team can use the project network diagram for planning and tracking the project through the project life cycle (from beginning to finish).
Figure-2 Personal Trainer Project Network In the above diagram, task ID: 1 and ID: 3 are critical path tasks represented in red colour, whereas task ID: 2, ID: 4, ID: 5, ID: 6 and ID: 7 are non-critical path tasks represented in blue colour. The network diagram presents the dependencies and critical path of the project in a graphical way(Gojko Nikolic, 2015). Based on the WBS and Project network we have come up with a schedule that illustrates how much time will be required to achieve project deliverables(Wale, 2015).
Gantt chart Figure:3 Personal Trainer Gantt Chart Schedule The Gantt chart represents all identified project activities/tasks in a logical and sequenced fashion along with associated time. Project budgeting A top-down forecasting approach has been adopted due to the small nature of the project. The project team has decided to use an approach similar to apportion method because most of the information which they are required about the cost and time is already available. Apportion method is suitable when projects are following past projects in costs and feature. With the use of this method, the project team can estimate project cost quickly with reasonable accuracy and little effort(Razdan & Pirgal, 2017). BudgetCost AUD Res: SIS40215 Certificate IV3390
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Res: Training Equipment10, 000.00 Res: Working with children85.00 Res: First Aid129.00 Res: Adverting300.00 Res: Total cost13, 904.00 Table: 2 project cost Critical path The project team members have utilized the Critical Path Method (CPM) in order to determine project duration by thoroughly analysing the sequence of tasks. The critical path can be defined as the longest path which has the least amount of float or slack(L, 2016). Figure:4 Critical paths for Personal Trainer project
In the above diagram, the critical path for the Trainer Project has been represented in red colour. It has been found that project team members can take approximately 370 days for starting up their business as personal trainers. The project team members can calculate the early finish/start and late finish/start date of the project for each project activity. Critical project activities can be tracked by the project team members in an effective way with the use of critical path method. In the above diagram, the critical path provides a more realistic view to the project team about the deadline which will further help the team to track whether the project deliverables are accomplished or not. Critical chain The critical chain can be defined as the longest chain which has a direct impact on the overall project duration(Shurrab, 2015). The project team members have analysed critical chain to understand how tasks could impact on project duration. Critical chain method is an effective projectschedulingtechniquewhichallowsprojectteammemberstoconsiderlimited resources during project schedule development. The critical chain for personal trainer project has been depicted below: Figure: 5 Critical chains for Personal Trainer Project
The designed critical chain is similar to the critical path as there is no constraint of resource availability. A huge amount of contingency has been added by the critical chain to the project in buffers for protecting due-date project performance. Poorly synchronized integration and bad multitasking waste the contingency which can be avoided through critical chain where the project team will try to understand all aspects of the project schedule. Moreover, the project team would use buffer management rather than earned value management for assessingproject performance in an effective way. In other words, the adoption of the critical value chain will be helpful for the project team as it ensures optimal resourcing, contingency and fit of time for the project schedule. Earned valueManagement system The project team can use EVMS (Earned Value Management System) for answering three important questions related to the project such as “where are we going?”, “where are we now?” and “where have we been?”.Earned value analysis will be performed by the project team members in order to calculate the planned value, earned value and actual cost for each project task. By using this approach, they can easily measure how much work has been done at a given point of time(Urgilés, Claver & Sebastián, 2019). It would be easy for the project team to analyse the variance in the budget and schedule as the project proceeds with the use of earned value analysisWilson & Carmenza, 2015).It has been recommended to the project team to use Microsoft Project software for calculating earned value efficiently and accurately. Agile methodology The project team will adopt agile project management methodology for project schedule as it provides the best way to communicate project scope, schedule, and cost with other project stakeholders(M.A., 2019. Best practices of agile project methodology are:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
1.Capturing and sequencing activities during the project initiation phase and releasing phase 2.Assigning resources to each agile sprint 3.Use agile metrics for estimating the effort and measure project progress 4.Verify the schedule and critical path 5.Conduct a schedule risk analysis 6.Update project schedule 7.Maintain baseline schedule Lean Project Management Lean project management will be adopted by the project team to reduce project timelines and reduce project cost. Best principles of lean project management for the project are listed below: 1.The project team members should not purchase extra training equipment’s to avoid the risk of cost overruns. 2.They should avoid the overproduction of pamphlets to eliminate the waste related to overproduction(Modi, 2014). 3.According to the project plan, the project team will buy training equipment’s and getting first aid certificate simultaneously to reduce overall project time. Project crashing The project team will use the project crashing technique for compressing the overall project duration(Nasseri & Aulin, 2016). In the project crashing process, project duration reduces with increases in project cost. The project team members can add extra resources to critical path tasks in order to reduce the overall project duration(Vyas, 2013). They can perform project crashing by executing below listed 4 steps:
1.Identify critical tasks and normal critical path 2.Calculate crash cost per week for all tasks by using below mentioned formula 3.Identify & select activity on the critical path with the smallest minimum cost/week. After that crashing project at the desired deadline. 4.Repeat step 2 until the critical path is the longest path. List of Project Deliverables Work Break Down Structure (WBS) Project Network Diagram Gantt Chart List of recommendations Critical path Critical chain Recommendations to achieve project success 1.The project team has been recommended to adopt agile, lean project management, CPM, critical chain analysis, project crashing and earned value analysis techniques to avoid critical issues associated with time and cost overruns. 2.User involvement, executive management support, hardworking and focused team members, smaller project milestones, proper planning, realistic expectations and clear statement of requirements are key project success factors for all types of industries. However, the project team should focus on these factors to successfully start their business as a personal trainer within the estimated cost and budget(Radujković & Sjekavica, 2017).
3.The project team has been recommended to adopt a Monte Carlo Simulation approach to prevent critical risks related to project delay and project failure. With the use of this approach, it would be easy for team members to understand the root causes which contribute to the occurrence of specific risk(Razaque, 2012). 4.Moreover, the project team members have been recommended to attend all periodic project status meetings to determine whether formal project milestones have been achieved or not by the scheduled date(Agarwal & Kumar, 2012). Conclusion This report summarized various project scheduling and control techniques such as agile, lean project management, CPM, critical chain analysis, project crashing and earned value analysis which can be used by project team members for successful project scheduling and control. In this report, all project team members have been provided with a few recommendations which will help them to achieve project success by reducing the occurrence of cost and time related risks. References Agarwal, V., & Kumar, D. (2012). An Activity Analysis of Project Scheduling Problem: A Case Stud.International Journal Of Latest Trends In Engineering And Technology (IJLTET),1(4). Retrieved from http://www.ijltet.org/wp-content/uploads/2013/01/11.pdf Become A Personal Trainer - Cert IV in Fitness. (2019). Retrieved from https://www.fitcollege.edu.au/BecomeaPersonalTrainer/BecomeAPersonalTrainerCertIV inFitness-493/ Gojko Nikolic, G. (2015). Creating a Network Planning Diagram: Men's Trousers Production Project.Journal Of Textile Science & Engineering,05(02). doi: 10.4172/2165- 8064.1000193 Kukhnavets, P. (2017). Work Breakdown Structure (WBS) in Project Management. Retrieved from https://blog.ganttpro.com/en/how-to-create-a-work-breakdown-structure-wbs-with- project-planning-templates/ L, J. (2016). PROJECT MANAGEMENT: A SYSTEM APPROACH TO PLANNING, IMPLEMENTATION, MONITORING, AND EVALUATION.International Journal Of Advanced Academic Research | Social & Management Sciences. Retrieved from https://ijaar.org/articles/Volume2-Number11/Social-Management-Sciences/ijaar-sms- v2n10-oct16-p15.pdf
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
M.A., A. (2019). Impact of Marketing Strategy on Business Performance A Study of Selected Small and Medium Enterprises (Smes) In Oluyole Local Government, Ibadan, Nigeria. IOSR Journal Of Business And Management (IOSR-JBM),11(4). Retrieved from http://www.iosrjournals.org/iosr-jbm/papers/Vol11-issue4/I01145966.pdf Modi, D. (2014). Lean Thinking: Reduction of Waste, Lead Time, Cost through Lean Manufacturing Tools and Technique.International Journal Of Emerging Technology And Advanced Engineering,4(3). Retrieved from https://pdfs.semanticscholar.org/8f25/5854b85da898d368c79ae2b8daeed9a65e16.pdf Nasseri, H., & Aulin, R. (2016). Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman.Journal Of Construction In Developing Countries,2121(2). Retrieved from http://web.usm.my/jcdc/vol21_2_2016/JCDC %2021(2)_Art%201(1-20).pdf Radujković, M., & Sjekavica, M. (2017). Project Management Success Factors.Procedia Engineering,196, 607-615. doi: 10.1016/j.proeng.2017.08.048 Razaque, A. (2012). Fostering Project Scheduling and Controlling Risk Management. International Journal Of Business And Social Science,3(14). Retrieved from https://arxiv.org/ftp/arxiv/papers/1210/1210.2021.pdf Razdan, S., & Pirgal, M. (2017). Application of Critical Path Method for Project Scheduling – A Case Study. Retrieved from https://www.researchgate.net/publication/315045237_Application_of_Critical_Path_Met hod_for_Project_Scheduling_-_A_Case_Study Shurrab, M. (2015). Traditional Critical Path Method versus Critical Chain Project Management: A Comparative View.International Journal Of Economics & Management Sciences,04(09). doi: 10.4172/2162-6359.1000292 Urgilés, P., Claver, J., & Sebastián, M. (2019). Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast.Complexity,2019, 1-11. doi: 10.1155/2019/3190830 Vyas, R. (2013). Scheduling Project Management Using Crashing CPM Network to get Project completed on Time.International Journal Of Engineering Research & Technology (IJERT),2(2). Retrieved from https://www.ijert.org/research/scheduling- project-management-using-crashing-cpm-network-to-get-project-completed-on-time- IJERTV2IS2272.pdf Wale, P. (2015). Planning and Scheduling of Project using Microsoft Project (Case Study of a building in India).IOSR Journal Of Mechanical And Civil Engineering (IOSR-JMCE), 12(3). Retrieved from http://www.iosrjournals.org/iosr-jmce/papers/vol12-issue3/Version-3/I012335763.pdf Wilson, N., & Carmenza, L. (2015). Agile Methodology to Develop Architecture of Information and Knowledge in Organizations (MADAIKE).International Journal Of Machine Learning And Computing,5(2), 153-159. doi: 10.7763/ijmlc.2015.v5.500