PPMP20007 Assessment Item 2 Coversheet Group Members: Student Name: Student Id: Student Name: Student Id: Student Name: Student Id: Student Name: Student Id:
Prototype User Acceptance Testing_1
Part A Question 1 The MS Project file is submitted along with the module as ‘PartAQ1.mpp’ Question 2 i.a. The duration of task ‘5.3. Prototype User Acceptance Testing’ has changedfrom 10 days to 5 days due to doubling or resource ‘TE’.This change in duration and because of resource has changed the overall durationform 200 days to 184 days, it could happen because the activity ‘5.3. PrototypeUser Acceptance Testing’ is in critical path of the project and any change induration either way can impact the overall schedule duration.b. Always the duration of a task cannot be decreased by simply adding theresources, because there are various other criteria which guide the reduction ofduration, like the relations with the successor and predecessor activities and thetechnical requirement of the activity. Suppose, if the activity is like ‘curing ofconcrete structure works needs 3 days to take any additional load above it’ so ifwe keep on increasing the resources to cure it 24 hours still any external loadingcannot be done before 3 days. So always by increasing the resources the durationof the activity cannot be decreased.ii. The MS Project file is submitted along with the module as ‘PartAQ2.mpp’Question 3 i.The resource over allocation issues can be resolved either by adding additionalresources or by delaying the activities. But the issue remains where the activitiesare in critical path the duration cannot be increased so the only options remain isto add extra resources.But there is also another option available is to distribute the available resourcewithin the float available in the activity so that the overall duration does nt getsimpacted but the resources also gets leveled with in the available +ve floatduration by applying below checks
Prototype User Acceptance Testing_2
ii.Yes, there will be the impact of any resource constraints on the overall projectduration, but as long as the resource constraints are in the critical path activities.Otherwise the resources may get leveled within the available float in the activity.The project duration as per PartAQ2.mpp was 184 days, but after the resourceshave been leveled within the available slack, the overall duration got reduced andsimply shown that the resources ‘Project Manager’ and ‘Business Analyst’ areover loaded, which needs leveling. They are now currently shown as red coloredas shown below:Question 4 To, The Director of Mobile App Development,
Prototype User Acceptance Testing_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Analysis of Unique Framework Usefulness
|7
|1598
|84

COIT12208- ICT Project Management
|7
|1529
|20

COIT12208 IT Project Management Assignment
|9
|1150
|59

COIT12208 - ICT Project Management
|8
|1185
|111

NIT1203 Introduction to Project Management
|3
|740
|209

Ms-Project Practical - PDF
|12
|928
|310