PRM701 PROJECT MANAGEMENT PRINCIPLES: - ASSESSMENT TASK 3 PRM701 Project Management Principles Assessment Task 3 Name of the Student Name of the University Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PRM701 PROJECT MANAGEMENT PRINCIPLES: - ASSESSMENT TASK 3 Question Explain how quality control measures on projects can reduce the number of defects and inefficiencies along with improving project process, outputs and objectives? Answer Quality can be defined the requirement of the project that is necessary and the processes those could allow the project manager to accomplish them. Quality control measures can allow the compliance of the suitability and the necessity of being used for meeting the objectives and goals of the project. Quality control measure is an approach that can allow the project manage the activities and operations those are necessary for the management and assurance of the project quality. Quality control measures can be helpful in the development of the strategies those could be helpful in managing the project constraints and output standard. Some of the beneficial aspects those could be availed through the effective and efficient implementation of the quality control measures: Project Scope Achievement: It can be helpful in facilitating the business that can be helpful in attaining the objectives those have been developed during the planning and development of the strategies at the prior of the project execution. It emphasizes on the application of the resources, equipment, and techniques those can be helpful in leading the project manager to ensure the achievements of the reliability and stability of the project delivery and output. Satisfaction of the Consumers: the proper and efficient execution of the quality control measures can lead the project delivery towards the satisfactory level that is capable of fulfilling the needs and requirements of the consumers. This is one of the major criteria for a successful project that the delivered output and production is capable of assuring that the PRM701 Assessment Task 32
PRM701 PROJECT MANAGEMENT PRINCIPLES: - ASSESSMENT TASK 3 needs and requirements of the consumers are being fulfilled and that can be attained through the application of the quality control measure. Implementation of the process improvement and best practices: Quality control measures allows the project manager to accomplish the activities those could lead the project andthenewimplementationtowardstheimprovement,enhancementintheoutput, consistency management, expenditure reduction, and enhanced production in association with the accomplishment of the project constraints. Production enhancement: It includes the techniques, tools, and trainings those could lead to the application of the best approaches towards the accomplishment of the objectives and goals of the project. The quality control measures allow the project to be productive and more beneficial in terms of finance and customer satisfaction. Less rework: The quality control measures emphasizes on the evaluation of the quality and production being made before introducing to the consumers and assuring that the developed project and production would be capable of meeting the needs and requirements of the consumers. Hence, the developed product or service will be less bounced back if already quality has been evaluated for the first time. Internal Communication Enhancement: The internal communication is one of the major factor for the successful delivery and execution of the project considering needs and requirements of the users and the quality control measure allows the project stakeholders to communicate in far better and efficient manner. The above benefits explains how the implementation of the quality control measures can lead to the reduction in the defects and thus, enhancing the efficiency of the project being delivered within the project. Question PRM701 Assessment Task 33
PRM701 PROJECT MANAGEMENT PRINCIPLES: - ASSESSMENT TASK 3 Compareandcontrastanytwodifferentprojecttime(schedule) managementtechniques/tools that enableprojects to be plannedand managed throughout the lifecycle. Answer Gantt chart and Schedule Network Analysis are two tools those could be utilized for the demonstration of the activities and their schedule of the activities throughout the project lifecycle. Gantt chart is a bar graphical representation of the timeline with the activities in horizontal view. The activities of the entire project lifecycle is demonstrated as bar and the length of the bar represents the estimated time that will be consumed by the particular activity. The Gantt chart also describesthedependencyoftheactivitiesoverotheractivitiesandsimilarconnectionis demonstrated through the arrow clarifying the start to start, start to finish, finish to finish, and finish to start relationship with the activities. The sequence of the bars can be I sequential form or it could run in parallel with other activity considering the time consumed by that certain activity. There are available tools those could be utilized for demonstrating the better and effective Gantt chart with proper and attractive visual representation. The bars start from the expected timeline and ends to the expected time that is the estimated time for the accomplishment of the activity. The comparisons can be made in between the actual time taken and the planned schedule of the project in much better and efficient manner. Schedule network analysis is another technique that is helpful in the graphical representation of the schedule that will be needed for the accomplishment of the expected activities throughout the project lifecycle. It a single page demonstration of the schedule network demonstrating from left to right across the page and all the logical interrelationships between the activities and work’s element. The project activities is demonstrated in the chronological order starting from the initiation phase of the project to the project closure of the project including all the intermediate activities between them. It is also known as network diagram and critical path can also be demonstrated through this network diagram describing the minimum time and essential activities those are most considerable PRM701 Assessment Task 34
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
PRM701 PROJECT MANAGEMENT PRINCIPLES: - ASSESSMENT TASK 3 for the accomplishment of the project in efficient and effective manner. A analysis can also be driven using this graphical representation that can be helpful in determining the current progress of the report and what are the changes necessary for the development and growth of the project. PRM701 Assessment Task 35
PRM701 PROJECT MANAGEMENT PRINCIPLES: - ASSESSMENT TASK 3 References Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge. Boud, D., Cohen, R. and Sampson, J. eds., 2014.Peer learning in higher education: Learning from and with each other. Routledge. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge. Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn. JOSEPH. PHILLIPS, P.M.P., CBAP, I. and PMP, C., 2018.PMP PROJECT MANAGEMENT PROFESSIONAL STUDY GUIDE. McGraw-Hill Education. Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Meredith, J.R., Shafer, S.M., Mantel Jr, S.J. and Sutton, M.M., 2016. Project management in practice. Wiley Global Education. Schwalbe, K., 2015. Information technology project management. Cengage Learning. Turner, R., 2016.Gower handbook of project management. Routledge. Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons. Walker, A., 2015. Project management in construction. John Wiley & Sons. PRM701 Assessment Task 36