logo

Recipe App Agile Project Reflection Assignment

   

Added on  2022-09-06

14 Pages3372 Words21 Views
Recipe app
Agile Project - Reflection
4/10/2020

Table of Contents
Journal Entries............................................................................................................................2
Sprint 1...................................................................................................................................2
Sprint 2...................................................................................................................................2
Sprint 3...................................................................................................................................3
Sprint 4...................................................................................................................................4
Sprint 5...................................................................................................................................5
Sprint 6...................................................................................................................................5
Sprint 7...................................................................................................................................6
Social, Legal, and Ethical Issues................................................................................................7
Harm Test...............................................................................................................................7
Legality Test...........................................................................................................................7
Colleague Test........................................................................................................................8
Reflection on Agile Processes....................................................................................................8
Activity 1................................................................................................................................8
Activity 2................................................................................................................................9
Activity 3..............................................................................................................................10
References................................................................................................................................12
1

Journal Entries
Sprint 1
Sprint number: 1 Start date: 10-04-2020
User story: As a user, I want an automated
system for managing the nutritious recipe
so that I can keep track of my nutritional
in-take on daily basis.
Sprint Plan reference: Link
Goal:
1. Gather all nutritional ingredients of a
diet.
Estimated effort: 1 weeks Actual effort: 1 weeks
Deliverable: Working set of the product Acceptance criteria:
Customer rating – 4.5 or
above
Number of critical
defects - Zero
Review: Link
Reflection: The team could complete the sprint in the determined timeframe and the
working set of the product was accepted. The team could improve on the
communication and collaboration as a unit so that the overall quality and productivity
levels are improved (Brechner, 2015).
Sprint 2
Sprint number: 2 Start date: 27-04-2020
User story: As a user, I want automated Sprint Plan reference: Link
2

management automated suggestions for
adding nutritional vegetables so that I may
improve my daily diet.
Goal: Implement a page of suggestions.
Estimated effort: 3 weeks Actual effort: 2.5 weeks
Deliverable: Working set of the product Acceptance criteria:
Customer rating – 4.5 or
above
Number of critical
defects - Zero
Review: Link
Reflection: The team succeeded in completing the sprint requirements and their
implementation with the improvements from the previous sprint in less than the
estimated timeframe. The team can introduce the automated testing tool for carrying
out regression tests.
Sprint 3
Sprint number: 3 Start date: 12-05-2020
User story: As a user, I want to view the
feedback on my performance to that I may
make required changes in my nutritional
diet .
Sprint Plan reference: Link
Goal: Implement page for adding friends.
Implement page for getting suggestion /
feedbacks.
Estimated effort: 3 weeks Actual effort: 3 weeks
Deliverable: Working set of the product Acceptance criteria:
Customer rating – 4.5 or
Review: Link