Equipment days 12/11/15 1/14/16 days Development
Engineer[300%],
Industrial Engineer[400%],
Design Engineer 2,
Development Engineer 2,
Industrial Engineer 2
3. The changes have modified network and critical path and they have been shown below,
Gantt chart
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Red Zuma Project_Part B278.01 daysFri 1/2/15 Fri 1/15/16
1 1 Market Analysis 25 days Fri 1/2/15 Wed 2/4/15
2 2 Product Design 20.77 daysThu 2/5/15 Wed 3/4/15
3 3 Manufacturing Study 22.5 days Wed 3/4/15 Fri 4/3/15
4 4 Product Design Selection 10 days Fri 4/3/15 Thu 4/16/15
5 5 Detailed Marketing Plan 15 days Thu 4/16/15 Wed 5/6/15
6 6 Manufacturing Process 46.67 daysThu 4/16/15 Thu 6/18/15
7 7 Detailed Product Design 45 days Thu 6/18/15 Wed 8/19/15
8 8 Build Prototypes 25 days Thu 7/30/15 Wed 9/2/15
9 9 Lab Test Prototypes 10.71 daysWed 9/2/15 Thu 9/17/15
10 10 Field Test Prototypes 15 days Wed 9/2/15 Wed 9/23/15
11 11 Finalized Product Design 20 days Wed 9/23/15 Tue 10/20/15
12 12 Final Manufacturing Process6.8 days Tue 10/13/15 Thu 10/22/15
13 13 Order Components 5.2 days Tue 10/20/15 Wed 11/4/15
14 14 Order Production Equipment7 days Thu 10/22/15 Mon 11/2/15
15 15 Install Production Equipment23.27 daysFri 12/11/15 Thu 1/14/16
16 16 Celebrate 1 day Thu 1/14/16 Fri 1/15/16
Marketing Specialist[400%]
Marketing Specialist,Design Engineer[400%],Development Engineer[200%],Industrial