This presentation provides an overview of the project to relocate Burnaby Hospital. It includes information on the current hospital, the need for relocation, project objectives, roles and responsibilities of the project team, scope of the project, work breakdown structure, schedule, key performance measurements, and health and safety considerations.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
RELOCATE
BURNABY HOSPITAL
BUILDING OF THE NEW HOSPITAL AT THE CORNER OF WILLINGDON AND
CANADA WAY
BURNABY HOSPITAL
BUILDING OF THE NEW HOSPITAL AT THE CORNER OF WILLINGDON AND
CANADA WAY
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
OVERVIEW OF THE BURNABY HOSPITAL
• The Burnaby Hospital is considered as a
large community hospital and has been
serving customers for a couple of years.
• The hospital provides different forms of
healthcare services that includes surgical,
tertiary, obstetric, psychiatry and medical
facilities to different problems in relation to
patient care. The hospital also provides
emergency care services and it has been
further reported that the hospital
organization serves nearly 80,000 patients
on an annual basis.
• The Burnaby Hospital is considered as a
large community hospital and has been
serving customers for a couple of years.
• The hospital provides different forms of
healthcare services that includes surgical,
tertiary, obstetric, psychiatry and medical
facilities to different problems in relation to
patient care. The hospital also provides
emergency care services and it has been
further reported that the hospital
organization serves nearly 80,000 patients
on an annual basis.
PROJECT FOR RELOCATING THE BURNABY
HOSPITAL
• The government had reached to a
conclusion that it would be highly
expensive to renovate the Burnaby
Hospital.
• A new hospital should be built at the
corner of Canada Way and Willingdon.
• This would be highly needed for
delivering the best forms of healthcare
facilities to the patients and thus
developing better relationship with the
customers.
HOSPITAL
• The government had reached to a
conclusion that it would be highly
expensive to renovate the Burnaby
Hospital.
• A new hospital should be built at the
corner of Canada Way and Willingdon.
• This would be highly needed for
delivering the best forms of healthcare
facilities to the patients and thus
developing better relationship with the
customers.
PROJECT OBJECTIVE
• Determining of the hospital site, surveying and preparing for the construction
work.
• Constructing the best form of infrastructure based on providing the best form
of healthcare facilities.
• Purchasing and installation of high quality medical equipment
• Procuring high quality hospital furnishings, office equipment and other non-
medical facilities.
• Designing the hospital infrastructure within the proper estimated budget and
within appropriate deadlines.
• Determining of the hospital site, surveying and preparing for the construction
work.
• Constructing the best form of infrastructure based on providing the best form
of healthcare facilities.
• Purchasing and installation of high quality medical equipment
• Procuring high quality hospital furnishings, office equipment and other non-
medical facilities.
• Designing the hospital infrastructure within the proper estimated budget and
within appropriate deadlines.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ROLES AND RESPONSIBILITIES OF THE
PROJECT TEAM
Team Members Roles and Responsibilities
Project Sponsors The Project Sponsors are at the responsibility of scrutinizing the requirements
of the entire project and look into the developmental aspects. They would
then be presenting the project for the relocation and construction of the
Burnaby Hospital in order to provide with financial help and progress through
the project based on the available resources.
Project Owners The project owners are mostly to be treated as the head of the business unit
who would be bearing the responsibility of the project including all the
successful implementation of the project and even the issues occurring.
Project Director The project director would be responsible for the management of the entire
project at a more strategic level where the project needs to be handled at a
much more perceived perception.
Project Manager The project Manager would be at the overall charge of the entire project
throughout the planning and the execution of the relocation and construction
of the project for Burnaby Hospital.
Contractors The general project Contractors are at the responsibility of the daily oversight
for the site of the construction for the Burnaby Hospital and at the same time,
would be responsible for the management of the people hired as the traders
and the vendors.
Project Management Team These would be the people who would have all the responsibilities of
conducting the progression of the project with individual roles to play and
handle the project as per the specific skills every individual team member is
capable of.
PROJECT TEAM
Team Members Roles and Responsibilities
Project Sponsors The Project Sponsors are at the responsibility of scrutinizing the requirements
of the entire project and look into the developmental aspects. They would
then be presenting the project for the relocation and construction of the
Burnaby Hospital in order to provide with financial help and progress through
the project based on the available resources.
Project Owners The project owners are mostly to be treated as the head of the business unit
who would be bearing the responsibility of the project including all the
successful implementation of the project and even the issues occurring.
Project Director The project director would be responsible for the management of the entire
project at a more strategic level where the project needs to be handled at a
much more perceived perception.
Project Manager The project Manager would be at the overall charge of the entire project
throughout the planning and the execution of the relocation and construction
of the project for Burnaby Hospital.
Contractors The general project Contractors are at the responsibility of the daily oversight
for the site of the construction for the Burnaby Hospital and at the same time,
would be responsible for the management of the people hired as the traders
and the vendors.
Project Management Team These would be the people who would have all the responsibilities of
conducting the progression of the project with individual roles to play and
handle the project as per the specific skills every individual team member is
capable of.
SCOPE OF THE PROJECT
• Building of a new hospital at a new site situated at Willingdon and Canada Way
• Upgrading of hospital surroundings and supporting infrastructure such as
sewer, water, gas and electricity
• Purchasing of new medical equipment and installing them
• Purchasing of new furniture, office equipment such as computers and
advanced medical infrastructure
• Acquisition of construction site, choosing of the contractors for the supply of
goods and bringing them within the site.
• Building of a new hospital at a new site situated at Willingdon and Canada Way
• Upgrading of hospital surroundings and supporting infrastructure such as
sewer, water, gas and electricity
• Purchasing of new medical equipment and installing them
• Purchasing of new furniture, office equipment such as computers and
advanced medical infrastructure
• Acquisition of construction site, choosing of the contractors for the supply of
goods and bringing them within the site.
WORK BREAKDOWN STRUCTURE (WBS)
Scenario of Construction of
Burnaby Hospital
Start Project Signing of Agreement and
choosing of hospital site
Preparing a team
meeting with the
different higher
officials
Discussing about
land acquisition
matters
Preparing an initial
document based on
court approval
Approval from the
court
Setting of tender
Acquiring proper
bids
Getting the proper
construction
contractor
Hiring of contractors
Preparing of Project Plan
and Hospital Layout Plan
Preparing of Initial
Project Plan
Preparing of
Financial Plan
Approval of Project
Plan and Financial
Plan
Designing the
Hospital Layout Plan
Approval of Hospital
Layout Plan
Preparing a List of
Equipment required
for Construction work
Preparing for a
Public Awareness
Campaign
Determination of
Certain Risks
Foundation Layout and
Bringing of Construction
Materials
Choosing of proper
supplier of raw
materials
Procuring the raw
materials
Laying out of
foundation of the
site
Informing the local
administration
Bringing of
construction
vehicles and
equipment
Closing the
surrounding area
Laying the materials
Final check over the
construction area
Implementation of
Construction Work
Cleaning of
construction area
Boring of Tunnel
Traffic management
Groundwater
monitoring
Designing integrated
systems and
architectural finishes
Performing
geotechnical review
Reviewing over the
final work done
Property acquisition
Installing of Medical
Equipment and final
Project Sign-off
Preparing the list of
items
Procuring the
medical equipment
Fitting the
equipment
Testing of the
equipment
Survey of the
hospital
Performing
geological
assessment
Making of final
payments
Implementation of
security systems
End Project
Scenario of Construction of
Burnaby Hospital
Start Project Signing of Agreement and
choosing of hospital site
Preparing a team
meeting with the
different higher
officials
Discussing about
land acquisition
matters
Preparing an initial
document based on
court approval
Approval from the
court
Setting of tender
Acquiring proper
bids
Getting the proper
construction
contractor
Hiring of contractors
Preparing of Project Plan
and Hospital Layout Plan
Preparing of Initial
Project Plan
Preparing of
Financial Plan
Approval of Project
Plan and Financial
Plan
Designing the
Hospital Layout Plan
Approval of Hospital
Layout Plan
Preparing a List of
Equipment required
for Construction work
Preparing for a
Public Awareness
Campaign
Determination of
Certain Risks
Foundation Layout and
Bringing of Construction
Materials
Choosing of proper
supplier of raw
materials
Procuring the raw
materials
Laying out of
foundation of the
site
Informing the local
administration
Bringing of
construction
vehicles and
equipment
Closing the
surrounding area
Laying the materials
Final check over the
construction area
Implementation of
Construction Work
Cleaning of
construction area
Boring of Tunnel
Traffic management
Groundwater
monitoring
Designing integrated
systems and
architectural finishes
Performing
geotechnical review
Reviewing over the
final work done
Property acquisition
Installing of Medical
Equipment and final
Project Sign-off
Preparing the list of
items
Procuring the
medical equipment
Fitting the
equipment
Testing of the
equipment
Survey of the
hospital
Performing
geological
assessment
Making of final
payments
Implementation of
security systems
End Project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
SCHEDULE OF THE PROJECT
ID Outline
Number
Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
0 0 Scenario of Construction of
Burnaby Hospital
1360
days
Mon
24-06-19
Fri
06-09-24
$1,575,800.00
1 1 Start Project 0 days Mon 24-06-19Mon 24-06-19 $0.00
2 2 Signing of Agreement and
choosing of hospital site
49 days Mon
24-06-19
Thu
29-08-19
$92,800.00
3 2.1 Preparing a team meeting with
the different higher officials
8 days Mon
24-06-19
Wed
03-07-19
1 Government of
Canada,Healthcare
Department,Hospital
$25,600.00
4 2.2 Discussing about land
acquisition matters
11 days Thu
04-07-19
Thu
18-07-19
3 Government of
Canada,Healthcare
Department,Hospital
$0.00
5 2.3 Preparing an initial document
based on court approval
6 days Fri
19-07-19
Fri
26-07-19
4 Project
Manager
$19,200.00
6 2.4 Approval from the court 0 days Fri 26-07-19Fri 26-07-195 $0.00
7 2.5 Setting of tender 5 days Mon 29-07-19Fri 02-08-196 Project Manager $16,000.00
8 2.6 Acquiring proper bids 10 days Mon 05-08-19Fri 16-08-197 Project Manager $32,000.00
9 2.7 Getting the proper
construction contractor
3 days Mon
19-08-19
Wed
21-08-19
8 $0.00
10 2.8 Hiring of contractors 6 days Thu 22-08-19Thu 29-08-199 $0.00
11 3 Preparing of Project Plan and
Hospital Layout Plan
32 days Fri
30-08-19
Mon
14-10-19
$176,800.00
12 3.1 Preparing of Initial Project
Plan
8 days Fri
30-08-19
Tue
10-09-19
10 Project
Manager
$25,600.00
13 3.2 Preparing of Financial Plan 7 days Fri 30-08-19Mon 09-09-1910 Project Sponsor $16,800.00
14 3.3 Approval of Project Plan and
Financial Plan
0 days Tue
10-09-19
Tue
10-09-19
12,13 Hospital
Management
Team
$0.00
15 3.4 Designing the Hospital Layout
Plan
16 days Fri
30-08-19
Fri
20-09-19
10 Construction
Manager,Project
Manager
$76,800.00
16 3.5 Approval of Hospital Layout
Plan
0 days Fri
20-09-19
Fri
20-09-19
15,14 $0.00
17 3.6 Preparing a List of Equipment
required for Construction
work
4 days Mon
23-09-19
Thu
26-09-19
16 Construction
Manager,Project
Manager
$19,200.00
18 3.7 Preparing for a Public
Awareness Campaign
5 days Fri
27-09-19
Thu
03-10-19
17 Project
Manager
$16,000.00
19 3.8 Determination of Certain Risks7 days Fri 04-10-19Mon 14-10-1918 Project Manager $22,400.00
20 4 Foundation Layout and
Bringing of Construction
Materials
30 days Tue
15-10-19
Mon
25-11-19
$63,200.00
21 4.1 Choosing of proper supplier
of raw materials
6 days Tue
15-10-19
Tue
22-10-19
19 Project
Manager
$19,200.00
22 4.2 Procuring the raw materials 4 days Wed 23-10-19Mon 28-10-1921 Construction Materials[1]$8,000.00
23 4.3 Laying out of foundation of
the site
7 days Tue
29-10-19
Wed
06-11-19
22 Construction
Manager
$11,200.00
24 4.4 Informing the local
administration
2 days Thu
07-11-19
Fri
08-11-19
23 $0.00
25 4.5 Bringing of construction
vehicles and equipment
7 days Mon
11-11-19
Tue
19-11-19
24 Hospital
Equipment[1]
$12,000.00
26 4.6 Closing the surrounding area 3 days Wed 20-11-19Fri 22-11-1925 $0.00
27 4.7 Laying the materials 4 days Wed 20-11-19Mon 25-11-1925 Project Manager $12,800.00
28 4.8 Final check over the
construction area
0 days Mon
25-11-19
Mon
25-11-19
27 $0.00
29 5 Implementation of
Construction Work
1114
days
Tue
26-11-19
Fri
01-03-24
$995,200.00
30 5.1 Cleaning of construction area 17 days Tue 26-11-19Wed 18-12-1926,27 Labours $13,600.00
31 5.2 Boring of Tunnel 39 days Thu 19-12-19Tue 11-02-2030 Labours $31,200.00
32 5.3 Traffic management 15 days Wed 12-02-20Tue 03-03-2031 Labours $12,000.00
33 5.4 Groundwater monitoring 35 days Wed 04-03-20Tue 21-04-2032 Construction Manager,Labours$84,000.00
34 5.5 Designing integrated systems
and architectural finishes
938 days Wed
22-04-20
Fri
24-11-23
33 Labours $750,400.00
35 5.6 Performing geotechnical
review
65 days Mon
27-11-23
Fri
23-02-24
34 Construction
Manager
$104,000.00
36 5.7 Reviewing over the final work
done
0 days Fri
23-02-24
Fri
23-02-24
35 $0.00
37 5.8 Property acquisition 5 days Mon 26-02-24Fri 01-03-2436 $0.00
38 6 Installing of Medical
Equipment and final Project
Sign-off
135 days Mon
04-03-24
Fri
06-09-24
$247,800.00
39 6.1 Preparing the list of items 8 days Mon 04-03-24Wed 13-03-2437 Project Manager $25,600.00
40 6.2 Procuring the medical
equipment
19 days Thu
14-03-24
Tue
09-04-24
39 Hospital
Equipment[1]
$12,000.00
41 6.3 Fitting the equipment 30 days Wed 10-04-24Tue 21-05-2440 Labours $24,000.00
42 6.4 Testing of the equipment 15 days Wed 22-05-24Tue 11-06-2441 Labours $12,000.00
43 6.5 Survey of the hospital 19 days Wed 12-06-24Mon 08-07-2442 Project Manager $60,800.00
44 6.6 Performing geological
assessment
14 days Tue
09-07-24
Fri
26-07-24
43 Construction
Manager
$22,400.00
45 6.7 Making of final payments 5 days Mon 29-07-24Fri 02-08-2444 Project Manager $16,000.00
46 6.8 Implementation of security
systems
25 days Mon
05-08-24
Fri
06-09-24
45 Security
Specialists,Security
Systems[1]
$75,000.00
47 7 End Project 0 days Fri 06-09-24Fri 06-09-2446 $0.00
24-06
Government of Canada,Healthcare Department,Hospital Management Team,Project Manager
Government of Canada,Healthcare Department,Hospital Management Team
Project Manager
26-07
Project Manager
Project Manager
Project Manager
Project Sponsor
10-09
Construction Manager,Project Manager
20-09
Construction Manager,Project Manager
Project Manager
Project Manager
Project Manager
Construction Materials[1]
Construction Manager
Hospital Equipment[1]
Project Manager
25-11
Labours
Labours
Labours
Construction Manager,Labours
Labours
Construction Manager
23-02
Project Manager
Hospital Equipment[1]
Labours
Labours
Project Manager
Construction Manager
Project Manager
Security Specialists,Security Systems[1]
06-09
02-06 21-07 08-09 27-10 15-12 02-02 22-03 10-05 28-06 16-08 04-10 22-11 10-01 28-02 18-04 06-06 25-07 12-09 31-10 19-12 06-02 27-03 15-05 03-07 21-08 09-10 27-11 15-01 05-03 23-04 11-06 30-07 17-09 05-11 24-12 11-02 31-03 19-05 07-07 25-08 13-10 01-12
11 April 21 July 01 November 11 February 21 May 01 September 11 December 21 March 01 July 11 October 21 January 01 May 11 August 21 November 01 March 11 June 21 September 01 January 11 April 21 July 01 November
ID Outline
Number
Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost
0 0 Scenario of Construction of
Burnaby Hospital
1360
days
Mon
24-06-19
Fri
06-09-24
$1,575,800.00
1 1 Start Project 0 days Mon 24-06-19Mon 24-06-19 $0.00
2 2 Signing of Agreement and
choosing of hospital site
49 days Mon
24-06-19
Thu
29-08-19
$92,800.00
3 2.1 Preparing a team meeting with
the different higher officials
8 days Mon
24-06-19
Wed
03-07-19
1 Government of
Canada,Healthcare
Department,Hospital
$25,600.00
4 2.2 Discussing about land
acquisition matters
11 days Thu
04-07-19
Thu
18-07-19
3 Government of
Canada,Healthcare
Department,Hospital
$0.00
5 2.3 Preparing an initial document
based on court approval
6 days Fri
19-07-19
Fri
26-07-19
4 Project
Manager
$19,200.00
6 2.4 Approval from the court 0 days Fri 26-07-19Fri 26-07-195 $0.00
7 2.5 Setting of tender 5 days Mon 29-07-19Fri 02-08-196 Project Manager $16,000.00
8 2.6 Acquiring proper bids 10 days Mon 05-08-19Fri 16-08-197 Project Manager $32,000.00
9 2.7 Getting the proper
construction contractor
3 days Mon
19-08-19
Wed
21-08-19
8 $0.00
10 2.8 Hiring of contractors 6 days Thu 22-08-19Thu 29-08-199 $0.00
11 3 Preparing of Project Plan and
Hospital Layout Plan
32 days Fri
30-08-19
Mon
14-10-19
$176,800.00
12 3.1 Preparing of Initial Project
Plan
8 days Fri
30-08-19
Tue
10-09-19
10 Project
Manager
$25,600.00
13 3.2 Preparing of Financial Plan 7 days Fri 30-08-19Mon 09-09-1910 Project Sponsor $16,800.00
14 3.3 Approval of Project Plan and
Financial Plan
0 days Tue
10-09-19
Tue
10-09-19
12,13 Hospital
Management
Team
$0.00
15 3.4 Designing the Hospital Layout
Plan
16 days Fri
30-08-19
Fri
20-09-19
10 Construction
Manager,Project
Manager
$76,800.00
16 3.5 Approval of Hospital Layout
Plan
0 days Fri
20-09-19
Fri
20-09-19
15,14 $0.00
17 3.6 Preparing a List of Equipment
required for Construction
work
4 days Mon
23-09-19
Thu
26-09-19
16 Construction
Manager,Project
Manager
$19,200.00
18 3.7 Preparing for a Public
Awareness Campaign
5 days Fri
27-09-19
Thu
03-10-19
17 Project
Manager
$16,000.00
19 3.8 Determination of Certain Risks7 days Fri 04-10-19Mon 14-10-1918 Project Manager $22,400.00
20 4 Foundation Layout and
Bringing of Construction
Materials
30 days Tue
15-10-19
Mon
25-11-19
$63,200.00
21 4.1 Choosing of proper supplier
of raw materials
6 days Tue
15-10-19
Tue
22-10-19
19 Project
Manager
$19,200.00
22 4.2 Procuring the raw materials 4 days Wed 23-10-19Mon 28-10-1921 Construction Materials[1]$8,000.00
23 4.3 Laying out of foundation of
the site
7 days Tue
29-10-19
Wed
06-11-19
22 Construction
Manager
$11,200.00
24 4.4 Informing the local
administration
2 days Thu
07-11-19
Fri
08-11-19
23 $0.00
25 4.5 Bringing of construction
vehicles and equipment
7 days Mon
11-11-19
Tue
19-11-19
24 Hospital
Equipment[1]
$12,000.00
26 4.6 Closing the surrounding area 3 days Wed 20-11-19Fri 22-11-1925 $0.00
27 4.7 Laying the materials 4 days Wed 20-11-19Mon 25-11-1925 Project Manager $12,800.00
28 4.8 Final check over the
construction area
0 days Mon
25-11-19
Mon
25-11-19
27 $0.00
29 5 Implementation of
Construction Work
1114
days
Tue
26-11-19
Fri
01-03-24
$995,200.00
30 5.1 Cleaning of construction area 17 days Tue 26-11-19Wed 18-12-1926,27 Labours $13,600.00
31 5.2 Boring of Tunnel 39 days Thu 19-12-19Tue 11-02-2030 Labours $31,200.00
32 5.3 Traffic management 15 days Wed 12-02-20Tue 03-03-2031 Labours $12,000.00
33 5.4 Groundwater monitoring 35 days Wed 04-03-20Tue 21-04-2032 Construction Manager,Labours$84,000.00
34 5.5 Designing integrated systems
and architectural finishes
938 days Wed
22-04-20
Fri
24-11-23
33 Labours $750,400.00
35 5.6 Performing geotechnical
review
65 days Mon
27-11-23
Fri
23-02-24
34 Construction
Manager
$104,000.00
36 5.7 Reviewing over the final work
done
0 days Fri
23-02-24
Fri
23-02-24
35 $0.00
37 5.8 Property acquisition 5 days Mon 26-02-24Fri 01-03-2436 $0.00
38 6 Installing of Medical
Equipment and final Project
Sign-off
135 days Mon
04-03-24
Fri
06-09-24
$247,800.00
39 6.1 Preparing the list of items 8 days Mon 04-03-24Wed 13-03-2437 Project Manager $25,600.00
40 6.2 Procuring the medical
equipment
19 days Thu
14-03-24
Tue
09-04-24
39 Hospital
Equipment[1]
$12,000.00
41 6.3 Fitting the equipment 30 days Wed 10-04-24Tue 21-05-2440 Labours $24,000.00
42 6.4 Testing of the equipment 15 days Wed 22-05-24Tue 11-06-2441 Labours $12,000.00
43 6.5 Survey of the hospital 19 days Wed 12-06-24Mon 08-07-2442 Project Manager $60,800.00
44 6.6 Performing geological
assessment
14 days Tue
09-07-24
Fri
26-07-24
43 Construction
Manager
$22,400.00
45 6.7 Making of final payments 5 days Mon 29-07-24Fri 02-08-2444 Project Manager $16,000.00
46 6.8 Implementation of security
systems
25 days Mon
05-08-24
Fri
06-09-24
45 Security
Specialists,Security
Systems[1]
$75,000.00
47 7 End Project 0 days Fri 06-09-24Fri 06-09-2446 $0.00
24-06
Government of Canada,Healthcare Department,Hospital Management Team,Project Manager
Government of Canada,Healthcare Department,Hospital Management Team
Project Manager
26-07
Project Manager
Project Manager
Project Manager
Project Sponsor
10-09
Construction Manager,Project Manager
20-09
Construction Manager,Project Manager
Project Manager
Project Manager
Project Manager
Construction Materials[1]
Construction Manager
Hospital Equipment[1]
Project Manager
25-11
Labours
Labours
Labours
Construction Manager,Labours
Labours
Construction Manager
23-02
Project Manager
Hospital Equipment[1]
Labours
Labours
Project Manager
Construction Manager
Project Manager
Security Specialists,Security Systems[1]
06-09
02-06 21-07 08-09 27-10 15-12 02-02 22-03 10-05 28-06 16-08 04-10 22-11 10-01 28-02 18-04 06-06 25-07 12-09 31-10 19-12 06-02 27-03 15-05 03-07 21-08 09-10 27-11 15-01 05-03 23-04 11-06 30-07 17-09 05-11 24-12 11-02 31-03 19-05 07-07 25-08 13-10 01-12
11 April 21 July 01 November 11 February 21 May 01 September 11 December 21 March 01 July 11 October 21 January 01 May 11 August 21 November 01 March 11 June 21 September 01 January 11 April 21 July 01 November
KEY PERFORMANCE MEASUREMENTS (KPMS)
• Safety Checklists
• Performance evaluation of Project Team
• Duration of the Project
• Risks mitigation success rate
• Cost management
• Usage of the cost contingency
• Safety Checklists
• Performance evaluation of Project Team
• Duration of the Project
• Risks mitigation success rate
• Cost management
• Usage of the cost contingency
WORK ACTIVITY
• Preparing a team meeting with the
different higher officials
• Discussing about land acquisition
matters
• Preparing an initial document based
on court approval
• Approval from the court
• Setting of tenders
• Acquiring proper bids
• Getting the proper construction
contractor
• Hiring of contractors
• Preparing of Initial Project Plan
• Preparing of Financial Plan
• Bringing of construction
vehicles and equipment
• Closing the surrounding area
• Laying the materials
• Final check over the
construction area
• Cleaning of construction area
• Boring of Tunnel
• Traffic management
• Groundwater monitoring
• Designing integrated systems
and architectural finishes
• Performing geotechnical review
• Approval of Project Plan and
Financial Plan
• Designing the Hospital Layout
Plan
• Approval of Hospital Layout Plan
• Preparing a List of Equipment
required for Construction work
• Preparing for a Public Awareness
Campaign
• Determination of Certain Risks
• Choosing of proper supplier of
raw materials
• Procuring the raw materials
• Laying out of foundation of the
site
• Informing the local
administration
• Reviewing over the final work done
• Property acquisition
• Preparing the list of items
• Procuring the medical equipment
• Fitting the equipment
• Testing of the equipment
• Survey of the hospital
• Performing geological assessment
• Making of final payments
• Implementation of security systems
• Preparing a team meeting with the
different higher officials
• Discussing about land acquisition
matters
• Preparing an initial document based
on court approval
• Approval from the court
• Setting of tenders
• Acquiring proper bids
• Getting the proper construction
contractor
• Hiring of contractors
• Preparing of Initial Project Plan
• Preparing of Financial Plan
• Bringing of construction
vehicles and equipment
• Closing the surrounding area
• Laying the materials
• Final check over the
construction area
• Cleaning of construction area
• Boring of Tunnel
• Traffic management
• Groundwater monitoring
• Designing integrated systems
and architectural finishes
• Performing geotechnical review
• Approval of Project Plan and
Financial Plan
• Designing the Hospital Layout
Plan
• Approval of Hospital Layout Plan
• Preparing a List of Equipment
required for Construction work
• Preparing for a Public Awareness
Campaign
• Determination of Certain Risks
• Choosing of proper supplier of
raw materials
• Procuring the raw materials
• Laying out of foundation of the
site
• Informing the local
administration
• Reviewing over the final work done
• Property acquisition
• Preparing the list of items
• Procuring the medical equipment
• Fitting the equipment
• Testing of the equipment
• Survey of the hospital
• Performing geological assessment
• Making of final payments
• Implementation of security systems
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
OTHER ISSUES
• Health and Safety Considerations
• It may occur that the area or the site chosen for the construction is not
feasible for the patients that are to be admitted to the hospital. It may
also occur that the people in responsibility of the construction might be
not effective with cleaning the construction site, which again can cause
health hazards to the overall health of the patients admitted to the
hospital.
• Health and Safety Considerations
• It may occur that the area or the site chosen for the construction is not
feasible for the patients that are to be admitted to the hospital. It may
also occur that the people in responsibility of the construction might be
not effective with cleaning the construction site, which again can cause
health hazards to the overall health of the patients admitted to the
hospital.
THANK
YOU
YOU
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.