The project is based on proposing the designing aspects of renovating the server room for a company. The renovation phase of the server room would include several aspects based on planning, preparing a financial plan for the project, procuring of technical items and developing the renovation over the project. Each of the items described within the Gantt chart would be strictly followed by the project manager in order to complete the phases of the project. The project also defines the cost estimation for the project. Based on defining each of the aspects of the project, the project would be completed in proper time frame and would lead to success for the company.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
Renovation of the Server room within a Company
Name of the Student
Name of the University
Author note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
Executive Summary
The project is based on proposing the designing aspects of renovating the server room for a company.
The renovation phase of the server room would include several aspects based on planning, preparing a
financial plan for the project, procuring of technical items and developing the renovation over the
project. Each of the items described within the Gantt chart would be strictly followed by the project
manager in order to complete the phases of the project. The project also defines the cost estimation for
the project. Based on defining each of the aspects of the project, the project would be completed in
proper time frame and would lead to success for the company.
Document Page
2RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
Table of Contents
1. Outline of the Project..............................................................................................................................3
2. Requirements of the Project....................................................................................................................3
3. Envisaged Project Team Members..........................................................................................................4
4. Development of Project Plan...................................................................................................................5
4.1 Project Scope.....................................................................................................................................5
4.1.1 Work Breakdown Structure (WBS)..............................................................................................5
4.2 Time Estimation of Project.................................................................................................................5
4.3 Resource needs for Project................................................................................................................5
4.4 Gantt chart and Network Diagram.....................................................................................................6
4.5 Estimation of Cost..............................................................................................................................8
4.6 Plan Quality.......................................................................................................................................8
4.7 Stakeholder Analysis..........................................................................................................................9
4.8 Plan Communications........................................................................................................................9
4.9 Plan Project Risks Management......................................................................................................11
4.10 Plan Project Deployment...............................................................................................................11
5. Project Sign Off......................................................................................................................................12
6. Post Project Review and Recommendations.........................................................................................13
Bibliography...............................................................................................................................................14
Document Page
3RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
1. Outline of the Project
The local server rooms form a major integral part within every company. Despite of the
movement of IT hardware to different locations such as the cloud or datacentre, there would be many
cases in which the active network devices or stack of servers would be highly useful for the company.
The use of server rooms within the company forms a major critical aspect within any company. The use
of such kind of servers within the company would be highly required for bringing in efficiency of the
work processes. These server rooms are equipped with workstations, routers, large servers and many
other networked devices. This project discusses about the various forms of renovation changes that
would be made within the ABC Company.
The renovation project would incur the use of different forms of techniques that would require
a huge amount of planning. The communication plan, project risks and the project deployment phase
would be defined for the project. Based on the definition for the project, a post project review and
recommendations would be included for the project.
2. Requirements of the Project
The functional requirements that would be required for the project would include:
1. Technical Details – In the technical details, each of the necessities that would be required for
defining of the plan for the project would be defined.
2. Data Manipulation and Processing – In this process, the different forms of data would be
processed. This would help in gaining a clear understanding for the progress of the project.
3. Calculations – The different kind of calculations that would be performed during calculating
the costs of the project would be performed.
The non-functional requirements, which would be required during the project are:
1. Security – With the defining of the security aspects, the security within the server would be
defined during the renovation phase of the project.
2. Reliability – With the renovation of the server rooms, the factors of reliability would need to
be kept in mind. The new servers that would be implemented should be highly reliable in nature.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
3. Performance Requirements – Different factors of performance based on renovating of the
server room would need to be defined. Based on defining of the performance, each of the criteria would
be defined that would be helpful for determining of the performance factors of the renovation phases.
3. Envisaged Project Team Members
The project team members who would be involved with the renovation phase of the project are:
1. Project Manager – The project manager should have skills based on understanding the
requirements described by the owner and thus should discuss with the technical development team
based on designing a plan for renovating the server room.
2. Technical Development Team – The technical development team should be responsible for
designing a technical plan for renovating the entire server room. They would plan the ways in which the
existing servers would be placed in a secure manner and thus the room would be renovated.
3. Quality Assurance Team – After the entire room has been renovated, the quality assurance
team would define plans for checking the quality of the systems.
Document Page
5RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
4. Development of Project Plan
4.1 Project Scope
4.1.1 Work Breakdown Structure (WBS)
Renovation of Server
Room
Start Project Initial planning for the
design
Meeting with the
owners
Preparing the design
of the project plan
Preparing the
financial budget
Approval of the
project plan and
financial budget
Completion of the
Phase
Planning and
Procurement
Procuring of
technical items
Preparing the
technical layout of
server room
Completion of the
Phase
Development of the
Project
Keeping the existing
servers in a proper
place
Development work
of the project
Painting of the new
room
Ensuring quality
check over the
development work
Completion of the
Phase
Project Closure Phase
Signing of
documents
Payment to
stakeholders
Completion of the
Phase
End Project
(Figure 1: The Work Breakdown Structure for the Project)
(Source: Created by author)
4.2 Time Estimation of Project
The renovation project for the server room would be completed in 70 days.
4.3 Resource needs for Project
The different resources that would be required for the project are comprised of human
resources and technical resources that would be required for the project.
The human resources who would be required for the project would include the project sponsor,
project manager, technical development team and quality assurance team. The technical resources that
would be required for the project are servers, workstations, furniture, paints and new technical
equipment.
Document Page
6RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
4.4 Gantt chart and Network Diagram
ID Outline
Number
Task
Mode
Task Name Duration Start Finish
0 0 Renovation of Server
Room
70 days Mon
20-05-19
Fri
23-08-19
1 1 Start Project 0 days Mon 20-05-19 Mon 20-05-19
2 2 Initial planning for
the design
18 days Mon 20-05-19 Wed
12-06-19
3 2.1 Meeting with the
owners
6 days Mon 20-05-19 Mon
27-05-19
4 2.2 Preparing the
design of the
project plan
12 days Tue 28-05-19 Wed
12-06-19
5 2.3 Preparing the
financial budget
8 days Tue 28-05-19 Thu
06-06-19
6 2.4 Approval of the
project plan and
financial budget
0 days Wed 12-06-19 Wed
12-06-19
7 2.5 Completion of the
Phase
0 days Wed 12-06-19 Wed
12-06-19
8 3 Planning and
Procurement
14 days Thu 13-06-19 Tue
02-07-19
9 3.1 Procuring of
technical items
10 days Thu 13-06-19 Wed
26-06-19
10 3.2 Preparing the
technical layout of
server room
14 days Thu 13-06-19 Tue
02-07-19
11 3.3 Completion of the
Phase
0 days Tue 02-07-19 Tue
02-07-19
12 4 Development of the
Project
35 days Wed 03-07-19 Tue
20-08-19
13 4.1 Keeping the
existing servers in
a proper place
3 days Wed 03-07-19 Fri 05-07-19
14 4.2 Development work
of the project
21 days Mon 08-07-19 Mon
05-08-19
15 4.3 Painting of the
new room
6 days Tue 06-08-19 Tue
13-08-19
16 4.4 Ensuring quality
check over the
development work
5 days Wed 14-08-19 Tue
20-08-19
17 4.5 Completion of the
Phase
0 days Tue 20-08-19 Tue
20-08-19
18 5 Project Closure Phase 3 days Wed 21-08-19 Fri 23-08-19
19 5.1 Signing of documents1 day Wed 21-08-19 Wed 21-08-19
20 5.2 Payment to
stakeholders
2 days Thu 22-08-19 Fri 23-08-19
21 5.3 Completion of the
Phase
0 days Fri 23-08-19 Fri 23-08-19
22 6 End Project 0 days Fri 23-08-19 Fri 23-08-19
20-05
Owner
Project Manager,Technical Development Team
Project Sponsor
12-06
12-06
Paint[1],Technical Equipment[1]
Technical Development Team
02-07
Technical Development Team
Technical Development
Painting team
Quality Assuranc
20-08
Project Manager
23-08
23-08
S T M F T S W S T M F
06 May '19 03 Jun '19 01 Jul '19 29 Jul '19 26 Aug '19
(Figure 2: The Gantt chart for the Project)
(Source: Created by author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
(Figure 3: The 1st Phase for the Project)
(Source: Created by author)
(Figure 4: The 2nd Phase for the Project)
(Source: Created by author)
Document Page
8RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
(Figure 5: The 3rd Phase for the Project)
(Source: Created by author)
(Figure 6: The 4th Phase for the Project)
(Source: Created by author)
4.5 Estimation of Cost
The entire cost for the project would be AUD $ 174,800.
4.6 Plan Quality
The plan quality phase of the project would help in developing the quality aspects of the project.
Based on discussing over the plans for the project, the project manager would appoint the quality
assurance team for checking the quality systems for the project. The quality analyst who would be
responsible for the task would ensure that each of the phases that would be made over the project
would be checked for quality purposes. If any of the phases would remain uncleared for the project, the
Document Page
9RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
quality analyst would help the technical development team in defining new aspects for the project. A
proper kind of planning would be defined based on checking over the quality of the systems. Ensuring
proper kind of planning for the quality of the systems would be considered to be highly important based
on providing different kind of benefits for the project.
4.7 Stakeholder Analysis
During the management of stakeholders within the project, different kind of factors would be
taken into consideration. The stakeholders involved within the project would be considered to be highly
important for benefiting the project. The different stakeholders involved within the project would be
discussed as follows:
1. Project Manager – The project manager would define the various criteria in relation to the
renovation works of the project. They would prepare an analysis based on performing the works of
renovation.
2. Technical Development Team – The development team would procure the different materials
that would be in relevance to the development of the new room for placing the servers. During the
development phases, the technical team would prepare the objective of the project in a document and
would thus plan for the entire activity list of the project.
3. Quality Assurance Team – The quality analyst would engage with the project manager and
technical development team in every aspect of the project. They would look into the detailed aspect of
each of the phases. This would be helpful for them in ensuring that each of the phases defined for the
project would be completed successfully without any form of errors within the systems.
4.8 Plan Communications
The communication plan that would be defined within the aspect of the project could be
defined as a simple and useful tool that would help them in enabling the ways in which the
communication over the project would be made. An efficient form of communication plan would help in
defining the type of communication that would be created with each of the team members of the
project. The creation of the communication plan would be able to set different forms of guidelines and
information for each of the team members involved within the project. They would also direct as who
would be responsible for maintaining communication in each of the sections of the project.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
Communication Frequency Goal Owner Audience
Email
Project Status
Report
Weekly The primary goal of the
project status report
Project Manager Project Sponsor,
Project Manager
Meetings
Project review At various
milestones
The primary goal of the
project would be to define to
review the various phases of
the project. With the help of
communicating with the team
in the form of meetings,
several issues would be
defined.
Project Manager Quality Assurance
team, Project
Manager
Project Closure
meeting
At the
concluding
part of the
project
To assess and discuss whether
each of the phases have been
completed successfully
Project Manager Quality Assurance
team, Project
Manager
Project Schedules
Update on team
work progress
Daily To share the daily progress of
update on the task. This would
help the project team to
understand about the update
on the several activities of the
project. Based on determining
about the update over each of
the activity, the project
manager would be able to
plan the future aspects of the
project.
Project Manager Project Manager
Document Page
11RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
4.9 Plan Project Risks Management
The different kind of risks that could affect the project during the renovation of the server rooms
are:
Type of Risks Risk Description Risk Mitigation Strategy
Technical Risks Different kind of technical risks might
affect the project. these include – failure
to meet the deadlines of completing the
project, ensuring secure data
communication, procuring of items within
the exact time
In order to mitigate the risks based on
technical factors, the project manager
should ensure that each of the
technical aspects would be addressed
properly. They should ensure that the
technical equipment would be
successfully procured within the
appropriate time. They should also
ensure that each of pre-defined
activities would be completed as per
the given plans and schedule.
Financial
constraints
There could be different forms of risks in
relation to fixing of the budget of the
project. The project might also exceed the
budget that would be initially be set.
In order to mitigate the risks affecting
the budget of the project, the project
sponsor and the project manager
should determine the budget before
the planning of the project.
Security of
data
During the renovation works, there might
be certain chances that the confidential
data of the company might be vulnerable
to attacks.
The technical team involved within the
project should ensure that the data
gathered within the servers should be
backed up to the cloud based service
platform.
4.10 Plan Project Deployment
Each of the aspects in relation to the project should be checked appropriately after the
completion of the project. After the completion of payment would be done to the stakeholders involved
within the project, they would sign the necessary documents in relevance to the project designing
phase. After proper signing of documents, the project manager would hand over the project to the
owners of the company. In this process, the project would be deployed to the owner and thus the server
room could be used again.
Document Page
12RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
5. Project Sign Off
1. Project Summary
Start Date Mon 20-05-19 Finish Date Fri 23-08-19
Project Duration The duration of the project is 70 days
2. Project Goal
The goal of the project was to renovate the server room for ABC Company. Each of the activities had
thus been completed as per the proper planning and thus the project had been deployed successfully.
3. Project Deliverables
The deliverables of the project was to bring a change in the server room. The room was completely
renovated by keeping each of the components intact. Each of the deliverables of the project were met
successfully for the project.
5. Document Signatures
Designation Description Signature Date
Owner I have acknowledged that each of
the defined criteria for the project
have been fulfilled. The deliverables
for the project have also been met.
Wed 21-08-19
Project Manager I have acknowledged that each of
the defined criteria for the project
have been fulfilled. The deliverables
for the project have also been met.
Wed 21-08-19
Quality Assurance Team I have acknowledged that each of
the defined criteria for the project
have been fulfilled. The deliverables
for the project have also been met.
Wed 21-08-19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
6. Post Project Review and Recommendations
Based on the conclusions drawn over the project, it could be discussed that the project have
been completed successfully and as per proper planning. The project was also completed within the
proper delivery time and the pre-estimated budget of the project. However, the project could have been
defined much more accurately by elongating the time period for the project. This would have reduced
the costs incurred for the project.
Document Page
14RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
Bibliography
Anthony, K., 2015. Calling all LEGO lovers! Add a mini control room to your collection (No. BUL-NA-2015-
193, p. 6).
Behrens, G., Weicht, J., Schlender, K., Fehring, F., Dreimann, R., Meese, M., Hamelmann, F., Thiel, C.,
Försterling, T. and Wübbenhorst, M., 2018. Smart Monitoring System of Air Quality and Wall
Humidity Accompanying an Energy Efficient Renovation Process of Apartment Buildings. In From
Science to Society (pp. 181-189). Springer, Cham.
Bird, C.J., Dillon, D.T., Dewar, C.N. and Dalton, J.M., Reducing Indoor Environmental Risks–the Life Cycle
of Safer Buildings.
Couch, L.R., 2018. Prevention in Design, Renovation. Practical Healthcare Epidemiology, p.387.
Harada, V.H., Kirio, C., Yamamoto, S., Reman, J. and Dickinson, G.K., 2015. Project-based learning: rigor
and relevance in high schools. School library management, 157.
Hulimka, J., Kubica, J. and Kałuża, M., 2018. Problems concerning reconstruction of old postindustrial
building of a closed coal mine and its adaptation to a new utility function. In MATEC Web of
Conferences (Vol. 174, p. 03021). EDP Sciences.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. Wiley.
Kontokosta, C.E., 2016. Modeling the energy retrofit decision in commercial office buildings. Energy and
Buildings, 131, pp.1-20.
Kraut, R.E., Egido, C. and Galegher, J., 2014. Patterns of contact and communication in scientific research
collaborations. In Intellectual teamwork (pp. 163-186). Psychology Press.
Lemire, N., Baril, P.L. and Le Blanc, E.L.I., 2014. Efficient labs for university: Honorable Mention
educational facilities, existing. ASHRAE Journal, 56(11), pp.70-76.
Lohse, R., Staller, H. and Riel, M., 2016. The Economic Challenges of Deep Energy Renovation—
Differences, Similarities, and Possible Solutions in Central Europe: Austria and
Germany. ASHRAE Transactions, 122(1), pp.69-87.
Document Page
15RENOVATION OF THE SERVER ROOM WITHIN A COMPANY
McArthur, J.J. and Jofeh, C.G.H., 2015. Strategic retrofit investment from the portfolio to the building
scale: a framework for identification and evaluation of potential retrofits. Procedia
engineering, 118, pp.1068-1076.
Milichenko, Y., Takaeva, E. and Voevodin, V., U-70 ACCELERATOR COMPLEX: CENTRALIZED ACCESS TO
IP-DEVICES WITH EMBEDDED WEB-SERVER.
Moses, S. and Rowe, D.C., 2016. Physical Security and Cybersecurity: Reducing Risk by Enhancing
Physical Security Posture through Multi-Factor Authentication and other Techniques.
Mugridge, R.L. and Sweeney, M., 2015. Data center consolidation at the University at
Albany. Information Technology and Libraries, 34(4), pp.18-29.
Park, R., 2017. Value engineering: a plan for invention. Routledge.
Rose, J. and Thomsen, K.E., 2015. Energy saving potential in retrofitting of non-residential buildings in
Denmark. Energy Procedia, 78, pp.1009-1014.
chevron_up_icon
1 out of 16
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]