Expertise and wherewithal to get the storage tank ready for the rescheduled shipment within three weeks. Two options: compress work packages or rearrange project schedule. Option 1: undertake two main tasks simultaneously, fast track repair works, and crash work program. Option 2: rearrange project work schedule completely and get tank Three ready. Compress work schedule and work packages to complete repairs within a much shorter time period by undertaking tasks concurrently, and working overtime.