Running head: PROJECT MANAGEMENT
Case study- Repairing the tanks of Western Australian Site
Name of the Student
Name of the University
Author’s Note

1
PROJECT MANAGEMENT
Table of Contents
1. Development of project budget..............................................................................................2
1.1 Project budget...................................................................................................................2
1.2 Assumptions made...........................................................................................................4
2. Project schedule.....................................................................................................................5
2.1 Preparation of project schedule with project deliverables and milestones......................5
2.2 Discussion about project merits of the tools, techniques and methods............................8
2.3 Comparison between tools, techniques and methodologies.............................................9
3. Estimation of resources..........................................................................................................9
3.1 Resources which are needed............................................................................................9
3.2 Integration of resource with project schedule................................................................10
3.3 Critical path....................................................................................................................14
3.4 Tools and techniques......................................................................................................15
Bibliography.............................................................................................................................16

2
PROJECT MANAGEMENT
1. Development of project budget
1.1 Project budget
The project that repairs the tanks of the Western Australian site requires budget of
around $91,360.00 in order to finish the project effectively. The budget that is needed for
executing each of the tasks of the project are provided in detail in the table that is given
below:
WBS Task Name Duration Cost
0
Repairing the tanks of Western
Australian Site
82 days $91,360.00
1 Project kick off phase 13 days $5,480.00
1.1 Identifying issues and problems 3 days $720.00
1.2 Testing the feasibility 4 days $1,600.00
1.3 Making project charter 3 days $1,200.00
1.4 Hiring staffs 4 days $1,120.00
1.5
Reviewing the starting phase of
the project
3 days $840.00
1.6
Milestone 1: Completion of
kick off phase
0 days $0.00
2 Planning phase 21 days $16,160.00
2.1 Making plan for the project 5 days $2,000.00

3
PROJECT MANAGEMENT
2.2
Making plan for the utilization
of resources
6 days $1,440.00
2.3
Developing the financial plan for
the project
8 days $2,560.00
2.4 Analyzing the quality 7 days $5,040.00
2.5
Developing risk management
plan
8 days $5,120.00
2.6
Milestone 2: Completion of
planning phase
0 days $0.00
3 execution phase 41 days $66,760.00
3.1 Creating agreement 14 days $5,040.00
3.2
Resolving external problems and
challenges
12 days $4,320.00
3.3 Development of project contract 13 days $4,680.00
3.4 Completion of predatory work 10 days $2,800.00
3.5
Developing strategies for
resolving leakage
14 days $5,040.00
3.6
Development of strategies for
resolving issues
12 days $3,360.00
3.7 Undertaking the project work 11 days $3,960.00

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Repairing the Tanks of Western Australian Site: Project Management Case Study
|19
|2766
|470

Project Management Project: Repairing of Australian Storage Name of the University Author's Note
|15
|2485
|277

Repairing of Storage Tanks at Western Australia Site - Project Management
|20
|2571
|195

Assignment on Project Management (pdf)
|15
|2685
|57

Project Management for Moomba Festival Melbourne
|5
|625
|97

Project Management: Status, Timeline, Cost, and Adjustments
|16
|2407
|200