This assignment delves into the practical applications of Radio Frequency Identification (RFID) technology, highlighting its role in enhancing value creation within organizations. It examines case studies showcasing RFID implementations in sectors like fashion retail, supply chain management, and service innovation. The analysis focuses on understanding how RFID solutions address specific challenges, improve operational efficiency, and contribute to overall business value.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Project Management
(Parcel Post Company)
Name of the student:
Name of the university:
Author Note
Project Management
(Parcel Post Company)
Name of the student:
Name of the university:
Author Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT
Executive summary
The report considers the Parcel Post Company implementing the RFID Tags and defines the
project scopes and establishes the project priorities. Further it has developed the Work Breakdown
Structure and the Risk Breakdown Structures. Lastly the identified risks are prioritized along with
proper risk treatment is proposed.
Executive summary
The report considers the Parcel Post Company implementing the RFID Tags and defines the
project scopes and establishes the project priorities. Further it has developed the Work Breakdown
Structure and the Risk Breakdown Structures. Lastly the identified risks are prioritized along with
proper risk treatment is proposed.
2PROJECT MANAGEMENT
Table of Contents
Introduction:..........................................................................................................................................3
The project scope:..................................................................................................................................3
The Work Breakdown Structure:...........................................................................................................5
Project priorities:...................................................................................................................................7
Risk breakdown structure for the project:.............................................................................................8
Evaluation and prioritizing of the identified risks:..............................................................................10
Conclusion:..........................................................................................................................................11
Bibliography:.......................................................................................................................................12
Table of Contents
Introduction:..........................................................................................................................................3
The project scope:..................................................................................................................................3
The Work Breakdown Structure:...........................................................................................................5
Project priorities:...................................................................................................................................7
Risk breakdown structure for the project:.............................................................................................8
Evaluation and prioritizing of the identified risks:..............................................................................10
Conclusion:..........................................................................................................................................11
Bibliography:.......................................................................................................................................12
3PROJECT MANAGEMENT
Introduction:
The resource manager of the Parcel Post Company has been planning to provide more
visibility to the clients as per as the position of the clients. Currently, the parcels ate getting sorted
automatically at the depot and placed in the containers loaded onto the trucks. These containers are
tagged with the RFID Tags.
The following report defines the project scopes and establishes the project priorities. It has
developed the Work Breakdown Structure and the Risk Breakdown Structures. Then the identified
risks are prioritized. Lastly, a proper risk treatment is proposed.
The project scope:
The various scopes are discussed in this section. The main objectives are to integrate the
RFID technology at the distribution and the storage network for achieving the product storage and
handling systematically. The maximizing the data accuracy of the movement of the product and
decreasing the relevant management risks are to be determined. Lastly, the project intends t achieve
the real-time monitoring of the distribution and the excellent control of the quality of the product
under the distribution network.
The RFID tag must be attached to the case and not on every item. The products should raise
the expense highly without any bringing of any simple financial impact. The domestic consumers
would not get any advantages since the tag would never help every one of them. The embedded
RFID tag in the packaging of the product could never be recollected in order to recycle. Moreover,
the ROI or the return of Investment has been very low.
Introduction:
The resource manager of the Parcel Post Company has been planning to provide more
visibility to the clients as per as the position of the clients. Currently, the parcels ate getting sorted
automatically at the depot and placed in the containers loaded onto the trucks. These containers are
tagged with the RFID Tags.
The following report defines the project scopes and establishes the project priorities. It has
developed the Work Breakdown Structure and the Risk Breakdown Structures. Then the identified
risks are prioritized. Lastly, a proper risk treatment is proposed.
The project scope:
The various scopes are discussed in this section. The main objectives are to integrate the
RFID technology at the distribution and the storage network for achieving the product storage and
handling systematically. The maximizing the data accuracy of the movement of the product and
decreasing the relevant management risks are to be determined. Lastly, the project intends t achieve
the real-time monitoring of the distribution and the excellent control of the quality of the product
under the distribution network.
The RFID tag must be attached to the case and not on every item. The products should raise
the expense highly without any bringing of any simple financial impact. The domestic consumers
would not get any advantages since the tag would never help every one of them. The embedded
RFID tag in the packaging of the product could never be recollected in order to recycle. Moreover,
the ROI or the return of Investment has been very low.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT MANAGEMENT
The first phase must include the RFID business analysis. Then there should be the technical
assessment and pilot. Then there must be the integration analysis and alt last there are the delivery
and the promotion phases.
Apart from all this, the support from the top management has been required strictly. The
stakeholders must be convinced with some of the benefits discussed below that are achieved over the
suggested investment. The following table illustrates the various aspects of the project scopes to be
considered.
Cost (Working
on Capital
Reduction)
The adoption on the RFID would enable the lesser man-hour over the quality
inspections. It should prevent the manual recording of data reducing the cost of
human capital at every warehouse.
Revenue (Profit
Increase)
There is the reduction of the labor costs for long terms in the warehouses and
stores. There is the decrease in the inventory with the more effective
information management. Moreover here lies the decrease in shipping loss and
the inventory loss because of the duplicate order, shortage, damage wrong
routing and much more.
Improve
efficiency
The assent visibility is developed leading to the rise in asset usage and the
efficiency of the working capital.
Improved service
and product
quality
The manufacturers must locate and recall the faulty products very fast before
they reach the customers.
Regulatory and
legal
requirements
The controlling of temperature assures the quality and safety ensuring the
longevity of the food products.
The first phase must include the RFID business analysis. Then there should be the technical
assessment and pilot. Then there must be the integration analysis and alt last there are the delivery
and the promotion phases.
Apart from all this, the support from the top management has been required strictly. The
stakeholders must be convinced with some of the benefits discussed below that are achieved over the
suggested investment. The following table illustrates the various aspects of the project scopes to be
considered.
Cost (Working
on Capital
Reduction)
The adoption on the RFID would enable the lesser man-hour over the quality
inspections. It should prevent the manual recording of data reducing the cost of
human capital at every warehouse.
Revenue (Profit
Increase)
There is the reduction of the labor costs for long terms in the warehouses and
stores. There is the decrease in the inventory with the more effective
information management. Moreover here lies the decrease in shipping loss and
the inventory loss because of the duplicate order, shortage, damage wrong
routing and much more.
Improve
efficiency
The assent visibility is developed leading to the rise in asset usage and the
efficiency of the working capital.
Improved service
and product
quality
The manufacturers must locate and recall the faulty products very fast before
they reach the customers.
Regulatory and
legal
requirements
The controlling of temperature assures the quality and safety ensuring the
longevity of the food products.
5PROJECT MANAGEMENT
Improve
customer
satisfaction
The more efficient information management of the stock level should help the
sales to make the required business decision. This must help in assisting the
customers on inquiry and orders.
Increase
visibility
The real-time data could be achieved for fast management decision like sorting,
routing and recalls.
Improve
collaboration
The rise in inventory accuracy the proper demand planning must be assisted
and the inventory cost must be reduced.
Apart from all this, the timeline is to be decided. For formulating the budget needed for the
project, all the resources needed are to be listed out. Research is to be conducted on the expenses
from the online sources.
The Work Breakdown Structure:
WBS Task Name Duration Start Finish
0 The Phases of project
management at the Parcel
Post Company
45 days Thu 6/1/17 Wed 8/2/17
1 RFID business analysis 3 days Thu 6/1/17 Mon 6/5/17
2 The technical assessment
and pilot
9 days Tue 6/6/17 Fri 6/16/17
3 The integration analysis 3 days Wed
7/12/17
Fri 7/14/17
4 The delivery phase 7 days Tue 7/18/17 Wed 7/26/17
Improve
customer
satisfaction
The more efficient information management of the stock level should help the
sales to make the required business decision. This must help in assisting the
customers on inquiry and orders.
Increase
visibility
The real-time data could be achieved for fast management decision like sorting,
routing and recalls.
Improve
collaboration
The rise in inventory accuracy the proper demand planning must be assisted
and the inventory cost must be reduced.
Apart from all this, the timeline is to be decided. For formulating the budget needed for the
project, all the resources needed are to be listed out. Research is to be conducted on the expenses
from the online sources.
The Work Breakdown Structure:
WBS Task Name Duration Start Finish
0 The Phases of project
management at the Parcel
Post Company
45 days Thu 6/1/17 Wed 8/2/17
1 RFID business analysis 3 days Thu 6/1/17 Mon 6/5/17
2 The technical assessment
and pilot
9 days Tue 6/6/17 Fri 6/16/17
3 The integration analysis 3 days Wed
7/12/17
Fri 7/14/17
4 The delivery phase 7 days Tue 7/18/17 Wed 7/26/17
6PROJECT MANAGEMENT
5 The promotion phase 5 days Thu
7/27/17
Wed 8/2/17
Figure 1: “The proposed Gantt Chart”
(Source: Created by Author)
5 The promotion phase 5 days Thu
7/27/17
Wed 8/2/17
Figure 1: “The proposed Gantt Chart”
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT MANAGEMENT
Figure 2: “The proposed Work Breakdown Structure”
(Source: Created by Author)
Project priorities:
It has been an inevitable fact that the best plans laid by RFID projects have been seldom
surviving totally intact as they are brought out to the real-world of the personnel changes of the end-
users. The new priorities of budget and as the client introduce any urgent system perquisites or
limitation stopping everyone in the tracks some aspects is to be covered. There must be developing
and achieving of the team approval of the project scope of the work. There must be conducting the
Figure 2: “The proposed Work Breakdown Structure”
(Source: Created by Author)
Project priorities:
It has been an inevitable fact that the best plans laid by RFID projects have been seldom
surviving totally intact as they are brought out to the real-world of the personnel changes of the end-
users. The new priorities of budget and as the client introduce any urgent system perquisites or
limitation stopping everyone in the tracks some aspects is to be covered. There must be developing
and achieving of the team approval of the project scope of the work. There must be conducting the
8PROJECT MANAGEMENT
calls of the conference of pre-installation per week. This should be done by reviewing the
development of the steps and timelines of the project plans. There must be the assuring of all the
new tags of RFID systems and hardware at the place from the proper vendors. Moreover, there
should be the approval from customers and tests done thoroughly regarding the portal and handled
the software. Lastly, there should be the fully vetted and developed custom interface to the back-end
legacy asset of the customer’s database.
The fundamental and the complicated elements of the system must include the tags,
middleware, sensors, encoders or printers, readers or encoders and in addition some needed software
adaptations. It should enable the legacy applications and the systems to receive the data originated
by the RFID.
The implementation of RFID at the current program and the support from the technical
consulting team from the third-party has constituted the majority of the costs. The team has been
needed to deliver one technical consulting engagement or perform a turnkey world-wide solution
across the comprehensive reseller and integration work of the system.
Risk breakdown structure for the project:
The risks are assessed as per as the following categories.
Technical: There should be checking of the inadequate data, information that could be hard
to disaggregate, improper recording of the data. These could generate issues in
the technical risk assessments. This technical risk assessment could moreover
occur due to accident migration. This indicates the tendency regarding the
ignored sectors of accidents. Further, there could be the regression at the mean or
calls of the conference of pre-installation per week. This should be done by reviewing the
development of the steps and timelines of the project plans. There must be the assuring of all the
new tags of RFID systems and hardware at the place from the proper vendors. Moreover, there
should be the approval from customers and tests done thoroughly regarding the portal and handled
the software. Lastly, there should be the fully vetted and developed custom interface to the back-end
legacy asset of the customer’s database.
The fundamental and the complicated elements of the system must include the tags,
middleware, sensors, encoders or printers, readers or encoders and in addition some needed software
adaptations. It should enable the legacy applications and the systems to receive the data originated
by the RFID.
The implementation of RFID at the current program and the support from the technical
consulting team from the third-party has constituted the majority of the costs. The team has been
needed to deliver one technical consulting engagement or perform a turnkey world-wide solution
across the comprehensive reseller and integration work of the system.
Risk breakdown structure for the project:
The risks are assessed as per as the following categories.
Technical: There should be checking of the inadequate data, information that could be hard
to disaggregate, improper recording of the data. These could generate issues in
the technical risk assessments. This technical risk assessment could moreover
occur due to accident migration. This indicates the tendency regarding the
ignored sectors of accidents. Further, there could be the regression at the mean or
9PROJECT MANAGEMENT
the natural ebb and flow of accidents related to a particular range of events.
External: These kinds of risks are arising from different events external to the company and
that has been beyond the control and influence. It could include the political and
natural disasters and some sift in macro-economy. As the organization is unable
to do away with those events, the management must be focusing on the
determination and the mitigation of the effects. The postal company should also
tailor the process of risk-management at the various categories. As the
compliance-based method has been effective to manage the risks preventable, it
has been completely insufficient for the external risks and strategic risks. This
needs the primarily various approaches on the basis of the explicit and open risk
discussions. This extensive organizational and behavioral research displays that
the people have hard cognitive biases discouraging them to think about and
discuss the risks till it gets late.
Organizational: Before starting the implementation it has been crucial for the Parcel Post
Company to impose the organizational risk assessment approach. The resources
are to be ensured and it must be determined that the infrastructure and support for
the project have been in place. For performing this steps are discussed here.
Firstly there should be secure commitment especially the approval for the senior
managers and support to tackle the problems. There must be the commitment of
sufficient resources, especially in the staff-time. There must be secure of
commitment from the employees and the representatives. The need to establish
must be considered and the project planning and the continuing of the
administration must be considered. The mechanism and the timing for the
communication policies are also to be considered and if appropriate the
the natural ebb and flow of accidents related to a particular range of events.
External: These kinds of risks are arising from different events external to the company and
that has been beyond the control and influence. It could include the political and
natural disasters and some sift in macro-economy. As the organization is unable
to do away with those events, the management must be focusing on the
determination and the mitigation of the effects. The postal company should also
tailor the process of risk-management at the various categories. As the
compliance-based method has been effective to manage the risks preventable, it
has been completely insufficient for the external risks and strategic risks. This
needs the primarily various approaches on the basis of the explicit and open risk
discussions. This extensive organizational and behavioral research displays that
the people have hard cognitive biases discouraging them to think about and
discuss the risks till it gets late.
Organizational: Before starting the implementation it has been crucial for the Parcel Post
Company to impose the organizational risk assessment approach. The resources
are to be ensured and it must be determined that the infrastructure and support for
the project have been in place. For performing this steps are discussed here.
Firstly there should be secure commitment especially the approval for the senior
managers and support to tackle the problems. There must be the commitment of
sufficient resources, especially in the staff-time. There must be secure of
commitment from the employees and the representatives. The need to establish
must be considered and the project planning and the continuing of the
administration must be considered. The mechanism and the timing for the
communication policies are also to be considered and if appropriate the
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT MANAGEMENT
organization stress policy is to be developed. Lastly, records are to be kept
regarding what has been done.
As per as the security of commitment is concerned, stress at work should be tackled at the
work. This could be done by performing some actions. Hence there might be already some idea
regarding what factors must secure the commitment at the top level in the Parcel post Company.
Regarding the business case or the tacking of the stress, there has been the tendency to
concentrate only on the direct expense of the staffs was not present. The research has seen that the
stress related to work might cause the reverse effect to the Parcel post Company. This might be in
terms of maintaining the business performance and output, performance and productivity of the
staffs, the intention to leave and the staff turnover, the attendance levels and the recruitment of
employees and retention. Moreover, there has been customer satisfaction and the organizational
reputation and image along with the potential litigation.
Evaluation and prioritizing of the identified risks:
Regarding the organizational risks, the employees must be involved along with the
representatives. The employees must also be informed regarding what they have been doing to make
the changes. As to the decision to prioritize the efforts to the restricted sector of the Parcel post-
Company the people must be stated with the proper explanation. As per as the external risks are
concerned, it is essential to assemble the teams with various backgrounds. The presence of distinct
viewpoints of the similar issues could analyze the external factors impacting the project. The
technical ones could be eradicated through the determination of the consequence and likelihood of
organization stress policy is to be developed. Lastly, records are to be kept
regarding what has been done.
As per as the security of commitment is concerned, stress at work should be tackled at the
work. This could be done by performing some actions. Hence there might be already some idea
regarding what factors must secure the commitment at the top level in the Parcel post Company.
Regarding the business case or the tacking of the stress, there has been the tendency to
concentrate only on the direct expense of the staffs was not present. The research has seen that the
stress related to work might cause the reverse effect to the Parcel post Company. This might be in
terms of maintaining the business performance and output, performance and productivity of the
staffs, the intention to leave and the staff turnover, the attendance levels and the recruitment of
employees and retention. Moreover, there has been customer satisfaction and the organizational
reputation and image along with the potential litigation.
Evaluation and prioritizing of the identified risks:
Regarding the organizational risks, the employees must be involved along with the
representatives. The employees must also be informed regarding what they have been doing to make
the changes. As to the decision to prioritize the efforts to the restricted sector of the Parcel post-
Company the people must be stated with the proper explanation. As per as the external risks are
concerned, it is essential to assemble the teams with various backgrounds. The presence of distinct
viewpoints of the similar issues could analyze the external factors impacting the project. The
technical ones could be eradicated through the determination of the consequence and likelihood of
11PROJECT MANAGEMENT
the event. This process must be structured for ensuring every significant task at the Parcel post
Company.
Conclusion:
The RFID technology has been the very innovative solution for the Parcel post Company.
The company should effectively design the process of business flows. It has the properties of various
distinct from the presently used labels of barcodes. However, the company has been not must aware
of the technology and the advantages that could contribute to the business management and process.
Moreover, the RFID tag price has been much higher than the barcode labels. The report has
effectively evaluated the project scopes and the risks at various sectors like technical, organizational
and external. Lastly, it has evaluated the various ways to mitigate those potential risks.
the event. This process must be structured for ensuring every significant task at the Parcel post
Company.
Conclusion:
The RFID technology has been the very innovative solution for the Parcel post Company.
The company should effectively design the process of business flows. It has the properties of various
distinct from the presently used labels of barcodes. However, the company has been not must aware
of the technology and the advantages that could contribute to the business management and process.
Moreover, the RFID tag price has been much higher than the barcode labels. The report has
effectively evaluated the project scopes and the risks at various sectors like technical, organizational
and external. Lastly, it has evaluated the various ways to mitigate those potential risks.
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.