This report explores the project that has been assigned by Peters company to Corwins for research, development and testing of its new rubber products. The project would involved 30 tests that would be run.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Requirements Management Student Name [Student No]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Requirements Management Contents Introduction...........................................................................................................................................2 Requirements management plan (RMP)................................................................................................2 Project Overview...............................................................................................................................2 Requirement Gathering......................................................................................................................2 Roles & Responsibilities....................................................................................................................3 Tools..................................................................................................................................................3 Requirements Traceability Matrix.....................................................................................................3 Change Control..................................................................................................................................4 Requirements Documents......................................................................................................................4 Business Requirements for Peters......................................................................................................4 Business Recruitments for Corwins...................................................................................................5 Stakeholder Requirements.................................................................................................................5 Solution Requirements......................................................................................................................6 Project Requirements.........................................................................................................................6 Transition Requirements....................................................................................................................6 Project Scope.........................................................................................................................................7 Scope Statement................................................................................................................................7 WBS..................................................................................................................................................7 WBS Dictionary................................................................................................................................8 Scope Validation.................................................................................................................................13 Conclusions.........................................................................................................................................14 References...........................................................................................................................................15
Requirements Management Introduction This report explores the project that has been assigned by Peters company to Corwins for research, development and testing of its new rubber products. The project would involved 30 tests that would be run. This document contains the detailed plan of how requirements of the project would gathered and documented using appropriate project management tools. It also presents a WBS and a dictionary defining its work packages. Requirements management plan (RMP) Project Overview This project has been taken by Corwins from Peters company that needs its Research and Development operations to be taken by Corwins for a project which would need 30 tests to be conducted on the special product. The project has been assigned a budget of $231,000 and has to be completed within 6 months. Requirement Gathering The requirements of the project have been gathered by marketing VP, Gene Frenel of Corwin from one of the key stakeholders of the Peters company named Frank Delia who is the marketing VP of his company. An initial interview have been conducted and thereafter the specification sheet had been sent by Peters company to Gene over email with detailed requirements on five tests to be conducted. For the remaining tests, a mutual agreement between two companies would be arrived at after discussion(C.R & Thomas, 2011). The high level requirements of the project were identified by interviewing the major stakeholders of the Peters company and these included: ï‚·The project would have to research and develop rubber products and conduct tests for them ï‚·There would be 30 tests to be conducted in 6 months ï‚·The 5 tests have to be run according to the specification sheets provided by the client ï‚·The 25 tests would be mutually decided between Peters and Corwins company considering the needs for the product and the market ï‚·The team would need to conduct a research on rubber materials and then develop them before testing would follow
Requirements Management Roles & Responsibilities The key people who are responsible for managing the project include marketing VP who has initiated the project, Royce who took the bidding decision, Dr. Reddy who would help in the resource planning and Dan West who would be the project manager of the project. NameRoleResponsibility Gene FremelMarketing – VPProject Acceptance RoyceEngineering - VPBidding decision Dr. ReddyR&D – DirectorProject Resource Planning Dan WestR&D – ScientistProject Management Tools For the management of the project, a number of project management tools would be used including responsibility traceability matrix, work breakdown structure, WBS dictionary, and project requirement documentation. Requirements Traceability Matrix Each requirement defined by the client would be recorded in the traceability matrix which would identify how they would be fulfilled including the source of request, department responsible, business need it would justify, WBS deliverable it would be connected to, test strategy to use, responsible person and as the project progresses, the status would keep getting updated. A sample matrix is provided below which illustrates how requirements of the project would be recorded(Leroy, 2012) Requirem ent Descriptio n Sour ce Departme nt Business Need WBS Delivera ble Test Strategy Responsibi lity Status 5 tests to be completed as per the test sheets provided Patri k Ray Project Managem ent Test the product for its market value TestingValidate as per specificati on sheet Project manager Yet to begin Project toGeneMarketingProjectProjectPlan to beProjectIn
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Requirements Management be completed within 6 months Frem el needs to be planned appropriat ely so that it can be completed in desired timeline planningvalidated by the project stakehold ers on scope manager – Dan West progre ss (BIS, 2010) Change Control Change is inevitable and as the project progresses, changes are required. If there are major changes made in deliverables of the project then it could affect the project constraints, performance, as well as the viability of the project. Thus, it is important that changes are carefully managed such that only those changes are made that are good for the project. Thus, it is essential to keep in place a change control policy such that unviable changes are not executed. For controlling change, an organized process would be used in which every change need sensed by any project team member would be formally placed to the project manager who would be evaluating the change requirements to see how it would affect the project. This assessment would involve review of the impact of change on project deliverables and constraints(Jainendrakumar, 2016). The changes requested would be recorded in a log and the decisions made on whether to accept the change or not would be updated in the log. Impacts of the change would be on cost, timeline, resource requirements, and project risks or issues. The result of change request can be acceptance, acceptance in special conditions, rejection or deferment in which change is rejected for the time being but is kept for consideration.If a change is approved, it is implemented and the implementation is reviewed to again assess the actual impact caused. Requirements Documents Business Requirements for Peters The company has been facing a shortage of workforce as most of the workforce is already involved in the existing R&D work and thus, needs an external company to take care of their new project’s Research and development as well as production for which Corwins have been
Requirements Management approached.The project is required to be profitable for the company and thus, has to be completed within $250,000 in six months with un-front payment of $125,000 paid and rest to be paid after completion. The R&D project would need 30 tests to be conducted out of which test conditions for first five projects have been specified by Peters Company. Business Recruitments for Corwins The company had estimated the cost of conducting test and expecting $19,000 as profits and thus, the aim of the company is to ensure that project is completed within the desired estimate as planned. The company needs to have the right professionals assigned the work of project completion. And should be able to complete the project within 6 months as given by the client. The total cost of labour should not be more than $30,000 while each test would cost $2000 with overheads of $90000, material costs of $30,000, and administrative expenses of $21,000, totalling the cost of project to $231,000(SAEO, 2015). Stakeholder Requirements Stakeholders are the key people associated with the project in some ways such that they either affect the project or are influenced by the project. Every stakeholder would have different levels on influence on the project and interest. Their requirements have to be understoodandcollectedfortheprojectdeliverablesandacceptancecriteria’stobe developed. From the interviews conducted with the key stakeholders of the project, some key requirements have been identified as listed in the table below(Baguley, 2008): StakeholderRols & ResponsbilityInfluence/Interest Frank DeliaMarketing – VPHigh, high Patrick RayIn-house representative High, high Gene FremelMarketingModerate, high RoyceEngineeringModerate, high Dr. ReddyDirect projectHigh, Moderate CustomersBuy rubber productsModerate, Moderate SuppliersSell rubber materialHigh, Moderate
Requirements Management Solution Requirements Based on the requirements identified by different groups of stakeholders, some requirements for the solution that is research, development, and testing of the rubber products have been identified as follows: ï‚·Research has to be conducted on the rubber materials needed for the manufacturing of the new products ï‚·Products have to be developed using the rubber material for Peters company ï‚·The testing has to be conducted on the rubber products so that the products tested positively can be launched in the market ï‚·Products are required to be tested positively in order to get passed for the mass production(Berbec, 2014) Project Requirements The project involving research, development and testing of the rubber products for Peters company would have the following project requirements: ï‚·Project needs to be completed within 6 months ï‚·The materials are required to be procured for the procedure in bulk ï‚·30 tests have to be conducted on the rubber products ï‚·The tests conducted should be mutually approved between Peters and Corwins company(C.R & Thomas, 2011) Transition Requirements In order to proceed with the project Corwin would need to deploy its team taking from other projects to the Peters project which would need a time for transition from one project environment to another. Also, the Peters company would be outsourcing its research and development process for the new rubber products and thus, would have to now depend on the Corwin team for development. The Corwin company has deployed its Engineer as the project manager while an in-house representative has been assigned by Peters company to coordinate with the project manager of the project. Based on the project needs, certain transition requirements could be identified such as: ï‚·The teams from Corwin and Peters have to be able to effectively coordinate and complete the project tasks on time
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Requirements Management Both companies representatives need to understand the working culture of the partner as well as the working style and leadership styles of each other(Clements & Gido, 2006) Project Scope Scope Statement The project involves planning, research, development, and testing for the new rubber products that are to be manufactured for the Peters company. The activities that are within the scope of the project include – Research on rubber material with potential for new product creation Development of rubber material for the new products Conducting 30 Testing procedures on new products on multiple parameters The activities that are excluded for this project include: Mass manufacturing of the positively tested products(FME, 2014) WBS 1.0Project Planning 1.1Project management 1.1.1Stakeholder management 1.1.2Human Resource Management 1.1.3Scheduling 1.1.4Budgeting 1.1.5Project Scope Management 1.2Requirement gathering 1.2.1Interviews with stakeholders 1.2.2Specification sheets 1.2.3Requirement Tracing 1.3Contract Signing 1.3.1Performance Specifications 1.3.2Fixed price contract 2.0Research 2.1Rubber Material Research 3.0Development
Requirements Management 3.1Rubber Material Development 4.0Testing 4.1Test planning 4.2Testing 4.3Results analysis 5.0Project Closure 5.1Deliverables 5.2Acceptance of deliverables 5.3Project Sign-off(Devi & Reddy, 2012) WBS Dictionary WBS dictionary can be used for defining various tasks and related details can be covered. For the rubber material research and development project, a WBS dictionary can be prepared for every task identified in the WBS as follows: WB S ID WBS Element Name DescriptionAccountabi lity Acceptance Criteria Assumpti ons Constraints 1Project Planning 1.1Project manageme nt 1.1. 1 Stakeholde r manageme nt Gathering stakeholder requirement sand planning communicat ionwith them Project Manager Requiremen tsvalidated by stakeholder s Stakehold ersknow theneeds ofthe project Stakeholders arenot always easily availableand thus, plan has to be adjusted totheir availability 1.1. 2 Human Resource Manageme nt Forming theproject teamand managing it Project manager Rolesand responsibilit iesa identified Project teamhas sufficient skillsto Thereare limited numberof resources that
Requirements Management and assigned conduct the project canbe utilized 1.1. 3 SchedulingIdentifying timeline and assigningit as per WBS Project manager Timelines arefeasible and validated by team The project canbe completed within given schedule Project has to be completed within6 months 1.1. 4 BudgetingItinvolves approvalof total cost of theproject and planningof howthe approved budget wouldbe utilized throughout the project Project Manager Creating and controlling budget Projectto be completed within budget Budget cannotbe exceeded 1.1. 5 Project Scope Manageme nt Project scope includesall the activities and deliverables thatare includedin the scope of the project Project Manager Defining scope, monitoring project progress, and managing scope Project scopeis clearly defined Nooutof scope activity can be done 1.2Requireme nt Project requirement ProjectCollecting requirement Allkey stakehold Resources are availableto
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Requirements Management gatheringsare collected from stakeholders Managersfrom stakeholder s ers involved meet requirements 1.2. 1 Interviews with stakeholder s Project requirement sare collected from stakeholders through interviews Project Manager Collecting requirement sfrom stakeholder s Allkey stakehold ers involved Resources are availableto meet requirements 1.2. 2 Specificati on sheets Detailsof theteststo be conducted inthe project Project Manager Test requirement stobe specified Allkey stakehold ers involved Resources are availableto meet requirements 1.2. 3 Requirem ent Tracing Project requirement swouldbe tracedto keep updatedif theyhave been completed Project Manager Stakeholde r requirement s gathering Allkey stakehold ers involved Resources are availableto meet requirements 1.3Contract Signing Contract wouldbe signed between Peters company and Corwins Project Manager Project managemen t contract Contract wouldbe legal Contractual terms have to be met
Requirements Management defining the termsand conditions, deliverable, andlegal detailsof the arrangement 1.3. 1 Performan ce Specificati ons This includes the specificatio nsofthe teststobe performed Project Manager Performanc e testing Should meet identified needs Mutually agreed upon 1.3. 2 Fixed price contract The company would get a fixedprice asthe contract amount Cost Manager Contract managemen t Contractu alterms are mutually agreed Fixed price 2ResearchProject Manager 2.1Rubber Material Research This would involve researchto be conducted onthe materials used for the developmen tofrubber Project Manager Material research Asper project scope Notoutof scope (Gardiner, 2005)
Requirements Management products 3Developme nt Project Manager 3.1Rubber Material Developme nt This would involve developmen tofthe rubber materials researched Materials Manager Rubber product developmen t Asper project scope Notoutof scope 4TestingProject Manager Product testing 4.1Test planning The specificatio nsofthe testswould be identified and planned Project Manager Product testing Asper test performan ce sheets No additional tests 4.2TestingTests wouldbe conducted onthe rubber materials developed TesterProduct testing Asper test performan ce sheets No additional tests 4.3Results analysis Theresults ofthetests wouldbe analysed TesterProduct testing Asper test performan ce sheets No additional tests 5Project Closure Includes the processes involvedin closingthe Project Manager
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Requirements Management project 5.1Deliverabl es Allthe project deliverables wouldbe submitted to theclient organization Project Manager Deliverable s submission Asper project scope all requirements havetobe met 5.2Acceptanc eof deliverable s Deliverables wouldbe accepted and approved by Peters company Project owner Client acceptance Asper project scope all requirements methaveto be accepted 5.3Project Sign-off Final project completion wouldbe marked by a sign off Project Manager Project completion Between two companie s (Jainendrakum ar, 2016) Scope Validation Scope validation involves acceptance of the completed project deliverables. Once the project is completed, all the project deliverables would be individually reviewed by the marketing manager and other key stakeholders from the Peters company and as per their acceptance criteria, they would review if all deliverables have ben covered in the scope. Once verified, the client would be accepting the project as completed. The best way to ensure that validation process is formally organized and sufficiently completed, it begins with the monitoring of the project where validation is done with each deliverables completion and not just after the completion of the project. Requirement traceability matrix would be used for the current
Requirements Management project to show if the requirements defined in the project scope were reached with the completion of the deliverable(PM4DEV, 2016). Conclusions This report was prepared to understand and explore how project requirements are collected, documented and met on a project. The report explored the case of a manufacturing company Peters that had outsourced its research, development, and testing activity to Corwinsfor its currentprojectrequiringrunningof30tests.Therequirementswerecollectedfrom stakeholders by interviewing them and were used to create a WBS. This WBS was further used to trace how project requirements were met.
Requirements Management References Baguley, P. (2008).Project management. .London: Hodder Education. Berbec, I. S. (2014).Aligning Project Scope And Deliverables With Business Strategy.KTH Royal Institute of Technology . Beringer, C. J., & Kock, A. D. (2013). Behavior of internal stakeholders in project portfolio management and its impact on success.International Journal of Project Management, 31(6), 840-846. BIS. (2010).GUIDELINES FOR MANAGING PROJECTS: How to organise, plan and control projects.BIS. C.R, K., & Thomas, S. M. (2011). Requirement Gathering for small Projects using Agile Methods.IJCA, 122-128. Clements, J. P., & Gido, J. .. (2006).Effective Project Management.Thompson. Cliff Consulting. (2007).A Systems Implementation Project Planning Guide.Cliff COnsulting,. Devi, T., & Reddy, V. (2012). Work Breakdown Structure of the Project.International Journal of Engineering Research and Applications, 683-686. FME. (2014).Project Scope Management: Project Skills.FME. Gardiner, P. D. (2005).Project Management: A Strategic Planning Approach.Macmillan International Higher Education. Jainendrakumar, T. D. (2016). Project Stakeholder Management.PM World Journal, 5(5), 1- 9. Leroy, A. (2012).Requirements Gathering Rules Basic guidelines for any project, .BDPA National Technology Conference. PM4DEV. (2016).Project Scope Management for Developing Organizations.PM4DEV. PMI. (2013).A Guide to Project Management Body of Knowledge.PMI. PMI. (2013).A guide to the project management body of knowledge.Newton Square: Pennsylvania.: PMI.