This assignment discusses the risks involved in the advancement of railways in NSW and proposes risk treatment strategies to mitigate them. It covers site risks, material risks, design risks, WHS risks, and environmental risks. Recommendations include the formation of a structured risk management plan and training of employees.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: RISK ASSESSMENT OF NEW NSW TRAINS RISK ASSESSMENT OF NEW NSW TRAINS Name of the Student: Name of the University: Author Note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 RISK ASSESSMENT OF NEW NSW TRAINS Table of Contents Introduction:................................................................................................................................1 Possible Risk treatment/response that are identified and are appropriate:..................................2 Risk 1. Site risks:.........................................................................................................................3 Risk description:......................................................................................................................3 Proposed risk treatment:..........................................................................................................4 Risk description:..........................................................................................................................4 Risk 2. Material risks:..................................................................................................................4 Proposed risk treatment:..........................................................................................................5 Risk 3. Design risk.......................................................................................................................5 Risk description:......................................................................................................................5 Risk mitigation:.......................................................................................................................5 Risk 4. WHS risks:......................................................................................................................6 Risk description:......................................................................................................................6 Risk mitigation methods:.........................................................................................................7 Risk 5. Environmental risks:........................................................................................................7 Risk description:......................................................................................................................7 Risk mitigation:.......................................................................................................................8 Recommendations:......................................................................................................................8 Formation of a structured risk management plan (RMP):...........................................................8
2 RISK ASSESSMENT OF NEW NSW TRAINS Training of employees of the project management company namely. Momentum:...............8 Conclusion:................................................................................................................................10 References:....................................................................................................................................11
3 RISK ASSESSMENT OF NEW NSW TRAINS Introduction: Railway is the backbone of the economic development of the Australian economy. The railways play a pivotal in transportation of goods as well as passengers. The Department of Infrastructure and Regional Development in its report released on March 2018 shows that the railway in future would play more important role in intermodal transport, thus playing a more important in development of trade and commerce in the country (Infrastructure.gov.au, 2019). This rising importance of railways in the economic development of the has necessitated the central and the state government to bring about high level advancement in the railways services in the country. However, advancement of railways attract several risks which are capable of disrupting the advancement altogether. The aim of the assignment would be delving into the risks which advancement projects in railways may face and recommending ways to mitigate or at least mitigate them. The research would be based on a report released by the NSW Government on February 28, 2019. The report reports that the NSW Government is modernizing its fleet by awarding the modernization works toMomentumwhich is an international consortium. The successful closure of the project would result in replacing existing train models like XPT and XPLORER which are over 36 years old. The report also mentionsthat the aim of the advancement would be making railway journey more comfortable and safe for passengers. The railway carriages would have modern CCTV surveillance systems installed in them, thus enabling vigilance on the railway compartment more advanced. The railways coaches would be built in Dubbo involving local labour which would generate income for the local community (Transport.nsw.gov.au. 2019). The scope of the report would be identify the risks which the project under consideration is likely to face so as to prepare a risk management plan to manage the risks.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 RISK ASSESSMENT OF NEW NSW TRAINS Possible Risk treatment/response that are identified and are appropriate: Identification of appropriate risk treatment strategies or risk management plan for the railway project undertaken by NSW Government would play crucial role in mitigation of risks or at least minimise them to the possible extent. The graph below shows that the ratio of railway transport would increase in future in freight movement using intermodal method. The Sydney Morning Herald reports passenger demands in train serving Sydney had risen by 20 percent in 2017 (O'Sullivan, 2017). Thus, it can assumed that the passenger patronage of trains has surged further and will keep on up surging. Thus, it can be pointed that the risk treatment plan should take into account the safety of the passengers and goods the trains in NSW transport. Figure1. Graph showing the ratio of various transport modes in intermodal transport (Source:Infrastructure.gov.au, 2019) The following are the risks and their respective risk treatment plans:
5 RISK ASSESSMENT OF NEW NSW TRAINS Risk 1. Site risks: Risk description: The first risk which railway advancement projects can face is site risks. The map below shows that the site of Dubbo maintenance facility in which the new models of trains would be built. The map shows that the site lies in an area which is heavily populated with large number of buildings around it. The area is flanked by several roads which carry heavy fleet of traffic. Thus, it is evident from the map that acquisition of risk would be a risk. This is because delayed site approval and acquisition would delay commencement of the project which would in turn lead to increase in maintenance costs. Moreover, the project management company namely, Momentum and the Government of NSW would come under intense pressure to finish the project within the specified time.
6 RISK ASSESSMENT OF NEW NSW TRAINS Figure2.Key features of the Dubbo Maintenance Facility (Source: Transport.nsw.gov.au. 2019) Proposed risk treatment: Risk description: The proposed risk treatment option in this case would be starting the project only after the site has been handed over for the commencement of the project in writing. The second site risk treatment option would be to ensure the Momentum complies with the laws in power in Australia and NSW, in particular related to acquisition of land for projects. The company should abstain from using any illegal or unethical means like acquiring the land from the local people by force and encroaching into the settlement area (Enrici & Hubacek, 2018). Risk 2. Material risks: The second risk which railway projects attract is material risks pertaining to the quality of raw materials used in the construction work. The ‘Dubbo Maintenance Facility Determination Report’ clearly shows that the scope of the work include construction of roads, approach ways, car parking and buildings as the part of the work (Transport.nsw.gov.au. 2019). Thus, it is evident from the description that using of low quality materials to construct the infrastructure would increase of risk collapse of the building causing injury and even death of the people using the buildings (Iqbal et al., 2015). Deep et al. (2017) mentions in this respect that use of inferior quality materials in construction of roads and approach ways would lead to accidents causing damage cars and commuters.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 RISK ASSESSMENT OF NEW NSW TRAINS Proposed risk treatment: The mitigation of material risks can be mitigated or at least minimised by several strategies. First, the Government of NSW should specify the brands and specifications of the materials which have to be used in the construction work. The Government of NSW should mandate the project management company undertaking the project to follow ISO standards while executing the project (ISO.org, 2019). The materials procured for the project should mandatorily have ISO certifications. This would ensure that the materials procured for the project adhere to the ISO standards. This reduce the risks of building and road collapses as well as subsequent damage. Thirdly, the government should appoint its own engineers who would strictly supervise the commencement of the project to ensure strict adherence to the quality specifications of materials and their storage. Risk 3. Design risk Risk description: The third risk which the project of introducing new trains in NSW would involve is design risks. This is because appropriate design specifications are crucial to ensure that the structures constructed do not collapse. Faulty design attract several risks like collapse of structures during construction and collapse of structures after closure of the projects (Gurcanli, Bilir & Sevim, 2015). The collapse of structures during construction would lead to injury and death of workers, thus escalating to work health and safety risks. The collapse of structures after closure of projects would lead to injury and death of users of facilities. Risk mitigation: The first risk mitigation strategy which the Government of NSW and Momentum can take is that they should ensure that appropriate design specifications are complied with during
8 RISK ASSESSMENT OF NEW NSW TRAINS planning and construction of structures like the roads and buildings. Further they should also ensure that appropriate railway platform building designs are followed. The Government of NSW in order maintain strict vigilance on the railway advancement project should conduct audit of the projects annually or if required on monthly basis (Wang, 2017,). The procurement contract should specify the requirements to adhere to designs specified and should also mention that the government body can also resort to penalising Momentum in events of gross breach of specifications. The government body would as a result able to put pressure on the project management company to comply with the design specifications. Risk 4. WHS risks: Risk description: The fourth risk which projects attract is work, health and safety risks. The employees of thegovernmentofNSW,theemployeesoftheprojectmanagementcompanynamely, Momentum and suppliers are susceptible to WHS risks owing to chances of injuries. The labour involved in construction work are susceptible to injuries and bruises during operating the construction machinery. The loud sound and glaring light which are emitted during construction are capable of damaging ears and eyes of the labour respectively. The gases, dust, smoke and other harmful chemicals used and/or emitted are also capable for posing threats to the health of workers. The outcome of the WHS risks would be injury or even death of workers. This leads to temporary stalling of project work or in extreme cases, the project may be closed down. The Safe WorkOmbudsmenofAustraliamayalsoinvestigatetheprojectattractfurtherpenalty (Safeworkaustralia.gov.au, 2019)
9 RISK ASSESSMENT OF NEW NSW TRAINS Risk mitigation methods: The first risk mitigation method which the Government of NSW should take is to ensure that the site of Dubbo Maintenance Facility is free to hazards like fire to the possible extent. Further the body should direct the management of Momentum to offer protective accessories like gloves and goggles to employees employed in building of train and allied structures like roads and buildings. The third strategy which the government body can take to minimise WHS risks like explosions is that it should ensure that the chemicals and inflammable substances should be storedseparately.Thefourthstrategywhichthebodycantakeprovisionofsufficient surveillance facilities like installation of CCTV cameras within and outside the Dubbo site. The management should ensure provision of modern fire fighting systems around the site. The labourers involved the building of trains should be provided safety training which would enable to take steps in event of risks. This would enable in minimising the risks. The government body also ensure presence of ambulances around the site which would facilitate hospitalisation of labourers in events of severe injuries. Risk 5. Environmental risks: Risk description: The fifth category of risks which projects like building of trains and allied construction of structures like buildings.Cannistraro et al.(2016) point out that railway projects lead to large scale sound pollution due to use of machinery. Riley et al. (2018) mention that railway projects result in large scale environmental pollution owing to release of gases, smoke, solid wastes and liquid wastes include untreated water loaded with chemicals.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 RISK ASSESSMENT OF NEW NSW TRAINS Risk mitigation: The Government of NSW can take the several steps to reduce environmental pollution since complete reduction of pollution is not feasible. The company undertaking the project, Momentum, in this case should be instructed to comply with the environmental laws in power in AustralialikeEnvironmentProtectionandBiodiversityConservationAct1999 (Environment.gov.au, 2019).Tang et al.(2018) mention that the government body should ensure that the waste water in released only after treating. The project management company namely, Momentum should also recycle water and reuse it in the construction works. Recommendations: The above discussion brings into light five risks which the NSW Railway project would attract and ways in which the same can be mitigated or at least minimised. The following recommendation can be made to the Government body of NSW on risk management: Formation of a structured risk management plan (RMP): The Government of NSW prior to sanctioning of the project should form a well- structured risk management plan. The risk management plan should identify the probable risks which the project may face during commencement and after closing. The risk management plan should outline the ways in which the identified risks can be mitigated. The RMP should also delegate authorities to specific departments and personnel to take steps in mitigating risks. Training of employees of the project management company namely. Momentum: The Government of NSW should train the employees of Momentum to recognise and report risks. This would enable the employees to contribute in management of the risks. The employeesshouldbeoperatemodernmachineryandriskmanagementdeviceslikefire extinguishers. The employees should be encouraged to participate in the formation of risk
11 RISK ASSESSMENT OF NEW NSW TRAINS management strategies. This, the employees would have clear idea of about the risks and the appropriate methods in which the risks can be controlled. Risk NoRisk IncidentRisk DescriptionCurrent ControlsLikelihoodOwner(stakeholder concerned) 1Site risks 1. Delay in handover of site. 2. Delay in project commencement. 3. Leads to increase in maintenance costs 4. Momentum and the Government of NSW would come under intense pressure to finish the project within the specified time. 1. Starting the project only after the site has been handed over for the commencement of the project in writing. 2.Abstain from using any illegal or unethical means like acquiring the land from the local people by force HighGovernment of NSW 2Material risks 1.Increase of risk collapse 2. injury and even death of the people using the buildings 3.Accidents on roads 1 Materials procured for the project should mandatorily have ISO certifications. 2.Appoint of engineers. Very highGovernment of NSW 3 Design risk1.Collapse of structures during construction and collapse of structures after closure of the projects. 2.After closure of projects would lead to injury and death of users of facilities 1.Ensure that appropriate design specifications are complied. 2. Audit of the projects annually or if required on monthly basis 3.Procurement contract should specify the requirements to adhere to designs HighGovernment of NSW 4 WHS risksConstruction companeis generates lower reveneu due to lack of investors 1. Injuries and bruises or even death 2. Action from Safe Work Australia Very highGovernment of NSW 6Environmental risks Large scale environmental pollution owing to release of gases, smoke, solid wastes and liquid wastes include untreated water loaded with chemicals. 1. Comply with the environmental laws in power in Australia like Environment Protection and Biodiversity Conservation Act 1999 2. Waste water in released only after treating 3.Recycle water and reuse it in the construction works Very highGovernment of NSW
12 RISK ASSESSMENT OF NEW NSW TRAINS Figure3. Risk matrix (Source: Knutson & Huettel, 2015) Conclusion: It can be concluded from the discussion above that expensive railway modernisation projects are necessary to enable faster and safer transport of goods as well as passengers. The railways development projects are undertaken to boost commercial activities and economic conditions of the countries like Australia as a whole. It can also be concluded from the discussion that such projects attract several risks. It can also be pointed out that the Government of NSW should form a risk management plan or RMP to mitigate the risks or at least reduce them.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13 RISK ASSESSMENT OF NEW NSW TRAINS References: Cannistraro, G., Cannistraro, A., Cannistraro, M., & Engineer, F. (2016). Evaluation of the sound emissions and climate acoustic in proximity of one railway station.Hospitals,6(22.00), 22-00. Deep, S., Khan, M. B., Ahmad, S., & Saeed, A. (2017). A study of various factors affecting contractor’sperformanceinlowestbidawardconstructionprojects.International Journal of Civil Engineering and Technology,8(2), 28-33. Enrici, A., & Hubacek, K. (2018). Challenges for REDD+ in Indonesia: a case study of three project sites.Ecology and Society,23(2). Environment.gov.au.(2019).Retrievedfromhttps://www.environment.gov.au/resource/local- government-and-australian-environment-law Gurcanli, G. E., Bilir, S., & Sevim, M. (2015). Activity based risk assessment and safety cost estimation for residential building construction projects.Safety science,80, 1-12. Infrastructure.gov.au.(2019).Retrievedfrom https://infrastructure.gov.au/transport/freight/freight-supply-chain-priorities/supporting- papers/files/Supporting_Paper_No3_Road_and_Rail.pdf Iqbal, S., Choudhry, R. M., Holschemacher, K., Ali, A., & Tamošaitienė, J. (2015). Risk managementin construction projects.Technological and Economic Development of Economy,21(1), 65-78. ISO.org. (2019). Retrieved fromhttps://www.iso.org/standard/62085.html
14 RISK ASSESSMENT OF NEW NSW TRAINS Knutson,B.,&Huettel,S.A.(2015).Theriskmatrix.CurrentOpinioninBehavioral Sciences,5, 141-146. O'Sullivan, M. (2017). Smh.com.au. Retrieved fromhttps://www.smh.com.au/national/nsw/opal- figures-show-skyrocketing-passenger-demand-on-sydney-train-lines-20170811- gxubre.html Riley, E., Harris, P., Kent, J., Sainsbury, P., Lane, A., & Baum, F. (2018). Including health in environmental assessments of major transport infrastructure projects: a documentary analysis.International journal of health policy and management,7(2), 144. Safeworkaustralia.gov.au. (2019). Retrieved fromhttps://www.safeworkaustralia.gov.au/ Tang, M., Quan, J., Lei, X., Zheng, H., & Tang, T. (2018). Risk factors analysis and risk assessment of sudden pollution from traffic accidents in the Middle Route of South-to- North Water Diversion Project. InMATEC Web of Conferences(Vol. 246, p. 02015). EDP Sciences. Transport.nsw.gov.au.(2019).Retrievedfrom https://www.transport.nsw.gov.au/projects/current-projects/regional-rail Wang, F. (2017, December). Analysis and Solution of Common Problems in Construction Project Audit. In2017 7th International Conference on Mechatronics, Computer and Education Informationization (MCEI 2017). Atlantis Press.