This assignment delves into the essential principles of project management. It examines key concepts like risk assessment, earned value analysis, and the benefits of project management training. Students are expected to demonstrate understanding of these principles through analysis and application to real-world scenarios.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Project management: Riverina Agricultural Lifestyle Show (RALS)
Name of the student:
Name of the university:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Table of Contents
Project overview..............................................................................................................................3
Part 1: Measurable organizational value..........................................................................................3
1.1 Desired area of impact...........................................................................................................3
1.2 Identification of project values..............................................................................................5
1.3 Appropriate project metrics development.............................................................................6
1.4 Timeframe for the RALS project...........................................................................................7
1.5 Summary of MOV project...................................................................................................13
Part 2: Development of scope management plan..........................................................................13
2.1 List of project scope.............................................................................................................13
2.2 List of project resources.......................................................................................................13
2.3 Project resource details........................................................................................................14
Part 3: Project schedule and Work Breakdown Structure.............................................................14
3.1 Work Breakdown Structure.................................................................................................14
3.2 Activities of RALS project..................................................................................................15
3.3 Project resource identification.............................................................................................17
3.4 Cost estimation for RALS project.......................................................................................19
3.5 Time allotted for RALS project...........................................................................................19
Part 4: Project risk analysis and planning......................................................................................22
4.1 Developing project risk management..................................................................................22
Part 5: Quality management plan..................................................................................................24
5.1 Team philosophy for the RALS project...............................................................................24
5.2 Quality assurance.................................................................................................................24
Part 6: Closure checklist development..........................................................................................25
6.2 Outlining the project closure plan........................................................................................25
Annotated Bibliography.................................................................................................................26
References......................................................................................................................................28
Document Page
2RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Project overview
This paper defines the importance of development of new online ticket booking system
for delivery as per the expectation of the owners and to meet the requirements of the consumers.
The online ticket booking system is arranged for Riverina agriculture lifetime Show (RALS)
organized by the local business named as Virtucon and Globex Company. A show for 3 days has
been arranged by Globex Company to make discussion about the agriculture equipments,
suppliers and about the other lifetime products. In order to make the show successful and
beneficial from the business and consumers perspectives it is necessary to deal accurately with
the liver program display, volunteers and catering services as well.
The concepts for this show was generated the year of 2000 and from that time onwards
the show us being carried out by the company. In order to reduce the work pressure from the
members associated to the project a Measurable Organizational Value (MOV), time schedule and
Work Breakdown Structure (WBS) is also developed which is elaborated in this report. Apart
from this, a scope management plan, project risk management and a professional quality
management plan is also illustrated in this report.
Part 1: Measurable organizational value
1.1 Desired area of impact
Desired area for
MOV
Ranking Frequency Impact
Strategies 1 Very high Business strategy is referred to as the most
important things to gain measurable
Document Page
3RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
success from any project. With the help of
project strategies the Globex Company
would be able to gain competitive
advantages and profit at the same time.
Consumers 2 High For any business organization, consumers
are very important asset. In order to satisfy
them the company is required to develop
the system focusing the requirements of the
consumers. Therefore during the
development of the online ticket booking
system the developer should reduce the
level of complexity and must make the
system user friendly.
Financial 3 High In order to meet the requirement of the
consumers, exact amount of capital
investment is necessary. Due to
inappropriate capital investment, the
company might fail to meet the aim and
goal of the project. Therefore, in the project
initiation phase the finance manager should
make a feasibility to make sure about the
total investment and expected outcome.
Operation 4 High In order to grab more number of consumers

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
the project manager should initially make
sure that the system is operating as per the
expectation. If it is found that, after
implementation it fails to meet the
functional and operational need then, the
operational ability of the company will be
interrupted.
Social 5 Medium Social support is another important thing
which defines the project success and other
operational criteria collectively. Again
support from the social media is also
required to implement the programs
sequentially.
1.2 Identification of project values
The project values must consider the following elements to ensure that the project is
beneficial.
Better: It is expected that the online ticket booking system will reduce the queue size of
the consumers and also will deliver on time service to the consumers with security and user
friendly application.
Faster: Considering the functional and operational ability of the online ticket booking
system, it is found that, it is faster than the manual ticket booking system.
Document Page
5RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Cheaper: The online ticket booking system automatically reduces the cost because in
this approach the number of both the operators and the manpower get reduce.
1.3 Appropriate project metrics development
In order to meet the requirement of the project, proper metrics are needed to be developed
by the project head. Followings are the metrics for project development:
Stakeholder Stakeholder’s Expectation
Project manager The project manager is expecting the complete
the project within estimated time and budget.
Project sponsors The project sponsors are expected to invest as
per the project requirements.
HR manager The HR manager is needed to manage all
project team members.
Operational manger The expectation of the operation manager is to
develop the system in such a way so that it
could operate accurately.
Finance manager The finance manager expects to develop the
online ticket booking system within the
estimated cost or budget.
System developer The system developer expects to develop the
online ticket booking system considering the
leading system requirements.
Business analyst Expects to develop the system considering the
Document Page
6RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
basic business strategies.
1.4 Timeframe for the RALS project
WBS Task Name Duration Start Finish Predecessors
Resource
Names
Cost
Variance
0
RALS project
scheduling
125 days
Wed
1/17/18
Tue
7/10/18
$30,088.00
1
Project
initiation phase
43 days
Wed
1/17/18
Fri
3/16/18
$10,792.00
1.1
Conceptualizin
g the project
6 days
Wed
1/17/18
Wed
1/24/18
business
analysts ,P
roject
manager
$1,680.00
1.2
Developing
project charter
4 days
Thu
1/25/18
Tue
1/30/18
2
Operation
manager ,
Project
manager
$1,120.00
1.3
Appointing
vendors
8 days
Wed
1/31/18
Fri 2/9/18 3
Project
manager ,
project
sponsors
$2,432.00

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
1.4
Hardware
requirements
collection
5 days
Mon
2/12/18
Fri
2/16/18
4
Operation
manager ,
Project
manager
$1,400.00
1.5
Software
requirements
gathering
6 days
Mon
2/19/18
Mon
2/26/18
5
Operation
manager ,
Project
manager
$1,680.00
1.6
Estimating
project budget
3 days
Tue
2/27/18
Thu
3/1/18
6
finance
manager
$360.00
1.7 Time allotment 5 days Fri 3/2/18
Thu
3/8/18
7
finance
manager,
Project
manager
$1,400.00
1.8
Consideration
of SLA guidelines
6 days Fri 3/9/18
Fri
3/16/18
4,8
Operation
manager
$720.00
2
Milestone 1:
completion of
project initiation
phase
0 days Fri 3/16/18
Fri
3/16/18
9
Project
manager
$0.00
Document Page
8RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
3
Project
planning phase
31 days
Mon
3/19/18
Mon
4/30/18
$5,400.00
3.1
Outlining the
design of the
online ticket
booking system
5 days
Mon
3/19/18
Fri
3/23/18
10
Operation
manager ,s
ystem
developer
$1,200.00
3.2
Collection the
development
elements
6 days
Mon
3/26/18
Mon
4/2/18
12
Operation
manager ,s
ystem
developer
$1,440.00
3.3
Prototype
designing
8 days Tue 4/3/18
Thu
4/12/18
13
system
developer
$960.00
3.4
Prototype
building
3 days Fri 4/13/18
Tue
4/17/18
14
system
developer
$360.00
3.5
Prototype
implementation
12 days Fri 4/13/18
Mon
4/30/18
13,14
system
developer
$1,440.00
4
Milestone 2:
complete project
planning phase
0 days
Mon
4/30/18
Mon
4/30/18
16
Project
manager
$0.00
Document Page
9RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
5
Online ticket
booking system
testing
39 days Tue 5/1/18
Fri
6/22/18
17 $10,880.00
5.1
System unit
testing
6 days Tue 5/1/18
Tue
5/8/18
Operation
manager
$720.00
5.2
Integration
testing
9 days
Wed
5/9/18
Mon
5/21/18
19
Operation
manager ,
Project
manager ,s
ystem
developer
$3,600.00
5.3
Review the
testing phase
8 days
Tue
5/22/18
Thu
5/31/18
20
Operation
manager ,
Project
manager ,s
ystem
developer
$3,200.00
5.4
Field testing of
the designed
prototype
7 days Fri 6/1/18
Mon
6/11/18
14,21
Operation
manager
$840.00
5.5 Testing result 9 days Tue Fri 22 business $2,520.00

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
analysis 6/12/18 6/22/18
analysts ,P
roject
manager
6
Milestone 3:
complete testing
phase
0 days Fri 6/22/18
Fri
6/22/18
23
Project
manager
$0.00
7 Project closure 12 days
Mon
6/25/18
Tue
7/10/18
$3,016.00
7.1
Stakeholders
signoff
5 days
Mon
6/25/18
Fri
6/29/18
24
HR
manager
$600.00
7.2
Final project
documentation
4 days
Mon
7/2/18
Thu
7/5/18
26
Project
manager ,
project
sponsors
$1,216.00
7.3
Post system
maintenance plan
3 days Fri 7/6/18
Tue
7/10/18
27
business
analysts ,
Operation
manager ,
Project
manager
$1,200.00
8 Milestone 4: 0 days Tue Tue 28 Project $0.00
Document Page
11RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Completion of
project closure
phase
7/10/18 7/10/18 manager
Figure 1: Gantt chart for RALS
(Source: created by Author)
Document Page
12RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
1.5 Summary of MOV project
In order to accomplish the Riverina Agricultural Lifestyle Show (RALS), arranged by
Globex Company the project manager is required to measurable Organizational Values
accurately. With the help of online ticket booking system the consumers would be able to look
for the available ticket and booked tickets as well. However, Measurable Organization Values
are helpful for RALS to motivate the staffs and consumers as well to meet the goal properly. In
order to meet the project goal with accurate mission, vision and strategy the MOV are helpful.
Part 2: Development of scope management plan
2.1 List of project scope
The scopes of RASL project development are as follows:
To implement a cheaper, faster and advanced online ticket booking system for the
consumers
To adapt the manual ticket booking approach to advanced online ticket booking
system
To design risk register and quality management plan for the RALS project
2.2 List of project resources
The resource list allotted for the RALS project is as follows:
2.3 Project resource details
Resources Responsibilities

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Project manager The role of the project manager is to control
and monitor the project to complete the project
within estimated time and budget.
Finance manager The role of the finance manager is to develop a
project feasibility to make ensure whether the
project successful or not. Again, the role of the
finance manager is to complete the project
within allotted time phase.
Operation manager The operation manager is responsible to
develop the system with proper operation and
functional excellence.
Business analyst The business analyst is responsible to make
sure that the system is efficient, user friendly
and helping the company to gain effective
benefits.
HR manager Responsible to manage all the project team
members and the project manager accurately.
Part 3: Project schedule and Work Breakdown Structure
3.1 Work Breakdown Structure
Document Page
14RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Figure 2: Work Breakdown Structure for RALS
(Source: created by Author)
3.2 Activities of RALS project
WBS Task Name Duration
0 RALS project scheduling 125 days
1 Project initiation phase 43 days
1.1 Conceptualizing the project 6 days
1.2 Developing project charter 4 days
1.3 Appointing vendors 8 days
Document Page
15RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
1.4 Hardware requirements collection 5 days
1.5 Software requirements gathering 6 days
1.6 Estimating project budget 3 days
1.7 Time allotment 5 days
1.8 Consideration of SLA guidelines 6 days
2
Milestone 1: completion of project
initiation phase
0 days
3 Project planning phase 31 days
3.1
Outlining the design of the online ticket
booking system
5 days
3.2 Collection the development elements 6 days
3.3 Prototype designing 8 days
3.4 Prototype building 3 days
3.5 Prototype implementation 12 days
4
Milestone 2: complete project planning
phase
0 days

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
5 Online ticket booking system testing 39 days
5.1 System unit testing 6 days
5.2 Integration testing 9 days
5.3 Review the testing phase 8 days
5.4 Field testing of the designed prototype 7 days
5.5 Testing result analysis 9 days
6 Milestone 3: complete testing phase 0 days
7 Project closure 12 days
7.1 Stakeholders signoff 5 days
7.2 Final project documentation 4 days
7.3 Post system maintenance plan 3 days
8
Milestone 4: Completion of project
closure phase
0 days
3.3 Project resource identification
Resource
Name
Type
Material
Label
Initials
Max.
Units
Std. Rate Ovt. Rate
Base
Calendar
Document Page
17RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Project
manager
Work P 100% $20.00/hr $18.00/hr Standard
finance
manager
Work f 100% $15.00/hr $12.00/hr Standard
HR manager Work H 100% $15.00/hr $8.00/hr Standard
system
developer
Work s 100% $15.00/hr $14.00/hr Standard
business
analysts
Work b 100% $15.00/hr $12.00/hr Standard
Operation
manager
Work O 100% $15.00/hr $15.00/hr Standard
project
sponsors
Work p 100% $18.00/hr $16.00/hr Standard
Document Page
18RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
3.4 Cost estimation for RALS project
Figure 3: Estimated cost for RALS
(Source: created by Author)
3.5 Time allotted for RALS project
Task Name Duration Start Finish
RALS project scheduling 125 days Wed 1/17/18 Tue 7/10/18
Project initiation phase 43 days Wed 1/17/18 Fri 3/16/18
Conceptualizing the project 6 days Wed 1/17/18 Wed 1/24/18

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Developing project charter 4 days Thu 1/25/18 Tue 1/30/18
Appointing vendors 8 days Wed 1/31/18 Fri 2/9/18
Hardware requirements
collection
5 days Mon 2/12/18 Fri 2/16/18
Software requirements
gathering
6 days Mon 2/19/18 Mon 2/26/18
Estimating project budget 3 days Tue 2/27/18 Thu 3/1/18
Time allotment 5 days Fri 3/2/18 Thu 3/8/18
Consideration of SLA
guidelines
6 days Fri 3/9/18 Fri 3/16/18
Milestone 1: completion of
project initiation phase
0 days Fri 3/16/18 Fri 3/16/18
Project planning phase 31 days Mon 3/19/18 Mon 4/30/18
Outlining the design of the
online ticket booking system
5 days Mon 3/19/18 Fri 3/23/18
Collection the development
elements
6 days Mon 3/26/18 Mon 4/2/18
Document Page
20RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Prototype designing 8 days Tue 4/3/18 Thu 4/12/18
Prototype building 3 days Fri 4/13/18 Tue 4/17/18
Prototype implementation 12 days Fri 4/13/18 Mon 4/30/18
Milestone 2: complete project
planning phase
0 days Mon 4/30/18 Mon 4/30/18
Online ticket booking system
testing
39 days Tue 5/1/18 Fri 6/22/18
System unit testing 6 days Tue 5/1/18 Tue 5/8/18
Integration testing 9 days Wed 5/9/18 Mon 5/21/18
Review the testing phase 8 days Tue 5/22/18 Thu 5/31/18
Field testing of the designed
prototype
7 days Fri 6/1/18 Mon 6/11/18
Testing result analysis 9 days Tue 6/12/18 Fri 6/22/18
Milestone 3: complete testing
phase
0 days Fri 6/22/18 Fri 6/22/18
Project closure 12 days Mon 6/25/18 Tue 7/10/18
Stakeholders signoff 5 days Mon 6/25/18 Fri 6/29/18
Final project documentation 4 days Mon 7/2/18 Thu 7/5/18
Document Page
21RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Post system maintenance plan 3 days Fri 7/6/18 Tue 7/10/18
Milestone 4: Completion of
project closure phase
0 days Tue 7/10/18 Tue 7/10/18
Part 4: Project risk analysis and planning
4.1 Developing project risk management
Phases Risk Probability Frequency Responsib
le person
Resolving strategy
Project
initiation
Improper
feasibility
Very High Frequent Project
manager
and
finance
manager
In order to avoid this
particular issue, the
finance manager should
make proper feasibility
study and that must be
approved by the project
manager
Planning Incorrect
selection
of
component
s
High Very
Frequent
System
developer
and project
manager
The system developers
should adopt all the
appropriate components
those are necessary for the
development of the online
ticket booking system

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
22RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
arranged by Globex
Company
Executio
n
Lack of
security
High Frequent Operation
manager
and system
developer
In order to avoid the issues
of online payment security
is the most important thing
that should have to be
considered by the system
developer and the
operation manager. Proper
security sources in terms
of password protection,
encryption, firewall etc.
Closure Maintenan
ce issue
Medium Frequent Project
manager
Even after the
implementation of the
system, the project
manager should make sure
that the system is
maintaining properly to
avoid system operational
and functional issues.
Document Page
23RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Part 5: Quality management plan
5.1 Team philosophy for the RALS project
For any project the mission, vision and strategies almost remain the same with very small
changes. The aim of RALS project is to deliver faster, cheaper, better, secured, user friendly and
advanced online ticket booking system to the users. It will help the company to grab more
number of consumers by reducing the size of the queue.
5.2 Quality assurance
Phases Activities
Verification activity Requirements collection from different sources
to develop the online ticket booking system for
RALS.
Analysis of the collected data
Development of service level agreement the
system that has to be developed
Development of the prototype model
Validation activity Addition of programming and coding to the
system to make it efficient
System testing
Consideration of components needed to
develop the online ticket booking system
Final document for RALS project
Document Page
24RIVERINA AGRICULTURAL LIFESTYLE SHOW (RALS)
Part 6: Closure checklist development
Project activities Person responsible Signature
Initiation phase Project manager and sponsors <Please fill>
Planning Project manager <Please fill>
Budget estimation Finance manager <Please fill>
Time management program Project manager and operation
manager
<Please fill>
System prototype
development
System developer and
business analyst
<Please fill>
6.2 Outlining the project closure plan
It is expected that after successful completion of the project the system and the company
will be able to meet the followings:
Passes will be available for each three days and for all the three days
Family passes will be available
Passes are available for stall holders, student and kinds with offered price
Number of sold tickets can be tracked
Remaining number of tickets can be traced accordingly
1 out of 25
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]