This lab assignment focuses on designing a VSC interfaced DG unit to supply real and reactive power to the grid. It also involves simulating and analyzing the results. The assignment includes steps, calculations, and simulation results. Subject: Smart Grid Systems, Course Code: SEE717, College/University: Not mentioned
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
SEE717 – SMART GRID SYSTEMS ASSIGNMENT NO: 4 NAME: FAREED STUDENT ID: 218669759 Laboratory Work #4 OBJECTIVES OF THE LAB ASSIGNMENT To design a VSC interfaced DG unit to supply real and reactive power to the grid.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
To Simulate andanalyse the results. INTRODUCTION Minor scale generation units 1kW-50Mw that yield electricity adjacent to the users or that are linked to the spread network are denoted to as distributed generators. In recent times, countless research have been embarked on to learn the influence of distributed generators on the nationwide grid. Over and above, new expertise have been thought up on which distributed generation can realized. This is because distributed generation has a number of recipients. Some of the dynamics that have steered to development of distributed generation or embedded generators take account of: Improved concentration in cogeneration and collective heat power generation. Improved concentration in renewable generation. Denationalization and new entrants in the power generation. DESCRIPTION OF THE ASSIGNMENT In this lab assignment we are required to model a small smart grid system as shown in figure 1 above in sim power system and perform load flow analysis on the power system. In the first part we are going to perform load flow on the power system as it exist. In the second part of the power system we will introduce PV and wind generators at zones B and C respectively to meet the following demands: Loss should be less than the existing case. Twenty percent of the total real power load demand is required to be supplied by the renewable energy resources. The voltage magnitude at each of the zones are required to be maintained with in ±2% of the rated or base voltage. The voltage angle of the zones are required to be maintained such that at least stability margin of 80 degrees is maintained. TASK PART A
Detail description of the steps and calculations to complete this design. Figure1: One-line diagram of the power network FORMULATION OF THE POWER SYSTEM In our formulation we will assume that all the four buses are on the same voltage level that is 11kV. Our problem will be determine the load flow of the system in simpowersystem. We will obtain the equivalent active and reactive ratings of the loads at zones A, B and C. P=S∗cosθ=S∗powerfactor Q=√S2−P2 The load values can be summarised as shown below: ZONE LOADAPPARENT POWER MVA POWER FACTOR LAGGING ACTIVE POWER MW REACTIVE POWER MVAR A50.954.751.561 B70.946.582.388 C70.946.582.388 The line impedance of the power system can be calculated as follows: Vbasekv=11, Sbase MVA=100, Zline=Zperkm∗Lengthoftheline Zact=Zpu∗Zbase
Zbase=Vbasekv2 Sbase=112 100=1.21Ω The line parameters can be summarised as shown below: LINELINE PARAMETERS in (p.u.) ACTUAL LINE PARAMETERS A0.003+j0.150.00363+j0.1815 B0.0015+j0.0750.001815+j0.09075 C0.0008+j0.040.000968+j0.0484 The line inductance can be calculated as: f=50Hz L=Xl 2∗π∗f The line inductance were obtained as 0.5777, 0.2889 and 0.1541 mH for lines connecting Zones A, zone B and zone C respectively. We built the power in simpowersytem as shown below: Figure2: The small power network in simpowersystem The simulation was then ran and load flow analysis was then performed by clicking powergui>>tools>>load flow. A report was then generated. The results are as shown below. SIMULATION RESULTS The Load Flow converged in 1 iteration!
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
SUMMARY for subnetwork No 1 Total generation: P=17.44 MW Q=6.85 Mvar Total PQ load: P=0.00 MW Q=-0.00 Mvar Total Zshunt load: P=17.43 MW Q=6.16 Mvar Total ASM load: P=0.00 MW Q=0.00 Mvar Total losses: P=0.01 MW Q=0.69 Mvar 1: generator bus V= 1.000 pu/11kV 0.00 deg; Swing bus Generation: P=17.44 MW Q=6.85 Mvar PQ_load: P=0.00 MW Q=0.00 Mvar Z_shunt: P=-0.00 MW Q=-0.00 Mvar --> zone A: P=17.44 MW Q=6.85 Mvar 2 : zone A V= 0.990 pu/11kV -1.50 deg Generation : P=0.00 MW Q=0.00 Mvar PQ_load: P=0.00 MW Q=-0.00 Mvar Z_shunt: P=4.65 MW Q=1.53 Mvar --> generator bus : P= -17.43 MW Q=-6.33 Mvar --> zone B: P=12.78 MW Q=4.80 Mvar 3 : zone B V= 0.986 pu/11kV -2.06 deg Generation : P=0.00 MW Q=0.00 Mvar PQ_load: P=0.00 MW Q=-0.00 Mvar Z_shunt: P=6.39 MW Q=2.32 Mvar --> zone A: P= -12.78 MW Q=-4.66 Mvar --> zone C: P=6.38 MW Q=2.33 Mvar 4 : zone C V= 0.985 pu/11kV -2.21 deg Generation : P=0.00 MW Q=0.00 Mvar PQ_load: P=0.00 MW Q=0.00 Mvar Z_shunt: P=6.38 MW Q=2.32 Mvar --> zone B: P=-6.38 MW Q=-2.32 Mvar DISCUSSION
From the results shown above it can be observed that the active power loss and reactive power loss were obtained as Mw and Mvar respectively. The real and reactive power balance across the power system can summarized as shown in the table below: LOCATIONACTIVE POWERREACTIVE POWER GENERATOR17.446.85 ZONE A17.436.33 ZONE B12.784.66 ZONE C6.382.32 The voltage levels at the four buses can be summarised as shown below: LOCATIONVOLTAGE MAGNITUDE p.u PHASE ANGLE GENERATOR1.0000.00 ZONE A0.990-1.50 ZONE B0.986-2.06 ZONE C0.985-2.21 From the report it can also be observed that the phase angle of the voltage was about -2.21 across the power system. TASK PART B: ) Simulation results and analysis of the results. Figure3: Power network with distributed generators added to it The amount of active power supplied by each distributed energy source can be calculated as
follows: PB=PC=0.2∗0.5∗(5+7+7)∗106W=1.9MW We then built the network in simpowersystem as shown below in the figure below: Figure4: The new power network with distributed generators We repeated the steps as stated in task Part A to determine the load flow of the system. That is, the simulation was then ran and load flow analysis was then performed by clicking powergui>>tools>>load flow. A report was then generated.We obtained the results as summarized below: The Load Flow converged in 2 iterations! SUMMARY for subnetwork No 1 Total generation: P=17.91 MW Q=6.71 Mvar Total PQ load: P=-0.00 MW Q=-0.00 Mvar Total Zshunt load: P=17.90 MW Q=6.33 Mvar Total ASM load: P=0.00 MW Q=0.00 Mvar Total losses: P=0.01 MW Q=0.37 Mvar 1: generator bus V= 1.000 pu/11kV 0.00 deg ; Swing bus Generation: P=14.11 MW Q=0.48 Mvar PQ_load: P=0.00 MW Q=0.00 Mvar Z_shunt: P=-0.00 MW Q=-0.00 Mvar --> zone A: P=14.11 MW Q=0.48 Mvar 2: zone A V= 0.999 pu/11kV -1.21 deg Generation: P=0.00 MW Q=0.00 Mvar
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PQ_load: P=-0.00 MW Q=-0.00 Mvar Z_shunt: P=4.74 MW Q=1.56 Mvar --> generator bus : P= -14.10 MW Q=-0.18 Mvar --> zone B: P=9.36 MW Q=-1.38 Mvar 3 : zone B V= 1.000 pu/11kV -1.62 deg Generation : P=1.90 MW Q=3.74 Mvar PQ_load: P=0.00 MW Q=0.00 Mvar Z_shunt: P=6.58 MW Q=2.39 Mvar --> zone A: P=-9.36 MW Q=1.44 Mvar --> zone C: P=4.68 MW Q=-0.09 Mvar 4 : zone C V= 1.000 pu/11kV -1.72 deg Generation : P=1.90 MW Q=2.49 Mvar PQ_load: P=0.00 MW Q=0.00 Mvar Z_shunt: P=6.58 MW Q=2.39 Mvar --> zone B: P=-4.68 MW Q=0.10 Mvar DISCUSSION From the report generated it was observed that power flow across the network was as shown in the table below: LOCATIONACTIVE POWERREACTIVE POWER GENERATOR14.110.48 ZONE A4.741.56 ZONE B6.582.39 ZONE C6.582.39 The voltage levels at the four buses can be summarised as shown below: LOCATIONVOLTAGE MAGNITUDE p.u PHASE ANGLE GENERATOR10 ZONE A0.999-1.21 ZONE B1-1.62 ZONE C1-1.72 It was observed that the total active and reactive power loss was 0.01 and 0.37 respectively.
From the report it can also be observed that the voltage was about -1.72 across the power system which meets the demands of the installation of DGs. Therefore the design specifications all met by incorporating distributed generators to the small power network. CONCLUSION In conclusion, we were able the design specifications of the smart grid system, therefore the objectives of the experiment were met. Therefore we can conclude that the objectives of the lab assignment were met.