SIB Project
Implementation
SIB Project Implementation_1

Project Objectives
DWS is a fast-growing
SME in Singapore

DWS has planned to
work on the smart
building project

DWS has secured a
project to implement a
smart building system

The project needs to
start of September 2,
2019

The project is required
to be completed early
in January 2020

However, the
preferable completion
date of the project is
December 26, 2019
SIB Project Implementation_2

Project Priorities
The priorities of the project are indicated as
follows-

o The SIB project needs to comply with the
IMDA’s requirement

o The project should have a CPI of at least 1

o Therefore, cost and the performance of the
project are two top most project priorities
SIB Project Implementation_3

Meeting Project Objectives
and Priorities

After the execution of the project, a few of the
priorities and the objectives of the project are met.

However, the project could not be implemented
with a CPI of 1 as the CPI turned out to be .97

The project could not be completed within
December 26 as it is completed in January 3, 2019
SIB Project Implementation_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Five Step Team Development Model
|2
|573
|47

CMP Project Management Report
|12
|495
|22

Project Management: HPSS Case Study
|6
|1195
|165

Project Management.
|9
|413
|175

Case Study on Driverless taxi system Assignment
|15
|800
|34