This document provides an overview of the software test documentation for an Online Backstage Management system. It includes information on the system overview, test approach, test plan, features to be tested, features not to be tested, testing tools and environment, test cases, Gantt chart, and budget.
Contribute Materials
Your contribution can guide someoneâs learning journey. Share your
documents today.
Running head:SOFTWARE TEST DOCUMENTATION Software Test Documentation Name of the Student Name of the University Authorâs note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1SOFTWARE TEST DOCUMENTATION Table of Contents Introduction:....................................................................................................................................2 System Overview:........................................................................................................................2 Test Approach:.............................................................................................................................3 Test Plan:.........................................................................................................................................4 Features to Be Tested:.................................................................................................................4 Features not to Be Tested:...........................................................................................................4 Testing Tools and Environment:.................................................................................................5 Test Cases:.......................................................................................................................................5 Gantt Chart:.....................................................................................................................................7 Budget:.............................................................................................................................................8 Bibliography:.................................................................................................................................13
2SOFTWARE TEST DOCUMENTATION Introduction: System Overview: The proposed system is an Online Backstage Management system. The system has been proposed for Royal South Street Society. The system has been proposed for converting the present paper based manual works into automatic processes. The system handles the competitors and their outcomes. The proposed system can be accessed from web browsers. The system will share the information to all the authorized users. The system will collecting data from various devices used by the end users and store it into a database management system. As the system will be deployed in the cloud environment, it can be easily accessed by all the users from remote locations. This eliminates the need of transferring files from one location to other manually. The system will significantly reduce the task completion time by allowing the end users to access data from any location and the system will automatically execute the back office processes. The system will be extremely dynamic and deployment in the cloud environment will increase the scalability of operations hugely. The system will circulate the information to all the end users suchasstagemanager,chairman,frontofhouseandadjudicatorsthroughwireless communication medium. The system will have an advance feature named adjustable screens. The user management will be integrated in the system through the login and registration process. The registration is for collecting personal and contact related data from the end users. The system administrator will be responsible for controlling the registration in the system. Without the approval of the system administrator, no user can complete system registration process. The system will provide high quality graphical user interface to the end users. Each user will get a screen, to communicate with the system, which will be designed and developed based
3SOFTWARE TEST DOCUMENTATION on the interactions user will do with the system. The Online Backstage Management System will be connected to a database management system. This database will further be connected to a backup/restore system. The system will provide opportunityto find the historic data easily and it maintains the integrity of data through the backup/restore approach. TheOnline Backstage Management System is developed based on the Object Oriented approach. The Java Server Pages has been used for the silverside scripting and JavaScript for client side scripting. MySQL database management system has been selected to implementing the database.Jasper Reports will allow the system to create reports in HTML, CSV, XML, PDF, Word and many other formats. Many other technologies has been used for developing the system but the above mentioned ones are the core technologies that enables the system to function. The modules of the system are Database, Core Data, Registration, Authentication, Results, Guide Book Import, Administration, Configurable screens, Reports, Search, Help, Users/Roles and Template/Design. Test Approach: The website testing can be referred as the software testing practice applied on websites. This test has the main criteria of finding bugs in the website code. From the base structure of the system to high level functionality are to be tested for Online Backstage Management System. The test approach will consisting of the following criteria. i.Functionality Testing ii.Usability testing iii.Interface testing iv.Compatibility testing
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4SOFTWARE TEST DOCUMENTATION v.Performance testing vi.Security testing Test Plan: Features to Be Tested: In the functionality testing, all the links in web pages, database connection, forms used for submitting or getting information from the user in the web pages, Cookie testing and many more. The usability testing another essential testing factor for theOnline Backstage Management System. The usability testing will allow the organization to find gaps in the human computer interactionof the system. This will include ease of learning, navigation,subjective user satisfaction and general appearance. Interface testing is done for checking the quality of server side interface. This testing approach iscompleted by validating that the communication is executed appropriately. The main interfaces of theOnline Backstage Management Systemare Webserver andapplicationserver interfaceand ApplicationserverandDatabaseserver interface. Compatibility testing includes Browser compatibility, Operating system compatibility, Mobile browsing and Printing options. The performance testing is done by checking how much load theOnline Backstage Management System can handle during its lifecycle. Web Load Testing and Web Stress Testing are the parts of performance testing. The final test approach is the security testing. It is done to check whether the Online Backstage Management System is capable of preventing the security threats.
5SOFTWARE TEST DOCUMENTATION Features not to Be Tested: The maintenance of the user records will not be tested for Online Backstage Management System. Another feature that will not be tested is Stage Configuration. The final feature that will not be tested is data maintenance of the competitors. Testing Tools and Environment: The Ranorex Studio will be used for testing the system functionality. It has a graphical user interface so that users can easily interpret what are the outcome of testing. It supports reliable object identification. USABILLA tool will be used for testing the usability of the system. TestingWhiz will be used for testing the interface of the system. TestingWhiz is a web UI automation testing tool for validating UI of the web applications & front-end to confirm its accurateappearanceacrossdifferentbrowsers,platformsanddevices. CrossBrowserTesting.Com is a great for testing the compatibility of the Online Backstage Management System. Apache JMeter is used for testing the performance of the system. Apache JMeter is an open source, cross-platform Apache project that is developed to analyze and measure software application performance. In order to test the security of the Online Backstage Management System, Vega tool will be used.It is a vulnerability scanning and testing tool written in Java. It works with OS X, Linux and Windows platforms. The URL to the tool is https://subgraph.com/vega/. Test Cases: Checking links:The purpose of the test is to check whether all the links are working. The inputs are the links available in the website. The expected outcome is that all links are working. The outcome will be done based on internal links, external links, mail links and broken links.
6SOFTWARE TEST DOCUMENTATION The test will fail if any links are not working. The test will be done by accessing all the links available in the Online Backstage Management System. Test Forms on All Pages:The form testing is done to check whether all the form validation is working, checking defaults values, wrong input acceptance and functionality of form create, update and delete processes. The input for the test is form name and data in the forms. The expected outcome is that all the forms are working properly and it can validate the user input. The test will be done by accessing the OBMS in a web browser and submitting the forms. Checking navigation:The purpose of the test is to check how easily the user can access the system. The inputs of the test are access patterns, contents, learnability and few more. The expected outcome is that user can access the required information or page in just three clicks. The user can easily understand the purpose of the page. Hints throughout theOnline Backstage Management System so that user can learn how to use the system quickly. Connection Testing:The purpose of the test is toverify that communication is done properly. The input is the conditions that allows the servers to communicate. The expected outcome is that server will be providing valid error messages and respond to request from other servers. The test will be done in the server where the system is deployed.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7SOFTWARE TEST DOCUMENTATION Gantt Chart: IDTask Mode Outline Number Task NameDurationStartFinishPredecessorsResource NamesCost 00Online Backstage Manageemnt System 332 daysThu 5/30/19Fri 9/4/20$1,240,000.00 11start project0 daysThu 5/30/19Thu 5/30/19Project Manager$0.00 22Internal Analysis of Wilson Jones6 daysThu 5/30/19Thu 6/6/19$88,000.00 32.1Gather relevant information2 daysThu 5/30/19Fri 5/31/191Customer Service Manager,Marketing Manager,Project Manager,Project Sponsor,Sales Manager$30,000.00 42.2Requirement analysis of Online Backstage Management System 2 daysMon 6/3/19Tue 6/4/193Customer Service Manager,Marketing $28,000.00 52.3identify the requirement of OBMS 2 daysWed 6/5/19Thu 6/6/194Customer Service Manager,Marketing $30,000.00 63CRM deployment plan12 daysFri 6/7/19Mon 6/24/19$12,000.00 73.1develop project scope2 daysFri 6/7/19Mon 6/10/195Deployment team,Employees,Project Manager,Wilson & Jones IT Manager$2,000.00 83.2Develop resource planning2 daysTue 6/11/19Wed 6/12/197Deployment team,Employees,Project Manager,Wilson & Jones IT Manager$2,000.00 93.3develop budget2 daysThu 6/13/19Fri 6/14/198Deployment team,Employees,Project Manager,Wilson & Jones IT Manager$2,000.00 103.4develop schedule2 daysMon 6/17/19Tue 6/18/199Deployment team,Employees,Project Manager,Wilson & Jones IT Manager$2,000.00 113.5develop change management plan 2 daysWed 6/19/19Thu 6/20/1910Deployment team,Employees,Project Manager,Wilson $2,000.00 123.6develop risk management plan2 daysFri 6/21/19Mon 6/24/1911Deployment team,Employees,Project Manager,Wilson & Jones IT Manager$2,000.00 134Business planning for CRM8 daysTue 6/25/19Thu 7/4/19$10,000.00 144.1Audit of existing process2 daysTue 6/25/19Wed 6/26/1912Marketing Manager,Project Manager,Sales Manager$2,500.00 154.2Optimization of processes2 daysThu 6/27/19Fri 6/28/1914Marketing Manager,Project Manager,Sales Manager$2,500.00 164.3define specifications2 daysMon 7/1/19Tue 7/2/1915Marketing Manager,Project Manager,Sales Manager$2,500.00 174.4Selection of Deloyment Environment 2 daysWed 7/3/19Thu 7/4/1916Marketing Manager,Project Manager,Sales $2,500.00 185System configuration of CRM8 daysFri 7/5/19Tue 7/16/19$60,000.00 195.1Analyze and Identify the hardware requirements of OBMS 2 daysFri 7/5/19Mon 7/8/1917Software designer,Wilson & Jones IT $15,000.00 205.2Contract Vendor to enquire about hardware 2 daysTue 7/9/19Wed 7/10/1919Software designer,Wilson & Jones IT $15,000.00 215.3Enquire networking capability of vendor 2 daysThu 7/11/19Fri 7/12/1920Software designer,Wilson & Jones IT $15,000.00 225.4develop the customization document 2 daysMon 7/15/19Tue 7/16/1921Software designer,Wilson & Jones IT $15,000.00 236Data acquisition8 daysWed 7/17/19Fri 7/26/19$50,000.00 246.1obtain data2 daysWed 7/17/19Thu 7/18/1922Project Manager,Wilson & Jones IT Manager$30,000.00 256.2review data2 daysFri 7/19/19Mon 7/22/1924Project Manager,Wilson & Jones IT Manager$5,000.00 266.3data screening and editing2 daysTue 7/23/19Wed 7/24/1925Project Manager,Wilson & Jones IT Manager$5,000.00 276.4prepare data migration2 daysThu 7/25/19Fri 7/26/1926Project Manager,Wilson & Jones IT Manager$10,000.00 287implementation of OBMS140 daysMon 7/29/19Fri 2/7/20$320,000.00 297.1prerequisites verification15 daysMon 7/29/19Fri 8/16/1927Deployment team,Employees,Software designer,Wilson & Jones IT Manager$25,000.00 307.2hardware deployment20 daysMon 8/19/19Fri 9/13/1929Deployment team,Employees,Software designer,Wilson & Jones IT Manager$50,000.00 317.3software deployment and licenses 20 daysMon 9/16/19Fri 10/11/1930Deployment team,Employees,Software designer,Wilson $95,000.00 327.4develop UI30 daysMon 10/14/19Fri 11/22/1931Deployment team,Employees,Software designer,Wilson & Jones IT Manager$20,000.00 337.5Customization of the CRM30 daysMon 11/25/19Fri 1/3/2032Deployment team,Employees,Software designer,Wilson & Jones IT Manager$110,000.00 347.6integration of the data source25 daysMon 1/6/20Fri 2/7/2033Deployment team,Employees,Software designer,Wilson & Jones IT Manager$20,000.00 358Deployment of OBMS55 daysMon 2/10/20Fri 4/24/20$550,000.00 368.1system configuration of OBMS10 daysMon 2/10/20Fri 2/21/2034Deployment team,Employees,Software designer,Wilson & Jones IT Manager$75,000.00 378.2Develop Websute UI10 daysMon 2/24/20Fri 3/6/2036Deployment team,Employees,Software designer,Wilson & Jones IT Manager$5,000.00 388.3Develop the Client Side Scripting5 daysMon 3/9/20Fri 3/13/2037Deployment team,Employees,Software designer,Wilson & Jones IT Manager$5,000.00 398.4Coding the server side scripting 5 daysMon 3/16/20Fri 3/20/2038Deployment team,Employees,Software designer,Wilson $5,000.00 408.5developing system views5 daysMon 3/23/20Fri 3/27/2039Deployment team,Employees,Software designer,Wilson & Jones IT Manager$5,000.00 418.6design dashboard15 daysMon 3/30/20Fri 4/17/2040Deployment team,Employees,Software designer,Wilson & Jones IT Manager$5,000.00 428.7Integrate the secuerity tools in OBMS 5 daysMon 4/20/20Fri 4/24/2041Deployment team,Employees,Software designer,Wilson $450,000.00 439Testing Phase35 daysMon 4/27/20Fri 6/12/20$75,000.00 449.1system test7 daysMon 4/27/20Tue 5/5/2042Deployment team,Wilson & Jones IT Manager$15,000.00 459.2infrastructure test7 daysWed 5/6/20Thu 5/14/2044Deployment team,Wilson & Jones IT Manager$15,000.00 469.3pilot test7 daysFri 5/15/20Mon 5/25/2045Deployment team,Wilson & Jones IT Manager$15,000.00 479.4Black box test7 daysTue 5/26/20Wed 6/3/2046Deployment team,Wilson & Jones IT Manager$15,000.00 489.5user acceptance test7 daysThu 6/4/20Fri 6/12/2047Deployment team,Wilson & Jones IT Manager$15,000.00 4910Support and training42 daysMon 6/15/20Tue 8/11/20$25,000.00 5010.1Administrator training7 daysMon 6/15/20Tue 6/23/2048Employees,Project Manager$5,000.00 5110.2user training7 daysWed 6/24/20Thu 7/2/2050Employees,Project Manager$5,000.00 5210.3develop quality manuals7 daysFri 7/3/20Mon 7/13/2051Employees,Project Manager$1,000.00 5310.4develop process flow7 daysTue 7/14/20Wed 7/22/2052Employees,Project Manager$2,000.00 5410.5develop guidelines and policies7 daysThu 7/23/20Fri 7/31/2053Employees,Project Manager$2,000.00 5510.6help desk support7 daysMon 8/3/20Tue 8/11/2054Employees,Project Manager$10,000.00 5611Go Live3 daysWed 8/12/20Fri 8/14/20$50,000.00 5711.1migrate all data2 daysWed 8/12/20Thu 8/13/2055Sales Manager,Wilson & Jones IT Manager$30,000.00 5811.2system handover1 dayFri 8/14/20Fri 8/14/2057Sales Manager,Wilson & Jones IT Manager$20,000.00 5912closedown and review15 daysMon 8/17/20Fri 9/4/20$0.00 6012.1Post implementation review2 daysMon 8/17/20Tue 8/18/2058Project Manager$0.00 6112.2technical support2 daysWed 8/19/20Thu 8/20/2060Project Manager$0.00 6212.3communication plan review2 daysFri 8/21/20Mon 8/24/2061Project Manager$0.00 6312.4develop end of project report2 daysTue 8/25/20Wed 8/26/2062Project Manager$0.00 6412.5change management review5 daysThu 8/27/20Wed 9/2/2063Project Manager$0.00 6512.6verify document distribution1 dayThu 9/3/20Thu 9/3/2064Project Manager$0.00 6612.7project signoff1 dayFri 9/4/20Fri 9/4/2065Project Manager$0.00 6713stop project0 daysFri 9/4/20Fri 9/4/2066Project Manager$0.00 5/30 Customer Service Manager,Marketing Manager,Project Manager,Project Sponsor,Sales Manager Customer Service Manager,Marketing Manager,Project Manager,Project Sponsor,Sales Manager Customer Service Manager,Marketing Manager,Project Manager,Project Sponsor,Sales Manager Deployment team,Employees,Project Manager,Wilson & Jones IT Manager Deployment team,Employees,Project Manager,Wilson & Jones IT Manager Deployment team,Employees,Project Manager,Wilson & Jones IT Manager Deployment team,Employees,Project Manager,Wilson & Jones IT Manager Deployment team,Employees,Project Manager,Wilson & Jones IT Manager Deployment team,Employees,Project Manager,Wilson & Jones IT Manager Marketing Manager,Project Manager,Sales Manager Marketing Manager,Project Manager,Sales Manager Marketing Manager,Project Manager,Sales Manager Marketing Manager,Project Manager,Sales Manager Software designer,Wilson & Jones IT Manager Software designer,Wilson & Jones IT Manager Software designer,Wilson & Jones IT Manager Software designer,Wilson & Jones IT Manager Project Manager,Wilson & Jones IT Manager Project Manager,Wilson & Jones IT Manager Project Manager,Wilson & Jones IT Manager Project Manager,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Employees,Software designer,Wilson & Jones IT Manager Deployment team,Wilson & Jones IT Manager Deployment team,Wilson & Jones IT Manager Deployment team,Wilson & Jones IT Manager Deployment team,Wilson & Jones IT Manager Deployment team,Wilson & Jones IT Manager Employees,Project Manager Employees,Project Manager Employees,Project Manager Employees,Project Manager Employees,Project Manager Employees,Project Manager Sales Manager,Wilson & Jones IT Manager Sales Manager,Wilson & Jones IT Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager 9/4 3/107/711/33/16/2810/25 September 1May 1January 1September 1
8SOFTWARE TEST DOCUMENTATION Budget: Task NameCost Online Backstage Management System$1,240,000.00 start project$0.00 Internal Analysis of Wilson Jones$88,000.00 Gather relevant information$30,000.00 Requirement analysis of Online Backstage Management System $28,000.00 identify the requirement of OBMS$30,000.00 CRM deployment plan$12,000.00 develop project scope$2,000.00 Develop resource planning$2,000.00 develop budget$2,000.00 develop schedule$2,000.00 develop change management plan$2,000.00 develop risk management plan$2,000.00 Business planning for CRM$10,000.00 Audit of existing process$2,500.00
9SOFTWARE TEST DOCUMENTATION Optimization of processes$2,500.00 define specifications$2,500.00 Selection of Deployment Environment$2,500.00 System configuration of CRM$60,000.00 Analyze and Identify the hardware requirements of OBMS $15,000.00 Contract Vendor to enquire about hardware$15,000.00 Enquire networking capability of vendor$15,000.00 develop the customization document$15,000.00 Data acquisition$50,000.00 obtain data$30,000.00 review data$5,000.00 data screening and editing$5,000.00 prepare data migration$10,000.00 implementation of OBMS$320,000.00 prerequisites verification$25,000.00 hardware deployment$50,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10SOFTWARE TEST DOCUMENTATION software deployment and licenses$95,000.00 develop UI$20,000.00 Customization of the CRM$110,000.00 integration of the data source$20,000.00 Deployment of OBMS$550,000.00 system configuration of OBMS$75,000.00 Develop Website UI$5,000.00 Develop the Client Side Scripting$5,000.00 Coding the server side scripting$5,000.00 developing system views$5,000.00 design dashboard$5,000.00 Integrate the security tools in OBMS$450,000.00 Testing Phase$75,000.00 system test$15,000.00 infrastructure test$15,000.00 pilot test$15,000.00
11SOFTWARE TEST DOCUMENTATION Black box test$15,000.00 user acceptance test$15,000.00 Support and training$25,000.00 Administrator training$5,000.00 user training$5,000.00 develop quality manuals$1,000.00 develop process flow$2,000.00 develop guidelines and policies$2,000.00 help desk support$10,000.00 Go Live$50,000.00 migrate all data$30,000.00 system handover$20,000.00 closedown and review$0.00 Post implementation review$0.00 technical support$0.00 communication plan review$0.00 develop end of project report$0.00
13SOFTWARE TEST DOCUMENTATION Bibliography: [1]Cholil, M.F. and Wagyana, A., âRancang Bangun Media Player Pada Layanan Aplikasi TV Streaming Program Studi Broadband Multimedia âPSBM TVâ,âTESLA: Jurnal Teknik Elektro,20(2), pp.150-162. 2019. [2]Memon, P., Hafiz, T., Bhatti, S. and Qureshi, S.S., âComparative Study of Testing Tools Blazemeter and Apache JMeter,âSukkur IBA Journal of Computing and Mathematical Sciences,2(1), pp.70-76, 2018. [3]Nigam, C. and Malik, S., âComparative Analysis of Automation Testing Tools,âIITM Journal of Information Technology, p.45, 2018. [4]Sabaren, L.N., Mascheroni, M.A., Greiner, C.L. and IrrazĂĄbal, E., âA Systematic Literature Review in Cross-browser Testing,âJournal of Computer Science & Technology,18,2018.