The project status report determines the variance rate.It is calculated that the planned date and actual date of the construction work are not Project status management details WBS and task description Status planned Actual % completed Start date Finish date Start date Finish date 1.1 Landscaping 1.1.1 Site selection and timeline setup 25% 26th February, 2020 3th March, 2020 26th February, 2020 10th March, 2020 1.1.3 Addition of ornamental features through tree plantation 35% 2nd March, 2020 10th March, 2020 2
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: STATUS REPORT
Status Report
Name of the University:
Course name:
Project name: Dream Home construction Project Status Report
Status Report
Name of the University:
Course name:
Project name: Dream Home construction Project Status Report
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT PLANNING
Table of Contents
Project Description..........................................................................................................................2
Status summary................................................................................................................................2
Project status details........................................................................................................................3
Earned values report........................................................................................................................6
Projection.........................................................................................................................................6
Table of Contents
Project Description..........................................................................................................................2
Status summary................................................................................................................................2
Project status details........................................................................................................................3
Earned values report........................................................................................................................6
Projection.........................................................................................................................................6
2PROJECT MANAGEMENT PLANNING
Project Description
Project status report developed for the Dream Home construction project demonstrates
details of cost and time distribution. In order to complete the construction work within assigned
time and cost, periodic reporting to the supervisor is essential. The construction work will take
place in the riverfront location of Canada and in order to let the project team realize the activity
distribution throughout, a detail Work Breakdown Structure (WBS) and a Gantt chart is
presented. The status report will help the stakeholders and team associates familiar regarding its
status.
Status summary
The project will initiate from 25th February, 2020 and of all the applications are properly
done throughout then the project planning will be successfully completed within 27th March.
Though, the construction work will take approximately 14 months from March after the plan is
approved by the clients and project sponsor.
The project status report will be delivered to the clients with an interval of 3 months for
each. Respectively after completion of 25%, 50% and 75% of the project the status report will be
designed and deliver to the client and sponsor for final approval. The raw materials that the
project team will use to construct the dream home are also part of the project status report. Again
before final initiation of the dream home project each material will be tested. The project status
report determines the variance rate. It is calculated that the planned date and actual date of the
construction work are not
Project Description
Project status report developed for the Dream Home construction project demonstrates
details of cost and time distribution. In order to complete the construction work within assigned
time and cost, periodic reporting to the supervisor is essential. The construction work will take
place in the riverfront location of Canada and in order to let the project team realize the activity
distribution throughout, a detail Work Breakdown Structure (WBS) and a Gantt chart is
presented. The status report will help the stakeholders and team associates familiar regarding its
status.
Status summary
The project will initiate from 25th February, 2020 and of all the applications are properly
done throughout then the project planning will be successfully completed within 27th March.
Though, the construction work will take approximately 14 months from March after the plan is
approved by the clients and project sponsor.
The project status report will be delivered to the clients with an interval of 3 months for
each. Respectively after completion of 25%, 50% and 75% of the project the status report will be
designed and deliver to the client and sponsor for final approval. The raw materials that the
project team will use to construct the dream home are also part of the project status report. Again
before final initiation of the dream home project each material will be tested. The project status
report determines the variance rate. It is calculated that the planned date and actual date of the
construction work are not
3PROJECT MANAGEMENT PLANNING
Project status details
WBS and task
description
Status planned Actual
%
completed
Start date Finish date Start date Finish date
1.1 Landscaping
1.1.1 Site selection Site
supervision and
government permission
23% 25th
February,
2020
29th
February,
2020
25th
February,
2020
28th
February,
2020
1.1.2 Feasibility
analysis and timeline
setup
25% 26th
February,
2020
3th March,,
2020
26th
February,
2020
10th
March,,
2020
1.1.3 Addition of
ornamental features
through tree plantation
35% 2nd March,
2020
10th March,
2020
2nd March,
2020
8th March,
2020
1.2 House structure
1.2.1 Concrete 45% 27th
February,
2020
4th March,
2020
27th
February,
2020
14th March,
2020
1.2.2 Floor, slab and
roof structure
presentation
35% 16th March,
2020
24th May,
2020
16th March,
2020
20th May,
2020
1.2.3 Selecting best
construction tools
20% 16th March,
2020
28th May,
2020
16th March,
2020
25th May,
2020
Project status details
WBS and task
description
Status planned Actual
%
completed
Start date Finish date Start date Finish date
1.1 Landscaping
1.1.1 Site selection Site
supervision and
government permission
23% 25th
February,
2020
29th
February,
2020
25th
February,
2020
28th
February,
2020
1.1.2 Feasibility
analysis and timeline
setup
25% 26th
February,
2020
3th March,,
2020
26th
February,
2020
10th
March,,
2020
1.1.3 Addition of
ornamental features
through tree plantation
35% 2nd March,
2020
10th March,
2020
2nd March,
2020
8th March,
2020
1.2 House structure
1.2.1 Concrete 45% 27th
February,
2020
4th March,
2020
27th
February,
2020
14th March,
2020
1.2.2 Floor, slab and
roof structure
presentation
35% 16th March,
2020
24th May,
2020
16th March,
2020
20th May,
2020
1.2.3 Selecting best
construction tools
20% 16th March,
2020
28th May,
2020
16th March,
2020
25th May,
2020
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT PLANNING
1.3 Inside work
1.3.1 Excavation and
PCC
40% 27th April,
2020
30th June,
2020
25th April,
2020
28th June,
2020
1.3.2 Installing tiles 42% 10th May,
2020
20th June 10th May,
2020
20th June
1.3.3 Complete drywall
and exterior design
32% 26th June
2020
25th July,
2020
18th June
2020
24th July,
2020
1.4 Infrastructure
1.4.1 Windows and
doors framing
42% 9th July,
2020
30th August,
2020
12th July,
2020
30th August,
2020
1.4.2 Painting and Tile
setting
25% 17th August,
2020
25th
September,
2020
20th August,
2020
28th
September,
2020
1.4.3 Plumbing and
electricity installation
23% 20th August,
2020
25th
September,
2020
21th August,
2020
30th
September,
2020
1.5 Management
1.5.1 Communication
management plan
30% 19th August,
2020
20th August,
2020
19th August,
2020
30th August,
2020
1.5.2 Human resource
management plan
45% 13th
September,
2020
28th
September,
2020
13th
September,
2020
30th
September,
2020
1.5.3 Quality 42% 17th 2nd 15th 2nd
1.3 Inside work
1.3.1 Excavation and
PCC
40% 27th April,
2020
30th June,
2020
25th April,
2020
28th June,
2020
1.3.2 Installing tiles 42% 10th May,
2020
20th June 10th May,
2020
20th June
1.3.3 Complete drywall
and exterior design
32% 26th June
2020
25th July,
2020
18th June
2020
24th July,
2020
1.4 Infrastructure
1.4.1 Windows and
doors framing
42% 9th July,
2020
30th August,
2020
12th July,
2020
30th August,
2020
1.4.2 Painting and Tile
setting
25% 17th August,
2020
25th
September,
2020
20th August,
2020
28th
September,
2020
1.4.3 Plumbing and
electricity installation
23% 20th August,
2020
25th
September,
2020
21th August,
2020
30th
September,
2020
1.5 Management
1.5.1 Communication
management plan
30% 19th August,
2020
20th August,
2020
19th August,
2020
30th August,
2020
1.5.2 Human resource
management plan
45% 13th
September,
2020
28th
September,
2020
13th
September,
2020
30th
September,
2020
1.5.3 Quality 42% 17th 2nd 15th 2nd
5PROJECT MANAGEMENT PLANNING
management plan October,
2020
December October,
2020
December
1.6 Others
1.6.1 Inspection 35% 5th October,
2020
15th
December,
2020
5th October,
2020
15th
December,
2020
1.6.2 Milestone 1:
Completion of pre
construction and
construction stage
42% 19th March,
2020
2nd January,
2021
19th March,
2020
12th January,
2021
1.6.3 Milestone 2:
Completion of project
construction stage
20% 27th March,
2020
12th
February,
2021
27th March,
2020
10th
February,
2021
The project will be completed by 50% by the end of August, 2020. If all the other
activities are successfully followed then, the project will meet the expected objective within
April, 2021.
A project schedule is presented and in order to accomplish the project no such major
challenges are anticipated.
It is learned that, for properly constructing the dream home project contractors and sub
contractors need to maintain the knowledge areas accurately.
management plan October,
2020
December October,
2020
December
1.6 Others
1.6.1 Inspection 35% 5th October,
2020
15th
December,
2020
5th October,
2020
15th
December,
2020
1.6.2 Milestone 1:
Completion of pre
construction and
construction stage
42% 19th March,
2020
2nd January,
2021
19th March,
2020
12th January,
2021
1.6.3 Milestone 2:
Completion of project
construction stage
20% 27th March,
2020
12th
February,
2021
27th March,
2020
10th
February,
2021
The project will be completed by 50% by the end of August, 2020. If all the other
activities are successfully followed then, the project will meet the expected objective within
April, 2021.
A project schedule is presented and in order to accomplish the project no such major
challenges are anticipated.
It is learned that, for properly constructing the dream home project contractors and sub
contractors need to maintain the knowledge areas accurately.
6PROJECT MANAGEMENT PLANNING
Earned values report
'20 '20 '20 '20 '20
$0.00
$10,000.00
$20,000.00
$30,000.00
$40,000.00
$50,000.00
$60,000.00
$70,000.00
ACWP BCWP BCWS
Figure 2: Earned value report for the dream house construction project
(Source: Created by author)
Projection
Cost Performance Index (CPI)
Task Name
Planned
Value - PV
(BCWS)
Earned Value
- EV (BCWP) CPI BAC EAC VAC
Dream home construction
project construction $58,992.00 $47,920.00 1 $278,192.00 $278,194.30 ($2.30)
1.1 Landscaping $22,352.00 $11,960.00 1 $25,296.00 $25,296.00 $0.00
1.1.1 Site selection Site
supervision and government
permission
$20,400.00 $10,200.00 1 $20,400.00 $20,400.00 $0.00
1.1.2 Feasibility analysis $480.00 $288.00 1 $480.00 $480.00 $0.00
Earned values report
'20 '20 '20 '20 '20
$0.00
$10,000.00
$20,000.00
$30,000.00
$40,000.00
$50,000.00
$60,000.00
$70,000.00
ACWP BCWP BCWS
Figure 2: Earned value report for the dream house construction project
(Source: Created by author)
Projection
Cost Performance Index (CPI)
Task Name
Planned
Value - PV
(BCWS)
Earned Value
- EV (BCWP) CPI BAC EAC VAC
Dream home construction
project construction $58,992.00 $47,920.00 1 $278,192.00 $278,194.30 ($2.30)
1.1 Landscaping $22,352.00 $11,960.00 1 $25,296.00 $25,296.00 $0.00
1.1.1 Site selection Site
supervision and government
permission
$20,400.00 $10,200.00 1 $20,400.00 $20,400.00 $0.00
1.1.2 Feasibility analysis $480.00 $288.00 1 $480.00 $480.00 $0.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT MANAGEMENT PLANNING
and timeline setup
1.1.3 Addition of
ornamental features through
tree plantation
$1,472.00 $1,472.00 1 $4,416.00 $4,416.00 $0.00
1.2 House structure $2,720.00 $2,040.00 1 $13,064.00 $13,064.00 $0.00
1.2.1 Concrete $2,720.00 $2,040.00 1 $3,400.00 $3,400.00 $0.00
1.2.2 Floor, slab and
roof structure presentation $0.00 $0.00 0 $7,680.00 $7,680.00 $0.00
1.2.3 Selecting best
construction tools $0.00 $0.00 0 $1,984.00 $1,984.00 $0.00
1.3 Inside work $33,920.00 $33,920.00 1 $89,360.00 $89,360.00 $0.00
1.3.1 Excavation and
PCC $33,920.00 $33,920.00 1 $33,920.00 $33,920.00 $0.00
1.3.2 Installing tiles $0.00 $0.00 0 $53,920.00 $53,920.00 $0.00
1.3.3 Complete drywall
and exterior design $0.00 $0.00 0 $1,520.00 $1,520.00 $0.00
1.4 Infrastructure $0.00 $0.00 0 $29,400.00 $29,400.00 $0.00
1.4.1 Windows and
doors framing $0.00 $0.00 0 $2,400.00 $2,400.00 $0.00
1.4.2 Painting cost $0.00 $0.00 0 $12,000.00 $12,000.00 $0.00
1.4.3 Plumbing and
electricity installation $0.00 $0.00 0 $15,000.00 $15,000.00 $0.00
1.5 Management $0.00 $0.00 0 $120,000.00 $120,000.00 $0.00
1.5.1 Communication
management plan $0.00 $0.00 0 $40,000.00 $40,000.00 $0.00
1.5.2 Human resource
management plan $0.00 $0.00 0 $40,000.00 $40,000.00 $0.00
1.5.3 Quality
management plan $0.00 $0.00 0 $40,000.00 $40,000.00 $0.00
and timeline setup
1.1.3 Addition of
ornamental features through
tree plantation
$1,472.00 $1,472.00 1 $4,416.00 $4,416.00 $0.00
1.2 House structure $2,720.00 $2,040.00 1 $13,064.00 $13,064.00 $0.00
1.2.1 Concrete $2,720.00 $2,040.00 1 $3,400.00 $3,400.00 $0.00
1.2.2 Floor, slab and
roof structure presentation $0.00 $0.00 0 $7,680.00 $7,680.00 $0.00
1.2.3 Selecting best
construction tools $0.00 $0.00 0 $1,984.00 $1,984.00 $0.00
1.3 Inside work $33,920.00 $33,920.00 1 $89,360.00 $89,360.00 $0.00
1.3.1 Excavation and
PCC $33,920.00 $33,920.00 1 $33,920.00 $33,920.00 $0.00
1.3.2 Installing tiles $0.00 $0.00 0 $53,920.00 $53,920.00 $0.00
1.3.3 Complete drywall
and exterior design $0.00 $0.00 0 $1,520.00 $1,520.00 $0.00
1.4 Infrastructure $0.00 $0.00 0 $29,400.00 $29,400.00 $0.00
1.4.1 Windows and
doors framing $0.00 $0.00 0 $2,400.00 $2,400.00 $0.00
1.4.2 Painting cost $0.00 $0.00 0 $12,000.00 $12,000.00 $0.00
1.4.3 Plumbing and
electricity installation $0.00 $0.00 0 $15,000.00 $15,000.00 $0.00
1.5 Management $0.00 $0.00 0 $120,000.00 $120,000.00 $0.00
1.5.1 Communication
management plan $0.00 $0.00 0 $40,000.00 $40,000.00 $0.00
1.5.2 Human resource
management plan $0.00 $0.00 0 $40,000.00 $40,000.00 $0.00
1.5.3 Quality
management plan $0.00 $0.00 0 $40,000.00 $40,000.00 $0.00
8PROJECT MANAGEMENT PLANNING
1.6 Others $0.00 $0.00 0 $1,072.00 $1,072.00 $0.00
1.6.1 Inspection $0.00 $0.00 0 $1,072.00 $1,072.00 $0.00
1.6.2 Milestone 1:
Completion of pre
construction and
construction stage
$0.00 $0.00 0 $0.00 $0.00 $0.00
1.6.3 Milestone 2:
Completion of post
construction stage
$0.00 $0.00 0 $0.00 $0.00 $0.00
Schedule Performance Index (SPI)
Task Name Planned Value -
PV (BCWS)
Earned
Value - EV
(BCWP)
SV SV% SPI
Dream home
construction project
construction
$58,992.00 $47,920.00 ($11,072.00) -19% 0.81
1.1 Landscaping $22,352.00 $11,960.00 ($10,392.00) -46% 0.54
1.1.1 Site selection
Site supervision and
government permission
$20,400.00 $10,200.00 ($10,200.00) -50% 0.5
1.1.2 Feasibility
analysis and timeline
setup
$480.00 $288.00 ($192.00) -40% 0.6
1.1.3 Addition of
ornamental features
through tree plantation
$1,472.00 $1,472.00 $0.00 0% 1
1.2 House structure $2,720.00 $2,040.00 ($680.00) -25% 0.75
1.6 Others $0.00 $0.00 0 $1,072.00 $1,072.00 $0.00
1.6.1 Inspection $0.00 $0.00 0 $1,072.00 $1,072.00 $0.00
1.6.2 Milestone 1:
Completion of pre
construction and
construction stage
$0.00 $0.00 0 $0.00 $0.00 $0.00
1.6.3 Milestone 2:
Completion of post
construction stage
$0.00 $0.00 0 $0.00 $0.00 $0.00
Schedule Performance Index (SPI)
Task Name Planned Value -
PV (BCWS)
Earned
Value - EV
(BCWP)
SV SV% SPI
Dream home
construction project
construction
$58,992.00 $47,920.00 ($11,072.00) -19% 0.81
1.1 Landscaping $22,352.00 $11,960.00 ($10,392.00) -46% 0.54
1.1.1 Site selection
Site supervision and
government permission
$20,400.00 $10,200.00 ($10,200.00) -50% 0.5
1.1.2 Feasibility
analysis and timeline
setup
$480.00 $288.00 ($192.00) -40% 0.6
1.1.3 Addition of
ornamental features
through tree plantation
$1,472.00 $1,472.00 $0.00 0% 1
1.2 House structure $2,720.00 $2,040.00 ($680.00) -25% 0.75
9PROJECT MANAGEMENT PLANNING
1.2.1 Concrete $2,720.00 $2,040.00 ($680.00) -25% 0.75
1.2.2 Floor, slab and
roof structure
presentation
$0.00 $0.00 $0.00 0% 0
1.2.3 Selecting best
construction tools $0.00 $0.00 $0.00 0% 0
1.3 Inside work $33,920.00 $33,920.00 $0.00 0% 1
1.3.1 Excavation and
PCC $33,920.00 $33,920.00 $0.00 0% 1
1.3.2 Installing tiles $0.00 $0.00 $0.00 0% 0
1.3.3 Complete
drywall and exterior
design
$0.00 $0.00 $0.00 0% 0
1.4 Infrastructure $0.00 $0.00 $0.00 0% 0
1.4.1 Windows and
doors framing $0.00 $0.00 $0.00 0% 0
1.4.2 Painting cost $0.00 $0.00 $0.00 0% 0
1.4.3 Plumbing and
electricity installation $0.00 $0.00 $0.00 0% 0
1.5 Management $0.00 $0.00 $0.00 0% 0
1.5.1 Communication
management plan $0.00 $0.00 $0.00 0% 0
1.5.2 Human resource
management plan $0.00 $0.00 $0.00 0% 0
1.5.3 Quality
management plan $0.00 $0.00 $0.00 0% 0
1.6 Others $0.00 $0.00 $0.00 0% 0
1.6.1 Inspection $0.00 $0.00 $0.00 0% 0
1.6.2 Milestone 1: $0.00 $0.00 $0.00 0% 0
1.2.1 Concrete $2,720.00 $2,040.00 ($680.00) -25% 0.75
1.2.2 Floor, slab and
roof structure
presentation
$0.00 $0.00 $0.00 0% 0
1.2.3 Selecting best
construction tools $0.00 $0.00 $0.00 0% 0
1.3 Inside work $33,920.00 $33,920.00 $0.00 0% 1
1.3.1 Excavation and
PCC $33,920.00 $33,920.00 $0.00 0% 1
1.3.2 Installing tiles $0.00 $0.00 $0.00 0% 0
1.3.3 Complete
drywall and exterior
design
$0.00 $0.00 $0.00 0% 0
1.4 Infrastructure $0.00 $0.00 $0.00 0% 0
1.4.1 Windows and
doors framing $0.00 $0.00 $0.00 0% 0
1.4.2 Painting cost $0.00 $0.00 $0.00 0% 0
1.4.3 Plumbing and
electricity installation $0.00 $0.00 $0.00 0% 0
1.5 Management $0.00 $0.00 $0.00 0% 0
1.5.1 Communication
management plan $0.00 $0.00 $0.00 0% 0
1.5.2 Human resource
management plan $0.00 $0.00 $0.00 0% 0
1.5.3 Quality
management plan $0.00 $0.00 $0.00 0% 0
1.6 Others $0.00 $0.00 $0.00 0% 0
1.6.1 Inspection $0.00 $0.00 $0.00 0% 0
1.6.2 Milestone 1: $0.00 $0.00 $0.00 0% 0
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT PLANNING
Completion of pre
construction and
construction stage
1.6.3 Milestone 2:
Completion of post
construction stage
$0.00 $0.00 $0.00 0% 0
The value of estimated at completion is elaborated in the below section:
Task Name
Planned
Value -
PV
(BCWS)
Earned
Value -
EV
(BCWP)
AC
(ACWP) SV CV EAC BAC VAC
Dream home
construction
project
construction
$58,992.0
0
$47,920.0
0
$47,920.0
0
($11,072.00
)
$0.0
0
$278,194.3
0
$278,192.0
0
($2.30
)
1.1
Landscaping
$22,352.0
0
$11,960.0
0
$11,960.0
0
($10,392.00
)
$0.0
0 $25,296.00 $25,296.00 $0.00
1.1.1 Site
selection Site
supervision
and
government
permission
$20,400.0
0
$10,200.0
0
$10,200.0
0
($10,200.00
)
$0.0
0 $20,400.00 $20,400.00 $0.00
1.1.2
Feasibility
analysis and
timeline setup
$480.00 $288.00 $288.00 ($192.00) $0.0
0 $480.00 $480.00 $0.00
1.1.3
Addition of
ornamental
features
through tree
plantation
$1,472.00 $1,472.00 $1,472.00 $0.00 $0.0
0 $4,416.00 $4,416.00 $0.00
1.2 House
structure $2,720.00 $2,040.00 $2,040.00 ($680.00) $0.0
0 $13,064.00 $13,064.00 $0.00
1.2.1
Concrete $2,720.00 $2,040.00 $2,040.00 ($680.00) $0.0
0 $3,400.00 $3,400.00 $0.00
Completion of pre
construction and
construction stage
1.6.3 Milestone 2:
Completion of post
construction stage
$0.00 $0.00 $0.00 0% 0
The value of estimated at completion is elaborated in the below section:
Task Name
Planned
Value -
PV
(BCWS)
Earned
Value -
EV
(BCWP)
AC
(ACWP) SV CV EAC BAC VAC
Dream home
construction
project
construction
$58,992.0
0
$47,920.0
0
$47,920.0
0
($11,072.00
)
$0.0
0
$278,194.3
0
$278,192.0
0
($2.30
)
1.1
Landscaping
$22,352.0
0
$11,960.0
0
$11,960.0
0
($10,392.00
)
$0.0
0 $25,296.00 $25,296.00 $0.00
1.1.1 Site
selection Site
supervision
and
government
permission
$20,400.0
0
$10,200.0
0
$10,200.0
0
($10,200.00
)
$0.0
0 $20,400.00 $20,400.00 $0.00
1.1.2
Feasibility
analysis and
timeline setup
$480.00 $288.00 $288.00 ($192.00) $0.0
0 $480.00 $480.00 $0.00
1.1.3
Addition of
ornamental
features
through tree
plantation
$1,472.00 $1,472.00 $1,472.00 $0.00 $0.0
0 $4,416.00 $4,416.00 $0.00
1.2 House
structure $2,720.00 $2,040.00 $2,040.00 ($680.00) $0.0
0 $13,064.00 $13,064.00 $0.00
1.2.1
Concrete $2,720.00 $2,040.00 $2,040.00 ($680.00) $0.0
0 $3,400.00 $3,400.00 $0.00
11PROJECT MANAGEMENT PLANNING
1.2.2
Floor, slab and
roof structure
presentation
$0.00 $0.00 $0.00 $0.00 $0.0
0 $7,680.00 $7,680.00 $0.00
1.2.3
Selecting best
construction
tools
$0.00 $0.00 $0.00 $0.00 $0.0
0 $1,984.00 $1,984.00 $0.00
1.3 Inside
work
$33,920.0
0
$33,920.0
0
$33,920.0
0 $0.00 $0.0
0 $89,360.00 $89,360.00 $0.00
1.3.1
Excavation
and PCC
$33,920.0
0
$33,920.0
0
$33,920.0
0 $0.00 $0.0
0 $33,920.00 $33,920.00 $0.00
1.3.2
Installing tiles $0.00 $0.00 $0.00 $0.00 $0.0
0 $53,920.00 $53,920.00 $0.00
1.3.3
Complete
drywall and
exterior design
$0.00 $0.00 $0.00 $0.00 $0.0
0 $1,520.00 $1,520.00 $0.00
1.4
Infrastructur
e
$0.00 $0.00 $0.00 $0.00 $0.0
0 $29,400.00 $29,400.00 $0.00
1.4.1
Windows and
doors framing
$0.00 $0.00 $0.00 $0.00 $0.0
0 $2,400.00 $2,400.00 $0.00
1.4.2
Painting cost $0.00 $0.00 $0.00 $0.00 $0.0
0 $12,000.00 $12,000.00 $0.00
1.4.3
Plumbing and
electricity
installation
$0.00 $0.00 $0.00 $0.00 $0.0
0 $15,000.00 $15,000.00 $0.00
1.5
Management $0.00 $0.00 $0.00 $0.00 $0.0
0
$120,000.0
0
$120,000.0
0 $0.00
1.5.1
Communicatio
n management
plan
$0.00 $0.00 $0.00 $0.00 $0.0
0 $40,000.00 $40,000.00 $0.00
1.5.2
Human
resource
management
plan
$0.00 $0.00 $0.00 $0.00 $0.0
0 $40,000.00 $40,000.00 $0.00
1.5.3
Quality
$0.00 $0.00 $0.00 $0.00 $0.0
0
$40,000.00 $40,000.00 $0.00
1.2.2
Floor, slab and
roof structure
presentation
$0.00 $0.00 $0.00 $0.00 $0.0
0 $7,680.00 $7,680.00 $0.00
1.2.3
Selecting best
construction
tools
$0.00 $0.00 $0.00 $0.00 $0.0
0 $1,984.00 $1,984.00 $0.00
1.3 Inside
work
$33,920.0
0
$33,920.0
0
$33,920.0
0 $0.00 $0.0
0 $89,360.00 $89,360.00 $0.00
1.3.1
Excavation
and PCC
$33,920.0
0
$33,920.0
0
$33,920.0
0 $0.00 $0.0
0 $33,920.00 $33,920.00 $0.00
1.3.2
Installing tiles $0.00 $0.00 $0.00 $0.00 $0.0
0 $53,920.00 $53,920.00 $0.00
1.3.3
Complete
drywall and
exterior design
$0.00 $0.00 $0.00 $0.00 $0.0
0 $1,520.00 $1,520.00 $0.00
1.4
Infrastructur
e
$0.00 $0.00 $0.00 $0.00 $0.0
0 $29,400.00 $29,400.00 $0.00
1.4.1
Windows and
doors framing
$0.00 $0.00 $0.00 $0.00 $0.0
0 $2,400.00 $2,400.00 $0.00
1.4.2
Painting cost $0.00 $0.00 $0.00 $0.00 $0.0
0 $12,000.00 $12,000.00 $0.00
1.4.3
Plumbing and
electricity
installation
$0.00 $0.00 $0.00 $0.00 $0.0
0 $15,000.00 $15,000.00 $0.00
1.5
Management $0.00 $0.00 $0.00 $0.00 $0.0
0
$120,000.0
0
$120,000.0
0 $0.00
1.5.1
Communicatio
n management
plan
$0.00 $0.00 $0.00 $0.00 $0.0
0 $40,000.00 $40,000.00 $0.00
1.5.2
Human
resource
management
plan
$0.00 $0.00 $0.00 $0.00 $0.0
0 $40,000.00 $40,000.00 $0.00
1.5.3
Quality
$0.00 $0.00 $0.00 $0.00 $0.0
0
$40,000.00 $40,000.00 $0.00
12PROJECT MANAGEMENT PLANNING
management
plan
1.6 Others $0.00 $0.00 $0.00 $0.00 $0.0
0 $1,072.00 $1,072.00 $0.00
1.6.1
Inspection $0.00 $0.00 $0.00 $0.00 $0.0
0 $1,072.00 $1,072.00 $0.00
1.6.2
Milestone 1:
Completion of
pre
construction
and
construction
stage
$0.00 $0.00 $0.00 $0.00 $0.0
0 $0.00 $0.00 $0.00
1.6.3
Milestone 2:
Completion of
post
construction
stage
$0.00 $0.00 $0.00 $0.00 $0.0
0 $0.00 $0.00 $0.00
management
plan
1.6 Others $0.00 $0.00 $0.00 $0.00 $0.0
0 $1,072.00 $1,072.00 $0.00
1.6.1
Inspection $0.00 $0.00 $0.00 $0.00 $0.0
0 $1,072.00 $1,072.00 $0.00
1.6.2
Milestone 1:
Completion of
pre
construction
and
construction
stage
$0.00 $0.00 $0.00 $0.00 $0.0
0 $0.00 $0.00 $0.00
1.6.3
Milestone 2:
Completion of
post
construction
stage
$0.00 $0.00 $0.00 $0.00 $0.0
0 $0.00 $0.00 $0.00
1 out of 13
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.