This project charter outlines the details, scope, goals, budget, and schedule for the development of a streaming media player system by Soliloquy Publishing Ltd.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running Head: PROJECT CHARTER Project Charter: Streaming Media Player System Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT CHARTER Table of Contents 1.0 Project Details............................................................................................................................2 1.1 Project Title...........................................................................................................................2 1.2 Project Authorization Date....................................................................................................2 1.3 Start and Finish Date.............................................................................................................2 2.0 Project Manager Details............................................................................................................2 2.1 Name of Project Manager......................................................................................................2 2.2 Contact Details.......................................................................................................................2 3.0 Mission, Vision, Goals..............................................................................................................2 3.1 Mission of the Organization..................................................................................................2 3.2 Vision Statement....................................................................................................................3 3.3 Goals and Objectives.............................................................................................................3 4.0 Project Scope.............................................................................................................................4 4.1 Project Scope Statement........................................................................................................4 4.2 Project Assumptions..............................................................................................................4 4.3 Project Constraints.................................................................................................................5 5.0 Success Criteria.........................................................................................................................5 6.0 Summary Budget.......................................................................................................................6 7.0 Summary Schedule....................................................................................................................6 7.1 Start and End Dates for Each Sprint......................................................................................6 7.2 Objectives, Deliverables and Milestones...............................................................................9 8.0 Summary of Project Management Methodology.....................................................................12 9.0 Governance..............................................................................................................................12 10.0 Roles and Responsibilities.....................................................................................................12 11.0 Project Sign Off for Stakeholders..........................................................................................13 Bibliography..................................................................................................................................14
2PROJECT CHARTER 1.0 Project Details 1.1 Project Title Soliloquy Publishing Ltd. – Streaming Media Player System 1.2 Project Authorization Date The project has been authorized on 10/04/2018. 1.3 Start and Finish Date Start Date: 30/04/2018 Finish Date: 01/11/2018 2.0 Project Manager Details 2.1 Name of Project Manager PLEASE FILL 2.2 Contact Details PLEASE FILL 3.0 Mission, Vision, Goals 3.1 Mission of the Organization The mission of the organization is to deliver a new system with extensive content and a new revenue system in which the clients will pay subscription fees for accessing contents. As per
3PROJECT CHARTER the mission, a new media database will be created and connected to the company website while a client application will be provided to the subscribers who will be able to access the contents through this application. If sufficient amount of client can be gained, the entire revenue structure of the company will grow resulting in the increase in annual profits. 3.2 Vision Statement The vision of the company is to enter online streaming market with the aim to provide the customers with high quality as well as informative contents at minimal subscription price. 3.3 Goals and Objectives The main goal of the company is to establish a client based application software through which, the clients will be able to access a huge variety of streaming and interactive contents given they have subscribed for the services. Through this system, the company will be able to gain revenue from the subscription prices taken from the clients. The objectives of the project are as follows. To develop a media server through which all video contents will be streamed To design and develop an online application through which the clients will be able subscribe and access the video contents To prepare and develop a subscription structure based on time period (monthly / yearly) To include an online payment feature in the application To test the accessibility of the application from different web browsers and smartphones To complete the project within a time period of 6 months
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT CHARTER To complete the project within a pre set budget of $700,000 4.0 Project Scope 4.1 Project Scope Statement As per the requirements of the project, there can be number of in scope and out scope items that are specified as follows. In Scope:- Development of the online application is within the scope of the project. Development of the media server is within the scope of the project. Preparation of subscription structure is within the scope of the project. Promotion of the application among the existing and projected customer bases is within the scope of the project. Contract signing with various media distributors is within the scope of the project. Out Scope:- Development of business strategy is out of scope of this project. Analysis of market and future predictions are out of scope of this project. 4.2 Project Assumptions In order to develop the project charter, a number of assumptions have been made that are as follows. It has been assumed that the allocated budget of $700,000 will be sufficient for the project.
5PROJECT CHARTER It has been assumed that the expended amount can be recovered within a time period of 2 years. It has been assumed that 6 months will be sufficient for the completion of the project. It has been assumed that all the necessary features and requirements can be incorporated within the system. 4.3 Project Constraints The constraints of the project are as follows. Although a cost benefit has been estimated from the project, chances of reaching such values are less due to a number of risk factors including lack of client interest, high competition in market and others. In spite of addition of the variety of features, the success of the project is not 100% ensured. There might be copyright and imaging rights issues if contents are streamed in the application without the prior permission of artists / content creators. 5.0 Success Criteria There is a number of success criteria for the project that will be evaluated based on a time period of one to two years after the completion of the project. The success criteria for the project are listed as follows. All the features proposed in the meeting have been incorporated within the developed system.
6PROJECT CHARTER The system is running according to the plan and the clients are able to subscribe to the services easily. The investment is recovered within a time period of 2 years. There is sufficient cost benefit achieved from the project. The client base is increased by at least 50% at the end of the first year after completion of project. 6.0 Summary Budget The summary budget for the project is shown in the following table. ResourceEstimated Cost Hardware for Developers$50,000 Software for Developers$100,000 Stakeholder Wages$250,000 Developer Costs$150,000 Consultancy Costs$50,000 Licensing and Other Costs$100,000 TOTAL$700,000 7.0 Summary Schedule 7.1 Start and End Dates for Each Sprint The start and end dates for each sprint of the project are shown in the following table. Task NameDurationStartFinish
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT CHARTER Development of Online Streaming Media Player 134 daysMon 4/30/18Thu 11/1/18 Project Planning10 daysMon 4/30/18Fri 5/11/18 Survey of Current Business System 2 daysMon 4/30/18Tue 5/1/18 Board Meeting1 dayWed 5/2/18Wed 5/2/18 Determination of Mission and Vision 2 daysThu 5/3/18Fri 5/4/18 Prepare Project Plan4 daysMon 5/7/18Thu 5/10/18 Authorization of the Project1 dayFri 5/11/18Fri 5/11/18 Project Initiation17 daysMon 5/14/18Tue 6/5/18 Appoint Stakeholders for Project2 daysMon 5/14/18Tue 5/15/18 Develop Project Charter5 daysWed 5/16/18Tue 5/22/18 Determine Project Scope1 dayWed 5/23/18Wed 5/23/18 Create List of Deliverables1 dayThu 5/24/18Thu 5/24/18 Make Assumptions1 dayFri 5/25/18Fri 5/25/18
8PROJECT CHARTER Evaluate Constraints1 dayMon 5/28/18Mon 5/28/18 Develop Project Schedule2 daysTue 5/29/18Wed 5/30/18 Estimate Project Budget3 daysThu 5/31/18Mon 6/4/18 Approval of Project Plan1 dayTue 6/5/18Tue 6/5/18 Project Execution96 daysWed 6/6/18Wed 10/17/18 Assign Roles to Stakeholders2 daysWed 6/6/18Thu 6/7/18 Hire Developers4 daysFri 6/8/18Wed 6/13/18 Procure Budget for Project2 daysThu 6/14/18Fri 6/15/18 Initiate Development1 dayMon 6/18/18Mon 6/18/18 Prepare List of Features to be Added 2 daysTue 6/19/18Wed 6/20/18 Develop Media Database20 daysThu 6/21/18Wed 7/18/18 Add All Required Features15 daysThu 7/19/18Wed 8/8/18 Develop Client Application30 daysThu 8/9/18Wed 9/19/18 ConnectApplicationwith Database 5 daysThu 9/20/18Wed 9/26/18 Run the System2 daysThu 9/27/18Fri 9/28/18
9PROJECT CHARTER Analyze Errors2 daysMon 10/1/18Tue 10/2/18 Address Errors4 daysWed 10/3/18Mon 10/8/18 Risk Management4 daysTue 10/9/18Fri 10/12/18 Final Testing2 daysMon 10/15/18Tue 10/16/18 Project Handover1 dayWed 10/17/18Wed 10/17/18 Project Closing11 daysThu 10/18/18Thu 11/1/18 Review of Project5 daysThu 10/18/18Wed 10/24/18 Appraisal2 daysThu 10/25/18Fri 10/26/18 Approval of Project Report2 daysMon 10/29/18Tue 10/30/18 Stakeholder Sign Off1 dayWed 10/31/18Wed 10/31/18 Official Closing1 dayThu 11/1/18Thu 11/1/18 7.2 Objectives, Deliverables and Milestones The objectives of the project that must be fulfilled are shown in the following work breakdown structure.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT CHARTER Figure 1: Work Breakdown Structure Showing Objectives of Project (Source: Created by Author) The deliverables and milestones of the project including the proposed schedule for each sprint are shown in the following Gantt chart.
11PROJECT CHARTER Figure 2: Gantt Chart Showing Milestones and Deliverables (Source: Created by Author)
12PROJECT CHARTER 8.0 Summary of Project Management Methodology The project management methodology to be followed for the project is Agile Scrum PM Methodology. This methodology framework will perfectly fit the requirements of the project as it will follow a specific execution structure as mentioned in Scrum method. Before starting the project, Scrum will allow the organization to develop a vision statement and a set of project goals and objectives. Based on these specifications, the project sprints will be determined within a fixed set of timeline. Within this timeline, the project sprints will be executed and then evaluated for further changes and additional requirements. 9.0 Governance The project will have a suitable governance structure that will require the stakeholders of the project to manage and govern different aspects of the project. There are four main stakeholders of the project, namely the project manager, promoter, chief financial officer and chief information officer. Since their duties are allocated in different aspects of the project, they also need to govern these aspects so that the project does not go out of scope or any problems and issues can be promptly addressed and solved. 10.0 Roles and Responsibilities The roles and responsibilities of the stakeholder in the project are as follows. Stakeholder NameDesignationDuty PLEASE FILLProject ManagerPreparationofcharter, management of entire project Tristan BardMain Promoter / SupporterApproval of project, promotion
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13PROJECT CHARTER of project Elijah Z. MoneyChief Financial OfficerManagement of project funds Ignatius T. ShoppeChief Information OfficerBusinessanalytics,providing suggestions regarding the system 11.0 Project Sign Off for Stakeholders The project charter has been reviewed and found to be according to the proposed plan. ______________________________ (Project Manager) ______________________________ (Promoter) ______________________________ (Chief Financial Officer) ______________________________ (Chief Information Officer)
14PROJECT CHARTER Bibliography Binder, J. (2016).Global project management: communication, collaboration and management across borders. Routledge. Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014).Peer learning in higher education: Learning from and with each other. Routledge. Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute. Harrison,F.,&Lock,D.(2017).Advancedprojectmanagement:astructuredapproach. Routledge. Heagney, J. (2016).Fundamentals of project management. AMACOM Div American Mgmt Assn. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Schwalbe, K. (2015).Information technology project management. Cengage Learning. Turner, R. (2016).Gower handbook of project management. Routledge. Verzuh, E. (2015).The fast forward MBA in project management. John Wiley & Sons. Walker, A. (2015).Project management in construction. John Wiley & Sons.